AI Puts Fiber on the Critical Path

Fiber Becomes Part of the Build A decade ago, DC Blox might have prioritized land near existing fiber from AT&T, Verizon, Zayo or another established network provider. That calculation is different today. As data center campuses have grown and hyperscalers have become a larger share of the customer base, Wabik said connectivity has increasingly become […]

Fiber Becomes Part of the Build

A decade ago, DC Blox might have prioritized land near existing fiber from AT&T, Verizon, Zayo or another established network provider. That calculation is different today. As data center campuses have grown and hyperscalers have become a larger share of the customer base, Wabik said connectivity has increasingly become another construction package associated with the project itself.

“If Zayo or Verizon or AT&T just happens to be there close by, that’s a good thing,” he said. “But fiber construction is inherently anymore just part of the construction component.”

That changes the site-selection question from Is there fiber nearby? to Can fiber be built here at the scale and diversity the customer requires? For DC Blox, Wabik said that can mean assessing whether sufficient public right-of-way exists to establish three or sometimes four diverse fiber paths into a data center.

That distinction is important, as AI workloads push infrastructure into markets where power, land and energy options may be more abundant than established carrier density. The hyperscalers themselves have also become major network builders.

Wabik characterized them provocatively as today’s telecom providers, pointing to the scale of terrestrial fiber they commission as well as the growing role of companies such as Amazon, Google and Meta in subsea cable development. The point is less that traditional carriers have disappeared than that hyperscalers increasingly design, commission and control enormous portions of the connectivity required to support their own infrastructure.

DC Blox now sees requests for 864-count fiber as routine and, in some cases, 1,728-count cable. That would have been difficult to imagine during an earlier era when a handful of fibers from an established carrier could satisfy a data center’s connectivity requirements.

AI-Scale Fiber Gets Physical

The scale becomes clearer when the discussion moves from abstract network capacity to what actually has to be put into the ground. Wabik said 864-count fiber is now about the smallest deployment DC Blox commonly sees. And the company is no longer designing conduit systems around the assumption that a modest amount of spare capacity will remain adequate for decades.

A few years ago, Wabik said, installing a handful of ducts during an initial build might have seemed sufficient for the next 20 years. Today, his minimum expectation is closer to 10 ducts, and sometimes 14. “I’ll put an 864 in it, I’ve got nine ducts left,” he said. “Who knows what’s coming and when it’s coming?” Sometimes the answer arrives almost immediately.

Wabik said a customer may request another 864-count cable before crews have completed the first installation. The second and third ducts can begin filling while the original construction effort is still underway. The density is equally striking inside hyperscale network facilities. Wabik described 10,000- to 20,000-square-foot network nodes containing hundreds of thousands of fiber splices, with equipment physically interconnected through an enormous web of fiber.

That scale mirrors what data center developers are seeing elsewhere in AI infrastructure. Wabik recalled hyperscaler requirements moving rapidly from 25 kW per cabinet to 35 kW and then 50 kW over a matter of weeks. The precise requirements can continue evolving while the underlying facility is being planned.

DC Blox’s job, he noted, is to provide the building, power, cooling and connectivity infrastructure around customer equipment whose final configuration may continue changing as deployment approaches. The same uncertainty encourages aggressive fiber over-provisioning. It is difficult to know exactly what the next requirement will be. The response is to create enough physical pathways to accommodate it.

“It’s just a massive buildout,” Wabik said. His shorthand for the moment is “beautiful insanity.”

Building a Connectivity Ecosystem

The result is something larger than a collection of point-to-point fiber routes. AI-scale campuses are becoming nodes inside increasingly dense connectivity ecosystems. DC Blox may construct fiber between hyperscale buildings, between campuses or into major network hubs. A customer can then ask the company to connect that newly built network with other fiber providers at multiple points along the route.

Those connections can require a series of intercepts and splices so the customer’s network can meet other networks at six or seven locations along a corridor. The picture that emerges is closer to a mesh than a traditional pair of routes entering a building. For hyperscalers, the ability to create that mesh is becoming part of the infrastructure equation from the beginning. But there is an important wrinkle in any discussion of fiber as a bottleneck.

Wabik does not see raw fiber deployment capacity as the obvious choke point. The industry is responding to demand by building at extraordinary scale. The harder problem often comes earlier. Before fiber can be placed, somebody has to grant permission to put it there.

The Hidden Constraint Is Permitting

When Data Center Frontier asked whether connectivity can keep pace when a developer finds large quantities of power, Wabik described data center development as a complicated choreography. Land has to be graded. Substations have to be built. Underground conduit has to be installed. Buildings have to rise. Metro and long-haul connectivity has to reach the campus. If any critical component misses the required date, the facility cannot operate as intended.

On the fiber side, Wabik said the hardest part is usually neither trenching nor horizontal boring. It is permitting. DC Blox has developed a roughly 475-mile route between Myrtle Beach, South Carolina, and Atlanta. Along a route of that length, fiber passes through numerous cities and counties, each potentially requiring its own equivalent of a building permit. Construction productivity can be measured. Crews can bore a certain number of feet per day and install a certain amount of fiber. A permit does not move according to the same clock. “Getting those permits is really the challenge,” Wabik said.

That has become important enough to affect routing decisions. If DC Blox knows a particular county previously took a year to approve a permit and became the long pole in a project schedule, Wabik said the company may simply route the next fiber build around that jurisdiction. That is a consequential development for an industry that usually discusses permitting primarily in connection with the data center campus itself. Permitting history can now influence the geography of the network connecting that campus.

A recent DC Blox metro Atlanta project illustrates the problem. Wabik said the company built roughly 55 miles of fiber to create a ring around the market. Most permits arrived during approximately the first two months of a 12-month construction window. Some did not. Several came in at what Wabik described as “right at the wire,” after months of follow-up with local jurisdictions.

Other infrastructure crossings make the process more complicated still. A bridge attachment can bring a highway department into the approval process. A river crossing may involve the U.S. Army Corps of Engineers. A railroad crossing introduces another third party with its own requirements and timetable. Wabik said DC Blox has seen individual segment permits take a year or, in some cases, 18 months.

The construction sequence then becomes an exercise in completing everything that can be built while waiting for the last approvals to land. Sending a crew home creates another problem. “If they have to go home, we have to remobilize them,” Wabik said. “That’s just a huge cost we really try to avoid.”

Fiber Supply Tightens Again

Permission to build is only one side of the problem. The physical supply chain has tightened again as well. Wabik said equipment lead times stretched dramatically during the COVID-era supply-chain disruptions, then eased during 2023 and 2024. Some fiber-related components returned to lead times measured in weeks.

That respite did not last. If DC Blox looks for 864-count or 1,728-count fiber today, Wabik said the lead time can reach 70 to 80 weeks when buying at what he considers normal market pricing. For an 864-count microfiber of approximately 10 or 11 millimeters in outside diameter, he said he would expect pricing around $7 to $7.50 per foot.

Inventory can be found more quickly for buyers willing to pay. Wabik said fiber sitting in available inventory may trade for $10, $12 or even $14 per foot when a project urgently needs material. The same pressure extends beyond connectivity. Large generators used for secondary data center power can also carry lead times in the 12- to 18-month range.

The challenge, therefore, is not simply obtaining one scarce component. Developers are coordinating a collection of long-lead systems whose delivery schedules have to converge on the same campus.

The Workforce Behind the AI Build

The physical scale of the build is also creating demand for people far beyond the AI software workforce that tends to dominate public discussion. Wabik pointed to real estate professionals locating land, specialists who understand how to work with utilities, construction crews grading enormous sites, plumbers, electricians, fiber technicians and the operating personnel required once hyperscale facilities come online.

Some large campuses can involve thousands of workers across the construction cycle. The constraint is increasingly visible in skilled trades. “There’s a shortage of electricians in the world right now,” Wabik said. Operations presents another challenge. Hyperscale facilities can contain hundreds of thousands of square feet of white space, requiring personnel capable of maintaining increasingly large and technically demanding environments.

In other words, the AI infrastructure build is creating a workforce requirement far broader than model development or semiconductor engineering. The servers only function after someone finds the land, secures the power, pours the foundations, installs the electrical infrastructure and connects the fiber.

Community Acceptance Enters the Critical Path

Another requirement has moved much earlier in the development cycle: community engagement. Wabik remembers an era when data center developers could enter communities with relatively little controversy, particularly when projects replaced distressed industrial assets.

A developer might acquire a former steel mill, remove an abandoned facility, remediate contaminated soil and introduce new investment. The current environment is markedly different. Community concerns around power consumption, water use, noise and environmental impacts have become central development issues in many markets.

Wabik argues that some of those concerns are driven by incorrect or overly broad assumptions about how individual facilities operate. He points to DC Blox’s own cooling architecture as one example. The company’s closed-loop systems may require roughly 500,000 gallons of water during commissioning, he said, with that water then recirculated rather than continuously consumed. He contrasted that design with facilities using evaporative cooling, which can have materially different water requirements.

The broader lesson for DC Blox has been that developers cannot assume communities understand those distinctions. The company is moving stakeholder engagement earlier and providing more detailed information about projects before construction. That can include expected sound levels, water consumption, environmental impacts, job creation and anticipated tax contributions.

Wabik noted that a large data center campus may represent several billion dollars of taxable property, along with business personal property inside the buildings. In some jurisdictions, a data center can become one of the largest individual taxpayers. Over a facility life that may extend 20, 40 or 50 years, he said the resulting tax contribution can reach hundreds of millions of dollars.

DC Blox increasingly sees communicating that complete project profile as part of development itself. That does not eliminate legitimate community questions about power, land, water or development policy. It does mean that the technical design of a project and the public understanding of that design can no longer be treated as separate exercises.

Everything Has to Arrive Together

The AI infrastructure boom has made power the dominant site-selection constraint for good reason. Without electricity, nothing else matters. But Wabik’s view from the fiber side shows why the next generation of development cannot be reduced to a single-variable search for megawatts.

Once the power is found, the network has to reach it. The right-of-way has to exist. The jurisdictions along the route have to approve construction. Fiber must be ordered far enough in advance. Crews have to be available when the permits arrive. Network paths have to multiply as customer requirements evolve. Communities have to understand what is being proposed before opposition hardens around assumptions that may or may not describe the actual project.

None of those requirements is particularly exotic on its own. What is new is their scale, their speed and the degree to which they are becoming interdependent. AI campuses are forcing developers to assemble power plants, substations, buildings, cooling systems, fiber networks and workforce ecosystems on timelines that increasingly overlap.

That may be the clearest meaning behind Wabik’s “beautiful insanity.” The fiber can follow the power. But power, connectivity, permits, equipment, labor and public acceptance increasingly have to arrive at nearly the same time.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Tool sprawl, AI complicate enterprise network operations

Enterprises can use AI to help correlate information and automate operations, but it doesn’t eliminate the need to address underlying operational problems. “AI can overcome data fragmentation across tools, but it’s not going to overcome bad data and bad operations in general,” McGillicuddy said. AI takes on more of the

Read More »

Energy Department Supports FERC’s Call for PJM to Protect Ratepayers and Build More Reliable Power

WASHINGTON—The U.S. Department of Energy (DOE) announced its support for the Federal Energy Regulatory Commission’s (FERC) guidance that would help ensure lower electricity costs for American families and businesses across the PJM Interconnection LLC’s (PJM) region spanning across the mid-Atlantic. DOE filed a Notice of Intervention and Statement of Position with FERC supporting its recommendation for PJM’s proposed Reliability Backstop Procurement. FERC recommends PJM submit revised tariff provisions to implement appropriate cost allocation and other reforms. FERC’s recommendations are consistent with President Trump’s Ratepayer Protection Pledge, ensuring large electricity users pay for the generation and infrastructure needed to serve them.  This action follows the Trump Administration’s call in January 2026 for PJM to adopt market rules to strengthen grid reliability and reduce electricity costs. Specifically, the Administration asked PJM to hold an emergency power auction and to accelerate the development of reliable power generation. The Trump administration was joined by governors from all 13 states who participate in the PJM grid. “The Trump Administration remains committed to doing everything it can to lower electricity costs, grow the supply of American energy and strengthen grid reliability,” said U.S. Secretary of Energy Chris Wright. “That’s why President Trump created the Ratepayer Protection Pledge, and the Energy Department supports having large electricity users pay for reliable new power generation.” “In January, the Trump Administration recognized early warning signs of capacity shortfalls in PJM and joined the Governors of all 13 PJM states in issuing a Statement of Principles to PJM, calling for PJM to adopt market rules to strengthen grid reliability and reduce electricity costs for American families and businesses,” said U.S. Deputy Secretary of Energy James P. Danly. “By increasing transparency and preventing unjust cost shifts onto existing customers, the proposed reforms advance President Trump’s Ratepayer Protection Pledge while ensuring Americans continue

Read More »

Shell agrees to acquire interest in Bay du Nord project

Shell plc and Equinor ASA have signed an agreement under which Shell will acquire a 30% interest in the Bay du Nord project offshore Newfoundland and Labrador in Canada. Equinor will retain a 70% interest and remain as the operator of the project. The transaction supports the continued maturation of Bay du Nord towards an investment decision currently targeted for early 2027, Equinor said. Bay du Nord is in Flemish Pass basin, about 500 km offshore Newfoundland and Labrador in 600–1,170 m of water. The development concept is based on a floating production, storage, and offloading vessel (FPSO). Bay du Nord and Cambriol discoveries are included in the initial phase, with potential future subsea tiebacks to Cappahayden, Harpoon, and Baccalieu. Estimated recoverable resources in the initial phase are more than 400 MMbbl of oil. First oil is anticipated in 2031, Equinor said. The project is currently finalizing front-end engineering and design (FEED), with continued work focused on strengthening capital efficiency, execution planning, and overall project robustness. Engagement with provincial and federal governments has supported progress through key milestones, according to the company. Equinor and Shell said they will continue to mature the project towards an investment decision subject to market conditions, regulatory approvals, and the companies’ internal decision processes. The project will require a toal investment of about $14 billion (Can.; US$12.6 billion), Equinor said.

Read More »

Dangote taps EIL for Kenya grassroots refinery project

Dangote Group has enlisted Engineers India Ltd. (EIL) to deliver project management and engineering, procurement, and construction management (EPCM) services for subsidiary Dangote East Africa Petroleum Refinery & Petrochemicals SEZ’s proposed 700,000-b/d grassroots integrated refinery and petrochemical complex to be built in Mokowe, Lamu County, Kenya. As part of the more than $450-million contract, EIL will serve as project management consultant (PMC) and EPCM consultant for the project, the service provider said in separate regulatory filings to BSE Ltd. and The National Stock Exchange of India Ltd. The proposed complex is planned near Lamu Port and the Lamu Port-South Sudan-Ethiopia Transport (LAPSSET) corridor, which will connect the site with inland and regional markets by providing a coastal location for importing construction materials and crude as well as exporting refined products. EIL said award of the PMC-EPCM consultancy contract for the Lamu refinery follows its previous role as PMC-EPCM consultant for Dangote Petroleum Refinery and Petrochemicals FZE (DPRP) 650,000-b/d refinery and petrochemical complex in the Lekki Free Zone near Lagos, Nigeria, which is currently being expanded to 1.4 million b/d. At a Sept. 30 groundbreaking ceremony for the Lamu refinery, Dangote described the $16-billion investment as a project aimed at expanding refined-product supply in East Africa that will serve markets both within and beyond Kenya. While the refinery will presumably process Kenya’s production of domestic crude such as volumes from South Lokichar basin—which could which could begin production before December 2026 at a rate of about 20,000 b/d—the integrated complex also will process crude sourced from other African producers, including Uganda, the African Export-Import Bank (Afreximbank) said in a release Oct. 1. Honeywell to license technologies The EIL contract joins a separate $300-million contract awarded to Honeywell Technologies for delivery process technology and related services at Lamu, including technology licensing, engineering

Read More »

Energy Department Announces New Genesis Mission Awards to Advance Super Intelligence for Science

WASHINGTON—The U.S. Department of Energy (DOE) today announced 12 Phase II Genesis Mission project awards totaling $159 million. Building on the Genesis Mission’s growing portfolio of projects, first announced in July, these Phase II project awards will unleash scientific discoveries with Super Intelligence (SI). President Trump launched the Genesis Mission in November 2025 to accelerate discovery and strengthen U.S. leadership in science, medicine, and technology. “These projects represent a critical step in turning the promise of Super Intelligence for science into transformative scientific capability,” said DOE Under Secretary for Science Dr. Darío Gil. “The Phase II teams have already demonstrated what is possible when SI is integrated with scientific expertise, data, and computing. These awards give them the opportunity to take that work to the next level. By bringing together our National Labs, universities, and industry partners, we are building on extraordinary work already underway and accelerating the pace of discovery.” The Phase II awards are developing new, powerful capabilities to tackle the Nation’s most complex National Science and Technology Challenges. By connecting America’s leading scientists with advanced SI, supercomputing, scientific data, and DOE’s world-class research infrastructure, the Genesis Mission is strengthening U.S. leadership at the frontiers of science and technology. Awarded Projects Through DOE’s Office of Science, the 12 newly awarded projects are: Accelerating the path to commercial fusion energy via an AI-enabled digital twin platform for SPARC: Led by Commonwealth Fusion Systems, this project will build a digital twin to simulate and optimize operations of a fusion demonstration device.  Decoding the RNA Structurome to Secure AI Advantage for the Bioeconomy: Led by the University of California San Diego, the project will expand the RNA structure database five-fold for training SI models to unlock the ability to engineer resilient crops and sustainable microbes.  Lattice Quantum Chromodynamics (LQCD) at the

Read More »

Energy Department Launches Genesis Mission Graduate Fellowship to Advance American Scientific Leadership

WASHINGTON—The U.S. Department of Energy (DOE) today announced the Genesis Mission Graduate Fellowship Pilot, a new funding opportunity designed to develop the next generation of American scientists and engineers and strengthen U.S. scientific leadership. Through accelerated, four-year doctoral pathways, the program will equip domestic graduate students with critical expertise in both Super Intelligence (SI) and core scientific and engineering disciplines. The inaugural fellowship advances President Trump’s historic Genesis Mission by investing in the education, development, and retention of domestic talent needed to accelerate U.S. scientific discovery and innovation. “To secure America’s position at the forefront of global scientific innovation, we must cultivate a workforce that is fluent in both foundational sciences and advanced Super Intelligence,” said DOE Under Secretary for Science Dr. Darío Gil. “The Genesis Mission Graduate Fellowship will bridge this critical gap by combining rigorous academic training with hands-on, high-impact experiences across our National Laboratories and industry partners.” DOE will fund an inaugural group of pilot projects led by domestic doctoral-granting institutions, supporting an initial cohort of approximately 100 Ph.D. fellows. As part of their four-year doctoral pathways, fellows will complete two high-impact, hands-on research experiences—one at a DOE National Laboratory or DOE User Facility and one with an industry partner—preparing them to lead the next generation of scientific discovery and innovation. Total planned funding is up to $100 million, with $20 million in Fiscal Year 2027, and outyear funding contingent on congressional appropriations. A webinar will be held on November 4, 2026, 4:00 PM ET. Register on Zoom. For more information, please visit the DOE Office of Science Funding Opportunities page.

Read More »

U.S. Department of Energy Awards $96 Million to 67 Early Career Scientists

WASHINGTON—The U.S. Department of Energy’s (DOE) Office of Science today announced the selection of 67 early career scientists to receive a combined $96 million through the 2026 Early Career Research Program (ECRP). Today’s announcement advances President Trump’s Executive Order Restoring Gold Standard Science by supporting exceptional researchers pursuing rigorous, mission-driven research in areas critical to America’s scientific and technological leadership, including Super Intelligence (SI), fusion energy, and quantum science. “Groundbreaking science begins with empowering extraordinary people,” said DOE Under Secretary for Science Dr. Darío Gil. “These 67 early career researchers represent the very best of American ingenuity. DOE is proud to invest in their vision as they push the boundaries of knowledge and cement U.S. leadership in the technologies that will define our century.” The 2026 Early Career Research Program (ECRP) selectees represent 39 universities, 11 DOE National Laboratories and Office of Science User Facilities, and 26 states. By investing in exceptional researchers at a pivotal stage in their careers, ECRP empowers the next generation of STEM leaders to pursue bold, innovative research that drives DOE’s mission and ensures America continues to lead the world in science and innovation. Since its inception in 2010, the program has made 1,238 awards, including 797 to university researchers and 441 to DOE National Laboratory researchers. Awards to scientists at institutions of higher education are approximately $875,000 over five years, while awards to scientists at DOE National Laboratories or Office of Science User Facilities are approximately $2,750,000 over five years. Information about the 67 selectees and their research projects is available on the Office of Science Awards page. Profiles of previous award recipients, including information about how the program helped advance their research and careers, are available on the Early Career Program profiles page. Selection for award negotiations is not a commitment by DOE

Read More »

DCF Global: Five Markets Redrawing the AI Infrastructure Map

The Global Constraint Is Execution These five markets demonstrate that the worldwide AI infrastructure buildout is no longer organized around a single development model. Spain is using permitting reform to attract investment. China is concentrating construction around energy resources. India is translating enormous capital commitments into an expanding development pipeline. Latin America is combining hyperscale growth with national industrial objectives. And Southeast Asia is creating interconnected infrastructure markets whose boundaries increasingly extend beyond individual cities and countries. Not every market is competing for the same business. Sovereign cloud services, enterprise applications, AI training clusters, and large-scale inference platforms carry different requirements involving power, connectivity, latency, data residency, and operating economics. But the infrastructure questions remain remarkably consistent. Can a project obtain enough electricity? Can transmission and supporting networks be delivered on schedule? Will the supply chain provide the required equipment? Can the facility be constructed and commissioned efficiently? And will the development retain the regulatory certainty and community acceptance required to operate for decades? The gap between announced development and actual capacity is becoming a defining measurement of the industry. Cushman & Wakefield estimates that Asia-Pacific alone had approximately 26.5 GW of data center capacity in its development pipeline during H1 2026. Of that total, roughly 4.8 GW was under construction, with another 21.7 GW in planning. Those figures reveal both the extraordinary scale of the opportunity and the considerable infrastructure work still required to realize it. What the Global Buildout Means for North America For U.S. data center operators, developers, engineering firms, equipment suppliers, and investors, international expansion is not a separate story. It is increasingly part of the same global competition for capital, equipment, power infrastructure, and specialized expertise. The transformers, switchgear, generators, advanced cooling systems, fiber networks, and electrical distribution equipment required by a major AI campus

Read More »

Bidding war over key component could eliminate third hard disk maker

What if the three remaining hard disk manufacturers became two? Seagate Technology and Western Digital control 90% of the market, according to market researcher TrendForce, with Toshiba picking up the crumbs. Seagate and WD both make their own magnetic drive heads, but Toshiba relies on a third party, TDK, which also sells to Seagate and WD when they need extra capacity. Seeking to guarantee supplies of this critical component, Toshiba made a bid for TDK’s drive head business earlier this year, according to Bloomberg. Concerned that this could affect its ability to meet the growing demand for hard disks from AI data centers, Seagate made a counteroffer, Bloomberg reported. TDK is staying mum.

Read More »

Oracle reportedly lands $7B GPU deal for Tencent

Oracle has reportedly signed a five-year, $7 billion agreement to provide Chinese technology conglomerate Tencent with access to roughly 100,000 advanced AI accelerators deployed in Oracle data centers across Southeast Asia, helping Tencent to sidestep restrictions on advanced AI equipment.  The deal, first reported by the Financial Times, would represent Tencent’s largest overseas cloud commitment with a U.S. provider. Neither Oracle nor Tencent has publicly confirmed the agreement or disclosed the specific AI processors involved. Under the reported terms, Tencent would pay about 30% of the contract value upfront—roughly $2.1 billion—with the remainder paid over the five-year term. That would give Oracle a substantial source of upfront funding for the expensive data center infrastructure required to build out the infrastructure.

Read More »

NVIDIA’s DSX Ready Brings Power and Cooling Into the AI Factory Blueprint

NVIDIA is extending its influence over AI infrastructure beyond the GPU, server rack and network, introducing qualification requirements for the power and cooling systems that increasingly determine the scale and performance of AI data centers. The company’s new NVIDIA DSX Ready program, announced September 21, establishes requirements for specific infrastructure products intended for use with NVIDIA’s DSX AI factory reference designs. Its first two categories—battery energy storage systems (BESS) and coolant distribution units (CDUs)—address two of the most pressing engineering challenges in AI infrastructure: managing rapidly changing electrical demand and removing heat from increasingly dense computing systems. The initial qualified suppliers are Hitachi Energy, LG Energy Solution and Tesla for battery storage, and LG Electronics, LiquidStack and Vertiv for liquid cooling. While the announcement might initially resemble another NVIDIA partner program, its technical details suggest something more consequential. The company is establishing performance criteria for the electrical and mechanical equipment supporting its computing platforms, connecting those requirements to an expanding ecosystem of qualified suppliers. Subsequent partner announcements offer a clearer view of what that means in practice. They describe battery systems designed to respond to AI load fluctuations, coolant distribution equipment operating at multi-megawatt capacities, and integrated cooling architectures intended to make more of a data center’s available power usable for computing. The initiative also coincides with the arrival of Chris Malone, formerly a data center infrastructure executive at OpenAI, Meta and Google, as NVIDIA’s vice president of the DSX Platform. Together, the developments point toward a closer relationship between computing architecture and facility engineering, with NVIDIA seeking to influence not only the processors deployed in AI factories but the infrastructure requirements that support their operation. From Reference Design to Infrastructure Qualification DSX Ready is an extension of the broader NVIDIA DSX AI Factory Platform, introduced in May 2026. As

Read More »

Brookfield’s AREP Deal Extends the AI Infrastructure Stack to Powered Land

The transaction goes beyond Brookfield investing in another portfolio of buildings. It is investing in a developer whose principal product increasingly begins before the building, with land, entitlements, substations, transmission access and utility capacity. PowerHouse Has Become a Gigawatt-Scale Development Platform PowerHouse was founded with a strong Northern Virginia orientation, but its development map now stretches well beyond Data Center Alley as its current portfolio includes projects in Virginia, Texas, Pennsylvania, North Carolina, Nevada, Indiana, Illinois and Kentucky. The company lists 515 MW across its Northern VA Ashburn properties, another 900 MW at its PH 95 development in Spotsylvania, 1.35 GW in Carlisle, Pennsylvania, 1.8 GW at Joliet, Illinois, and substantial campuses across multiple Texas and Indiana locations. The various projects do a good job of illustrating how the definition of a hyperscale development site is changing. At PowerHouse Arcola in Loudoun County, Virginia, PowerHouse announced a long-term hyperscale lease earlier this year. The 37-acre campus includes two planned data center buildings totaling approximately 615,000 square feet and is designed for up to 120 MW of utility capacity. PowerHouse emphasizes not only the buildings but the campus’s on-site substation, fiber access, power security and support for high-density GPU and liquid-cooled deployments. In Texas, it might be that everything really is bigger, and PowerHouse’s Grand Prairie development covers approximately 810 acres and 8.5 million developable square feet. Its project page cites maximum utility power of 1.8 GW and a development schedule extending through 2029 and beyond. The Texas development plans also include a proposed Circle T campus in Westlake outside Fort Worth, which calls for as many as four roughly 300,000-square-foot facilities totaling approximately 300 MW. According to reporting on local filings, PowerHouse has funded a 350-MW Oncor substation intended to serve the campus and the town’s pump station. The company’s development in

Read More »

AI Is Turning Energy Storage Into Active Power Infrastructure

AI Turns the Power Problem Into a Transient Problem At the heart of the issue is the changing behavior of the IT load. In a conventional data center, DeLattre said, large numbers of independent loads create a relatively predictable electrical profile. AI clusters introduce much greater synchronization. As GPUs begin processing a common workload, large numbers of accelerators can increase their power consumption simultaneously. Instead of asking the electrical infrastructure to serve a relatively smooth load, the facility can experience fast power pulses moving through the system. Hybrid supercapacitors are intended to act as a buffer between that dynamic compute load and the infrastructure supplying it. During an upward transient, storage provides some of the incremental power demanded by the IT load. When demand falls, the storage system recharges. The objective is not to create additional energy. It is to keep every upstream component — from the UPS to generators and ultimately the utility connection — from having to respond directly to every rapid change taking place inside the AI cluster. From the perspective of the upstream power source, DeLattre said, the goal is to make a highly dynamic AI load appear significantly smoother. That distinction between energy and power is central to Musashi’s argument for hybrid supercapacitors. A conventional supercapacitor, also known as an electric double-layer capacitor, can deliver very high power almost instantly but stores relatively little energy. A lithium-ion battery can store considerably more energy, but DeLattre argues that it is less suited to being aggressively charged and discharged tens or hundreds of thousands of times. Musashi’s hybrid technology uses a capacitor architecture with a lithium-doped graphite electrode intended to increase energy density while preserving the fast response and high cycling capability associated with capacitors. DeLattre reduces the distinction to a simple formulation. “Batteries are very good

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »