Stay Ahead, Stay ONMINE

Charging Forward: ‘Formidable’ battery energy storage investment in Scotland, China starts installing world’s largest compressed air energy storage project, and more

In this week’s Charging Forward, Scotland secures a “formidable” £800 million investment in battery energy storage, Statera acquires a 680 MW battery project near Manchester and Centrica raises concerns around gas storage levels. And in international news, developers in China have started installation work on the world’s largest compressed air energy storage project while Danish […]

In this week’s Charging Forward, Scotland secures a “formidable” £800 million investment in battery energy storage, Statera acquires a 680 MW battery project near Manchester and Centrica raises concerns around gas storage levels.

And in international news, developers in China have started installation work on the world’s largest compressed air energy storage project while Danish firm Hyme Energy is seeking EU funds for what it says will be the world’s largest thermal energy storage system.

This week’s headlines:

  • £800m investment in Scottish battery energy storage (BESS) projects
  • UK reaches 4.7 of operational BESS capacity in 2024
  • UK battery storage sector “back on strack”, Gresham House says
  • UK government vows to remove barriers to energy storage deployment
  • Centrica raises gas storage concerns
  • Statera acquires 680 MW BESS project
  • Wind2 lodges Scottish wind-BESS application
  • Developers appeal Aberdeen City Council BESS refusal
  • NatPower UK submits plans for 1 GW Bellmoor BESS
  • Cubico starts work on 95 MWh UK BESS
  • RES submits plans for 100 MW BESS in Northern Ireland
  • Conrad Energy to optimise KX Power Immingham BESS
  • Bluefield Renewables Cramlington BESS approved
  • Telis Energy starts early work on Lincolnshire solar-BESS
  • International News: China compressed air energy storage and Danish thermal energy storage project developments

£800m for Scotland BESS projects

Investment fund manager Copenhagen Infrastructure Partners (CIP) has announced it will build two more battery storage sites in Scotland in partnership with Susgen subsidiary Alcemi.

The £800m investment in the 1 GW Coalburn 2 and 500 MW Devilla will see Scotland become home to some of the largest BESS projects in Europe.

Alongside the first phase of Coalburn, the three projects will have a combined energy storage capacity of 3 GWh.

© Jane Barlow/PA Wire
The Coalburn 1 battery energy storage site under construction in Lanark, South Lanarkshire. Image: Jane Barlow/PA Wire

Canadian Solar will supply the batteries for the projects, which will be manufactured in China.

In response to the investment, Scotland’s First Minister John Swinney said: “This is an essential component of our journey to net zero. It’s an essential component of creating resilience within our networks.

“The fact that Scotland has been able to attract such a formidable investment demonstrates that Scotland is open for investment and open for business.”

GB reaches 4.7 GW of BESS capacity in 2024

Across Great Britain, a total of 1 GW of battery capacity began commercial operations in 2024, taking the total rated power of BESS to 4.7 GW according to Modo Energy.

Meanwhile, the total energy capacity of GB batteries grew to 6.5 GWh, meaning the average duration of batteries was 1.39 hours by the end of 2024.

Modo said the buildout in 2024 was lower than expected, after a record breaking year in 2023 saw 1.6 GW of new capacity become commercially operational.

Over the year, 12 new battery owners began commercial operations including SSE, SUSI/Eelpower, NextEnergy/Eelpower and Econergy, contributing a total of 380 MW.

TagEnergy brought the largest site online in 2024 as its 100 MW Lakeside project, while Gresham House added three sites totalling 150 MW.

According to the National Energy System Operator (NESO), UK BESS capacity will need to reach between 23-27 GW in 2030 to ensure the government meets its clean power goals.

UK battery storage sector ‘back on track’

UK battery storage investor Gresham House Energy Storage Fund (LON:GRID) has said the industry is “back on track” as trading conditions improved, particularly in December.

The UK’s largest fund specialising in battery energy storage systems (BESS) highlighted improvements in service from NESO as well as its renewed commitment to to the sector as part of clean power aims by 2030.

Gresham also revealed that revenues exceeding £60,000 per MW of electricity its facilities provided in the second half of 2024 meant it would meet or even exceed revenue targets.

This comes after the fund said it had faced a “weak revenue environment” in the first part of the year. In April it reported a £110 million loss compared to a £217m profit the previous year and paused dividends.

UK vows to remove energy storage barriers

The UK government has vowed to remove barriers to energy storage deployment in response to an Environmental Audit Committee (EAC) report.

In its report, the EAC warned the lack of long duration energy storage (LDES) in the UK was driving the importation of gas.

The report found market, policy and regulatory barriers were holding back the development of LDES projects in the UK.

The government has now set out steps it plans to take to remove market barriers to “support the rollout of energy storage projects at scale”.

Alongside the introduction of a cap-and-flor mechanism for LDES in October last year, the government confirmed it is reviewing the energy storage system alongside NESO “to help make it fit for the future”.

The government will also align grid connections with strategic plans so as to accelerate connections for projects that are ready to generate electricity.

Officials will also publish the status of the grid connection queue to allow for greater transparency.

EAC chair and Labour MP Toby Perkins welcomed the government’s response to the previous committee’s report.

“Addressing the grid constraints which could block the path to net zero is crucial, if the government is to achieve its ambitions and clean up our energy supply,” Perkins said.

“They explain that significant market barriers to long-term energy storage are to be identified, long-term energy storage will be rolled out and skills shortages in the sector are to be addressed: it is clear that the EAC’s advice has been taken seriously by the new government.”

Centrica raises gas storage concerns

British Gas owner Centrica (LON:CNA) said UK gas storage levels fell to “concerningly low levels” amid a “perfect storm” of winter conditions last week.

On Thursday, stocks at UK gas storage sites were 26% lower than the same period last year, leaving them about half full, the energy giant said.

Gas inventory levels have come under pressure from the cold weather conditions and the end of Russian gas pipeline supplies through Ukraine at the end of last month.

Centrica chief executive Chris O’Shea said the UK will need to use more energy storage systems to help meet demand, including gas and hydrogen storage.

“We are an outlier from the rest of Europe when it comes to the role of storage in our energy system and we are now seeing the implications of that,” O’Shea said.

lhyfe centrica green hydrogen © Supplied by Centrica
Centrica has plans to revamp its Rough site into a storage base for hydrogen.

“Energy storage is what keeps the lights on and homes warm when the sun doesn’t shine and the wind doesn’t blow, so investing in our storage capacity makes perfect economic sense.

“We need to think of storage as a very valuable insurance policy.”

Centrica operates the country’s largest gas storage site at the Rough field in the North Sea. The company is exploring the feasibility of converting the site for future use as a hydrogen storage facility.

Statera acquires 680 MW BESS project

Statera Energy has acquired a 680 MW BESS project in north-west England from Carlton Power.

The Carrington Storage project forms part of the Trafford Low Carbon Energy Park, located on the site of a former coal-fired power station near Manchester.

The project is Statera’s largest consent BESS project to date and is more than twice the size of its 300 MW Thurrock Storage project.

Statera said the Carrington Storage project alone will equate to nearly a quarter of the current installed energy capacity of the UK BESS fleet.

© Supplied by Statera Energy
Statera Energy staff next to a battery energy storage system. Image: Statera Energy

In 2023, Carlton Power received planning consent to develop up to 2GW of BESS on the Trafford site.

Other her planned developments include an agreement with Highview Power to build a £300m liquid air energy storage (LAES) project onsite.

Carlton Power also has planning consent for the 200MW Trafford Green Hydrogen production facility.

The project secured financial support from the Department for Energy Security and Net Zero (DESNZ) as part of the first hydrogen allocation round.

The first 15MW phase is expected to begin operation in the next two years.

Carlton Power chief executive Keith Clarke said Trafford is “becoming a beacon for low carbon energy” in the north-west of England.

“The investment in the Trafford Low Carbon Energy Park over the next two to five years demonstrates Carlton Power’s long-term vision and commitment to the Trafford site, and we are actively exploring further options to fully realise the strategic benefits of the Trafford facility,” Clarke said.

Wind2 submits Scottish wind-BESS plans

Renewable energy developer Wind2 has submitted a planning application to the Highland Council for the Swarclett Wind Farm, which includes a 21.6 MW BESS.

The wind farm includes two wind turbines with a blade tip height of up to 149.9 metres on a site near Castletown in Caithness.

Wind2 said the project will generate approximately 66,000 MWh of electricity annually while offsetting approximately 6,000 tonnes of CO2 per year.

The project includes a community benefit fund worth £48,000 per year, and Wind2 said residents living closest to the turbines will be offered the opportunity to claim up to £600 per year towards their electricity costs.

Developers appeal Aberdeen BESS refusal

Flexion Energy is pushing for the Scottish government to approve its 40 MW battery storage site at Countesswells after Aberdeen City Council rejected the plans.

Councillors knocked back the proposal in September as they believed the industrial site would be “out of place” on land just off Countesswells Road.

But Flexion said the proposal meets all national, regional and local planning rules, as well as specific criteria for energy sites such as this.

They added: “The unwarranted refusal is preventing the delivery of infrastructure that is critical to the delivery of renewable energy in the time of a climate crisis.

“Given the significant renewable energy benefits, the appropriateness of the site, and the proposed mitigation measures, the appeal seeks the overturning of the refusal.”

NatPower submits plans for 1 GW Bellmoor BESS

Renewable energy developer NatPower UK has submitted its plans for a 1 GW BESS near Thirsk to North Yorkshire Council.

If plans for the Bellmoor project are approved, NatPower said it will contribute up to £1m each year for 40 years to local community initiatives.

The submission comes just weeks after NatPower lodged a separate planning application with Redcar and Cleveland Council for a 1 GW BESS at Teesside.

The company has previously warned the UK government needs to deliver grid connection reform within six months to ensure its clean power 2030 target stays on track.

NatPower urged regulators to remove “non-credible” projects looking to connect to Britain’s electricity grid, and warned delays could put some of its plans to invest £10bn at risk.

Cubico starts work on 47.5 MW UK BESS

Renewable energy developer Cubico Sustainable Investments has started the construction process for its 47.5 MW Mannington BESS in Dorset.

The two-hour duration 95 MWh project is the company’s first “ready to build” BESS project in the UK, with Tesla selected as the battery supplier.

The Mannington project is the first in Cubico’s global BESS pipeline to reach the construction phase.

Across its global development portfolio, Cubico has 1.3 GW of battery projects at an “advanced stage” and an additional 2.3 GW of greenfield BESS projects in early stage development.

Cubico head of northern Europe James Pinney said issuing procurement and construction contracts for the Mannington BESS is a “key milestone” for the company.

“Integrating renewables into power grids requires substantial investment into storage solutions, and we have a growing pipeline of greenfield projects both in the UK and globally that we are now bringing to fruition,” Pinney said.

RES submits plans for Northern Ireland BESS

Renewable energy developer RES has submitted a planning application for a 100 MW BESS project to Fermanagh and Omagh District Council in Northern Ireland.

RES said the site for the Shaneragh BESS, located near Dromore in County Tyrone, was chosen for its proximity to the Dromore substation.

The site also lies outside of any national or local environmental designations, RES added.

RES development project manager Peter Henry said the importance of battery storage was demonstrated in October when the UK-Norway interconnector went offline.

“As a result, the frequency of our grid network dropped well below the operational limits and this would have led to power outages had it not been for fast-acting frequency services, like battery energy storage, which were able to recover the system within two minutes,” Henry said.

“As well as playing an important role in decarbonising our energy system and providing grid stability, our Shaneragh proposal would also enhance biodiversity in the local area through proposed new native hedgerow and grassland planting.”

If consented, RES said the Shaneragh BESS will take around 15 months to complete.

Across the UK and Ireland, RES has developed over 830 MW of battery storage and currently manages over 600 MW of operational storage projects.

Conrad Energy to optimise KX Power Immingham BESS

Conrad Energy has secured an agreement with KX Power to optimise its 80 MW/160 MWh Immingham BESS.

The Immingham project is set to go live in the first quarter of 2025, and Conrad Energy will utilise its trading platform to “ensure peak operational performance”.

Conrad Energy chairman Damian Darragh said the firm will operate the Immingham BESS over the next three years “providing critical stability and flexibility to the GB network”.

© Supplied by KX Power
Construction of the KX Power 80 MW Immingham BESS. Image: KX Power

KX Power chief investment officer Olivia He said: “Conrad Energy have a track record of successfully optimising their own assets as well as offering a strong balance sheet and flexible contracting.

“We’re confident that their trading desk will ensure the battery system at Immingham is optimised in the most efficient way possible.”

In addition to optimising third party assets, Conrad Energy owns a portfolio of 83 sites, both operational and in development, with the potential to generate 983 MW of electricity.

Bluefield Renewables 50 MW BESS approved

Northumberland County Council has approved plans from UK developer Bluefield Renewables to build a 50 MW BESS in Cramlington.

The Low Horton BESS will be located adjacent to the company’s Low Horton Solar Farm project, which received planning permission in 2022.

The solar farm will be built across two sites in Blyth and Bedlington, with the both sites located on sites formerly associated with coal mining.

Speaking at a meeting of the council’s strategic planning committee, Bluefield managing director Jonathan Selwyn said: “Battery storage is complementary to renewable technology and help achieve climate change targets, and support the UK’s urgent need for energy security.

“In particular, they help to balance generation against demand, stabilise the grid and reduce the likelihood of blackouts.”

Telis Energy starts work on solar-BESS

Renewable energy developer Telis Energy UK has commenced early stage works on an up to 600 MW solar-battery project in Lincolnshire.

The Leoda Solar Farm includes plans for a solar farm with a capacity between 500 and 600 MW, and an onsite BESS.

Because of its size, the project has been deemed “nationally significant” and will be determined by UK energy secretary Ed Miliband rather than the local council.

Shortly after Labour took office last year, Miliband pledged to triple UK solar power capacity.

The announcement came as Miliband approved three major solar power projects which had stalled under the former Conservative government.

Leoda Solar Farm head of planning Alex Herbert said: “As the UK continues its transition towards renewable energy, projects like Leoda Solar Farm are vital.

“This project not only supports national goals for net zero emissions but also provides a significant opportunity to invest in our environment, health, and local communities.

“We are committed to working closely with stakeholders and residents over the coming months to develop a project that benefits both the region and the country as a whole.”

Telis Energy UK is part of the wider Telis Energy Group, which has a 10 GW pipeline of projects across the UK, Germany, France and Italy.

China starts work on Jiangsu compressed air energy storage project

Chinese developer Huaneng Group has started construction on the expansion of the country’s first salt cavern compressed air energy storage (CAES) facility.

Billed as the world’s largest project of its kind, the expansion of the Jintan Salt Cavern CAES began on Wednesday 18 December.

The second phase involves building two 350 MW CAES units, with the capacity to store 2.8 GWh of electricity, the equivalent of charging 100,000 electric vehicles.

© Supplied by Tsinghua University
Aerial photo of the Jiangsu Jintan Salt Cavern Compressed Air Energy Storage project in China. Image: Tsinghua University

The power station uses electric energy to compress air into an underground salt cavern, before releasing the air to drive a turbine and generate electricity when required.

According to state-owned Chinese news outlet Xinhua, the station will help save 270,000 tonnes of standard coal and reduce CO2 emissions by 520,000 tonnes annually.

China National Salt Industry Group and Tsinghua University are co-developing the project alongside Huaneng Group.

Hyme Energy seeks EU funds for thermal energy storage project

Danish firm Hyme Energy is seeking EU funding for what it says will be the world’s largest industrial thermal storage system.

Hyme is collaborating with Danish firm Arla on the 200 MWh project at the dairy company’s milk powder facility in Holstebro.

The thermal energy storage system will convert renewable electricity into heat, which is stored in molten salt tanks above 500 degrees celsius.

Hyme said the stored heat can then be used to replace fossil fuels in Arla’s milk powder production.

The project will enable up to a 100% reduction in CO2 emissions from process heat at the production facility, Hyme said.

© Supplied by Hyme Energy
A render of an industrial thermal energy storage system designed by Danish firm Hyme Energy.

Hyme Energy chief commercial officer Nis Benn said the project could be a “game-changer for industrial decarbonisation”.

“It will show that reducing CO2 emissions in large-scale industries is not only feasible but also economically attractive.

“We believe this project will serve as a blueprint for future deployments, and we encourage other industry leaders to join the energy transition.”

Hyme and Arla are jointly seeking up to €30m (£25m) in EU funding for the project. If successful, Arla said it could scale the technology across its manufacturing network.

Hyme has already secured EU Horizon funding to build a 20 MWh thermal storage demonstration unit to provide district heating in the Danish town of Bornholm.

Recommended for you

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

An “Unstoppable Web” is a reality that Tether is orchestrating

The current web is optimized for surveillance capitalism; this is positive compared to other ways our data can be used. Data from activities on native utility applications and communications on social messaging applications, both offline and online, are routed through centralized systems managed by admins who decide whether these actions

Read More »

NextDecade contractor Bechtel awards ABB more Rio Grande LNG automation work

NextDecade Corp. contractor Bechtel Corp. has awarded ABB Ltd. additional integrated automation and electrical solution orders, extending its scope to Trains 4 and 5 of NextDecade’s 30-million tonne/year (tpy)  Rio Grande LNG (RGLNG) plant in Brownsville, Tex. The orders were booked in third- and fourth-quarters 2025 and build on ABB’s Phase 1 work with Trains 1-3, totaling 17 million tpy.  The scope for RGLNG Trains 4 and 5 includes deployment of an integrated control and safety system consisting of a distributed control system, emergency shutdown, and fire and gas systems. An electrical controls and monitoring system will provide unified visibility of the plant’s electrical infrastructure. These two overarching solutions will provide a common automation platform. ABB will also supply medium-voltage drives, synchronous motors, transformers, motor controllers and switchgear.  The orders also include local equipment buildings—two for Train 4 and one for Train 5— housing critical control and electrical systems in prefabricated modules to streamline installation and commissioning on site. The solutions being delivered to Bechtel use ABB adaptive execution, a methodology for capital projects designed to optimize engineering work and reduce delivery timelines. Phase 1 of RGLNG is under construction and expected to begin operations in 2027. Operations at Train 4 are expected in 2030 and Train 5 in 2031. ABB’s senior vice-president for the Americas, Scott McCay, confirmed to Oil & Gas Journal at CERAWeek by S&P Global in Houston that the company is doing similar work through Tecnimont for Argent LNG’s planned 25-million tpy plant in Port Fourchon, La.; 10-million tpy Phase 1 and 15-million tpy Phase 2. Argent is targeting 2030 completion for its plant.

Read More »

Persistent oil flow imbalances drive Enverus to increase crude price forecast

Citing impacts from the Iran war, near-zero flows through the Strait of Hormuz, accelerating global stock draws, and expectations for a muted US production response despite higher prices, Enverus Intelligence Research (EIR) raised its Brent crude oil price forecast. EIR now expects Brent to average $95/bbl for the remainder of 2026 and $100/bbl in 2027, reflecting what it described as a persistent global oil flow imbalance that continues to draw down inventories. “The world has an oil flow problem that is draining stocks,” said Al Salazar, director of research at EIR. “Whenever that oil flow problem is resolved, the world is left with low stocks. That’s what drives our oil price outlook higher for longer.” The outlook assumes the Strait of Hormuz remains largely closed for 3 months. EIR estimates that each month of constrained flows shifts the price outlook by about $10–15/bbl, underscoring the scale of the disruption and uncertainty around its duration. Despite West Texas Intermediate (WTI) prices of $90–100/bbl, EIR does not expect US producers to materially increase output. The firm forecasts US liquids production growth of 370,000 b/d by end-2026 and 580,000 b/d by end-2027, citing drilling-to-production lags, industry consolidation, and continued capital discipline. Global oil demand growth for 2026 has been reduced to about 500,000 b/d from 1.0 million b/d as higher energy prices and anticipated supply disruptions weigh on economic activity. Cumulative global oil stock draws are estimated at roughly 1 billion bbl through 2027, with non-OECD inventories—particularly in Asia—absorbing nearly half of the impact. A 60-day Jones Act waiver may provide limited short-term US shipping flexibility, but EIR said the measure is unlikely to materially affect global oil prices given broader market forces.

Read More »

Equinor begins drilling $9-billion natural gas development project offshore Brazil

Equinor has started drilling the Raia natural gas project in the Campos basin presalt offshore Brazil. The $9-billion project is Equinor’s largest international investment, its largest project under execution, and marks the deepest water depth operation in its portfolio. The drilling campaign, which began Mar. 24 with the Valaris DS‑17 drillship, includes six wells in the Raia area 200 km offshore in water depths of around 2,900 m. The area is expected to hold recoverable natural gas and condensate reserves of over 1 billion boe. Raia’s development concept is based on production through wells connected to a 126,000-b/d floating production, storage and offloading unit (FPSO), which will treat produced oil/condensate and gas. Natural gas will be transported through a 200‑km pipeline from the FPSO to Cabiúnas, in the city of Macaé, Rio de Janeiro state. Once in operation, expected in 2028, the project will have the capacity to export up to 16 million cu m/day of natural gas, which could represent 15% of Brazil’s natural gas demand, the company said in a release Mar. 24. “While drilling takes place, integration and commissioning activities on the FPSO are progressing well putting us on track towards a safe start of operations in 2028,” said Geir Tungesvik, executive vice-president, projects, drilling and procurement, Equinor. The Raia project is operated by Equinor (35%), in partnership with Repsol Sinopec Brasil (35%) and Petrobras (30%).

Read More »

Woodfibre LNG receives additional modules as construction advances

Woodfibre LNG LP has received two major modules within a week for its under‑construction, 2.1‑million tonne/year (tpy) LNG export plant near Squamish, British Columbia, advancing construction to about 65% complete. The deliveries include the liquefaction module—the project’s heaviest and most critical process unit—and the powerhouse module, which will serve as the plant’s central power and control hub. The liquefaction module, delivered aboard the heavy cargo vessel Red Zed 1, is the 15th of 19 modules scheduled for installation at the site, the company said in a Mar. 24 release. Weighing about 10,847 metric tonnes and occupying a footprint roughly equivalent to a football field, it is among the largest modules fabricated for the project. Once installed and commissioned, the liquefaction module will cool natural gas to about –162°C, converting it into LNG for export. Shortly after the liquefaction module’s arrival, Woodfibre LNG received the powerhouse module, the 16th module delivered to site. Weighing more than 4,200 metric tonnes, the powerhouse module will function as a power and control system, receiving electricity from BC Hydro and managing and distributing power to the plant’s electric‑drive compressors. The Woodfibre LNG project is designed as the first LNG export plant to use electric‑drive motors for liquefaction, replacing conventional gas‑turbine‑driven compressors. The Siemens electric‑drive system will be powered by renewable hydroelectricity from BC Hydro, eliminating the largest operational source of greenhouse gas emissions typically associated with liquefaction, the company said. The project is being built near the community of Squamish on the traditional territory of the Sḵwx̱wú7mesh Úxwumixw (Squamish Nation) and is regulated in part by the Indigenous government.  All 19 modules are expected to arrive on site by spring 2026. Construction is scheduled for completion in 2027. Woodfibre LNG is owned by Woodfibre LNG Ltd. Partnership, which is 70% owned by Pacific Energy Corp.

Read More »

ExxonMobil begins Turrum Phase 3 drilling off Australia’s east coast

@import url(‘https://fonts.googleapis.com/css2?family=Inter:[email protected]&display=swap’); a { color: var(–color-primary-main); } .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; font-family: Inter; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; opacity: .6; } #onetrust-pc-sdk [id*=btn-handler], #onetrust-pc-sdk [class*=btn-handler] { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-policy a, #onetrust-pc-sdk a, #ot-pc-content a { color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-pc-sdk .ot-active-menu { border-color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-accept-btn-handler, #onetrust-banner-sdk #onetrust-reject-all-handler, #onetrust-consent-sdk #onetrust-pc-btn-handler.cookie-setting-link { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-consent-sdk .onetrust-pc-btn-handler { color: #c19a06 !important; border-color: #c19a06 !important; } Esso Australia Pty Ltd., a subsidiary of ExxonMobil Corp. and current operator of the Gippsland basin oil and gas fields in Bass Strait offshore eastern Victoria, has started drilling the Turrum Phase 3 project in Australia. This $350-million investment will see the VALARIS 107 jack-up rig drill five new wells into Turrum and North Turrum gas fields within Production License VIC/L03 to support Australia’s east coast domestic gas market. The new wells will be drilled from Marlin B platform, about 42 km off the Gippsland coastline, southeast of Lakes Entrance in water depths of about 60 m, according to a 2025 information bulletin.   <!–> Turrum Phase 3, which builds on nearly $1 billion in recent investment across the Gippsland basin, is expected to be online before winter 2027, the company said in a post to its LinkedIn account Mar. 24. In 2025, Esso made a final investment decision to develop the Turrum Phase 3 project targeting underdeveloped gas resources. The Gippsland Basin joint venture is a 50-50 partnership between Esso Australia Resources and Woodside Energy (Bass Strait) and operated by Esso Australia.  ]–><!–> ]–>

Read More »

The Golden Rule of the oil market: Understanding global price dynamics and emerging exceptions

Mark FinleyBaker Institute, Rice University  In recent weeks, questions surrounding the oil market crisis have been framed around a core principle described as the Golden Rule of the Oil Market: it is a global market. When conditions change anywhere—positively or negatively—prices respond everywhere. That framework helps explain why gasoline prices are rising in the US despite limited direct imports from the Middle East and the US’s status as a significant net exporter of oil. It also explains why oil cargoes that Iran permits to transit the Strait of Hormuz reduce Iran’s leverage over global oil prices, and by extension over US consumers and policymakers concerned about prices at the pump. Alongside its own exports, Iran has allowed a handful of additional tankers to transit the Strait, including several tankers destined for China and LPG shipments for India. The greater the volume of oil transiting the Strait, the smaller the disruption to the global oil market and the less upward pressure on global prices. The same logic applies to US efforts to ease sanctions on Iranian and Russian oil cargoes already at sea, which are unlikely to provide meaningful relief for rising oil prices. Under the Golden Rule, those barrels—having already been produced and shipped—would have found buyers regardless of sanctions, with price discounts sufficient to offset the risk of US penalties, as has been the case for Russian oil since 2022. Exceptions The Golden Rule has described oil market dynamics effectively for decades. However, a small number of potential exceptions have begun to emerge. For now, those exceptions remain relatively inconsequential, though larger risks may be developing. The non-market player There are two ways that supply and demand can be equalized. In a global market, it is achieved by price changes. Prices rise or fall to ensure that there is

Read More »

Q1 Executive Roundtable Recap

Matt Vincent is Editor in Chief of Data Center Frontier, where he leads editorial strategy and coverage focused on the infrastructure powering cloud computing, artificial intelligence, and the digital economy. A veteran B2B technology journalist with more than two decades of experience, Vincent specializes in the intersection of data centers, power, cooling, and emerging AI-era infrastructure. Since assuming the EIC role in 2023, he has helped guide Data Center Frontier’s coverage of the industry’s transition into the gigawatt-scale AI era, with a focus on hyperscale development, behind-the-meter power strategies, liquid cooling architectures, and the evolving energy demands of high-density compute, while working closely with the Digital Infrastructure Group at Endeavor Business Media to expand the brand’s analytical and multimedia footprint. Vincent also hosts The Data Center Frontier Show podcast, where he interviews industry leaders across hyperscale, colocation, utilities, and the data center supply chain to examine the technologies and business models reshaping digital infrastructure. Since its inception he serves as Head of Content for the Data Center Frontier Trends Summit. Before becoming Editor in Chief, he served in multiple senior editorial roles across Endeavor Business Media’s digital infrastructure portfolio, with coverage spanning data centers and hyperscale infrastructure, structured cabling and networking, telecom and datacom, IP physical security, and wireless and Pro AV markets. He began his career in 2005 within PennWell’s Advanced Technology Division and later held senior editorial positions supporting brands such as Cabling Installation & Maintenance, Lightwave Online, Broadband Technology Report, and Smart Buildings Technology. Vincent is a frequent moderator, interviewer, and keynote speaker at industry events including the HPC Forum, where he delivers forward-looking analysis on how AI and high-performance computing are reshaping digital infrastructure. He graduated with honors from Indiana University Bloomington with a B.A. in English Literature and Creative Writing and lives in southern New Hampshire with

Read More »

Executive Roundtable: The AI Infrastructure Credibility Test

For the fourth installment of DCF’s Executive Roundtable for the First Quarter of 2026, we turn to a question that increasingly sits alongside power and capital as a defining constraint. Credibility. As AI-driven data center development accelerates, public scrutiny is rising in parallel. Communities, regulators, and policymakers are taking a closer look at the industry’s footprintin terms of its energy consumption, its land use, and its broader impact on local infrastructure and ratepayers. What was once a relatively low-profile sector has become a visible and, at times, contested presence in regional economies. This shift reflects the sheer scale of the current build cycle. Multi-hundred-megawatt and gigawatt campuses are no longer theoretical in any sense. They are actively being proposed and constructed across key markets. With that scale comes heightened expectations around transparency, accountability, and tangible community benefit. At the same time, the industry faces a more complex regulatory and political landscape. Questions around grid capacity, rate structures, environmental impact, and economic incentives are increasingly being debated in public forums, from state utility commissions to local zoning boards. In this environment, the ability to secure approvals is no longer assured, even in historically favorable markets. The concept of a “social license to operate” has therefore moved to the forefront. Beyond technical execution, developers and operators must now demonstrate that AI infrastructure can be deployed in a way that aligns with community priorities and delivers shared value. In this roundtable, our panel of industry leaders explores what will define that credibility in the years ahead and what the data center industry must do to sustain its momentum in an era of growing public scrutiny.

Read More »

International Data Center Day: Future Frontiers 2030-2070

In honor of this year’s International Data Center Day 2026 (Mar 25), Data Center Frontier presents a forward-looking vision of what the next era of digital infrastructure education—and imagination—could become. As the media partner of 7×24 Exchange, DCF is committed to elevating both the technical rigor and the human story behind the systems that power the AI age. What follows is not reportage, but a plausible future: a narrative exploration of how the next generation might learn to build, operate, and ultimately redefine data centers—from tabletop scale to lunar megacampuses. International Data Center Day, 2030 The Little Grid That Could They called it “Build the Cloud.” Which, to the adults in the room, sounded like branding. To the kids, it sounded literal. On a gymnasium floor somewhere in suburban Ohio (though it could just as easily have been Osaka, or Rotterdam, or Lagos) thirty-two teams of middle school students crouched over sprawling tabletop worlds the size of model train layouts. Only these weren’t towns with plastic trees and HO-scale diners. These were data centers. Tiny ones. Living ones. Or trying to be. Each team had been given the same kit six weeks earlier: modular rack frames no taller than a juice box, fiber spools thin as thread, micro solar arrays, a handful of millimeter-scale wind turbines, and a small fleet of programmable robotic “operators”—wheeled, jointed, blinking with LED status lights. The assignment had been deceptively simple: Design, build, and operate a self-sustaining data center campus. Then make it come alive. Now it was International Data Center Day, 2030, and the judging had begun. The Sound of Small Machines Thinking If you stood at the edge of the gym and closed your eyes, it didn’t sound like a science fair. It sounded like… something else. A low hum of micro-inverters stepping

Read More »

Superconducting the AI Era: Rethinking Power Delivery for Gigawatt Data Centers

For the data center industry, the AI era has already rewritten the rules around capital deployment, site selection, and infrastructure scale. But as the build cycle accelerates into the gigawatt range, a deeper constraint is coming into focus; one that sits beneath generation, beneath interconnection queues, and even beneath permitting. It is the physical act of moving power. The challenge is no longer simply how to procure energy, but how to deliver it efficiently from the grid edge to the campus, across buildings, and ultimately into racks that are themselves becoming industrial-scale power consumers. In this emerging reality, traditional copper-based distribution systems are beginning to show signs of strain not just economically, but physically. In the latest episode of the Data Center Frontier Show Podcast, MetOx CEO Bud Vos frames this moment as a structural turning point for the industry, one where superconducting technologies may begin to shift from theoretical to practical. “When you start looking at gigawatt-type campuses,” Vos explains, “you find three fundamental constraints in the power distribution problem: the grid interconnect, the campus distribution, and then delivery inside the data hall.” Each of these layers compounds the difficulty of scaling infrastructure in a copper-based world. More capacity means more cables, more trenching, more materials, and more complexity in an exponential expansion of the physical systems required to support AI workloads. A Different Kind of Conductor High-temperature superconducting (HTS) wire offers a radically different path forward. Developed from research originating at the University of Houston and now manufactured through advanced thin-film processes, HTS replaces bulk conductive material with a highly efficient layered structure capable of carrying dramatically higher current densities. Vos describes the manufacturing approach in familiar terms for a data center audience: “You can think of it as a semiconductor process. We’re creating thin film depositions on

Read More »

DCF Poll: AI Data Center Assumptions

Matt Vincent is Editor in Chief of Data Center Frontier, where he leads editorial strategy and coverage focused on the infrastructure powering cloud computing, artificial intelligence, and the digital economy. A veteran B2B technology journalist with more than two decades of experience, Vincent specializes in the intersection of data centers, power, cooling, and emerging AI-era infrastructure. Since assuming the EIC role in 2023, he has helped guide Data Center Frontier’s coverage of the industry’s transition into the gigawatt-scale AI era, with a focus on hyperscale development, behind-the-meter power strategies, liquid cooling architectures, and the evolving energy demands of high-density compute, while working closely with the Digital Infrastructure Group at Endeavor Business Media to expand the brand’s analytical and multimedia footprint. Vincent also hosts The Data Center Frontier Show podcast, where he interviews industry leaders across hyperscale, colocation, utilities, and the data center supply chain to examine the technologies and business models reshaping digital infrastructure. Since its inception he serves as Head of Content for the Data Center Frontier Trends Summit. Before becoming Editor in Chief, he served in multiple senior editorial roles across Endeavor Business Media’s digital infrastructure portfolio, with coverage spanning data centers and hyperscale infrastructure, structured cabling and networking, telecom and datacom, IP physical security, and wireless and Pro AV markets. He began his career in 2005 within PennWell’s Advanced Technology Division and later held senior editorial positions supporting brands such as Cabling Installation & Maintenance, Lightwave Online, Broadband Technology Report, and Smart Buildings Technology. Vincent is a frequent moderator, interviewer, and keynote speaker at industry events including the HPC Forum, where he delivers forward-looking analysis on how AI and high-performance computing are reshaping digital infrastructure. He graduated with honors from Indiana University Bloomington with a B.A. in English Literature and Creative Writing and lives in southern New Hampshire with

Read More »

A Faster Path to Power: What Natrium’s NRC Approval Means for AI Infrastructure

The race to build AI infrastructure at scale has exposed a deeper constraint than capital or compute: power that can be delivered on predictable timelines. That constraint is now colliding with a system that has historically moved at the pace of decades. But in early March, a key signal emerged that the equation may be starting to change. A Regulatory Breakthrough at the Moment of Peak Power Demand TerraPower’s Natrium reactor cleared a major milestone with the Nuclear Regulatory Commission, which approved a construction permit for Kemmerer Power Station Unit 1 in Wyoming, representing the company’s first commercial-scale plant. It is the first reactor construction approval the NRC has granted in nearly a decade, and the first for a commercial non-light-water reactor in more than 40 years. More significantly, it is the first advanced reactor to reach this stage under the modern U.S. licensing framework. For an industry increasingly defined by gigawatt-scale AI campuses and compressed build cycles, that milestone lands with unusual timing. Construction Approved — But Not Yet ‘Power Delivered’ The distinction between construction approval and operational readiness is critical. TerraPower has not received a license to generate electricity. What the NRC has granted is permission to begin nuclear-related construction at the Kemmerer site, following safety and environmental review. Before the plant can operate, TerraPower’s subsidiary, US SFR Owner, must still secure a separate operating license. But in practical terms, this is the moment when a project transitions from concept to execution. It is a regulatory green light not for power generation, but for steel, concrete, and capital deployment. And in the context of advanced nuclear, that step has historically been the hardest to reach. An 18-Month Signal to the Market The speed of that approval may ultimately matter as much as the approval itself. TerraPower submitted its construction

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »