![](https://onmine.io/wp-content/uploads/2025/02/67a63d4e489738c654524115-plant_vogtle2_mobile.jpg)
The rule also mandates that any new contracts between Georgia Power and large-load customers exceeding 100 MW be submitted to the PSC for review. This provision ensures regulatory oversight and transparency in agreements that could significantly impact the state’s power grid and ratepayers.
Commissioner Lauren “Bubba” McDonald points out that this is one of a number of actions that the PSC is planning to protect ratepayers, and that the PSC’s 2025 Integrated Resource Plan will further address data center power usage.
Keeping Ahead of Anticipated Energy Demand
This regulatory change reflects Georgia’s proactive approach to managing the increasing energy demands associated with the state’s growing data center industry, aiming to balance economic development with the interests of all electricity consumers.
Georgia Power has been trying very hard to develop generation capacity to meet it’s expected usage pattern, but the demand is increasing at an incredible rate.
In their projection for increased energy demand, the 2022 number was 400 MW by 2030. A year later, in their 2023 Integrated Resource Plan, the anticipated increase had grown to 6600 MW by 2030.
Georgia Power recently brought online two new nuclear reactors at the Vogtle Electric Generating Plant, significantly increasing its nuclear generation capacity giving the four unit power generation station a capacity of over 4.5 GW. This development has contributed to a shift in Georgia’s energy mix, with clean energy sources surpassing fossil fuels for the first time.
But despite the commitment to nuclear power, the company is also in the process of developing three new power plants at the Yates Steam Generating Plant. According to the AJC newspaper, regulators had approved the construction of fossil fuel power, approving natural gas and oil-fired power plants.
Designed as “peaker” plants to come online at times of increased the demand, the power plants will be able to deliver up to 1.3 GW of power when necessary, or roughly the equivalent of a single one of the four reactors at the Vogtle Nuclear Generation Station.
More details should be available soon, when the 2025 Integrated Resource Plan is released, about Georgia Power’s plan to issue an RFP to directly address capacity needs for 2029 through 2031.
This follows on to the 2024 RFP for 500 MW energy storage systems. The company’s most recent projections for energy demand are looking to add 10 GW of renewable energy by 2035; almost doubling previous projections for 2030.
Getting the Power Where It Is Needed
In October of 2024, Georgia Power was awarded over $160 million from the Department of Energy via the Grid Resilience and Innovation Partnerships (GRIP) program.
Investments under GRIP are targeted at improving the resiliency of the grid and making events such as extreme weather conditions less likely to threaten power delivery.
According to Fran Forehand, Senior Vice President of Transmission for Georgia Power: