Want to get a data center online quickly? Give it some flex.

At the end of a tense and scoreless first half of a soccer match between the English men’s team and rival Germany, millions of Brits let out a collective sigh and did what they so often do in moments of stress: They made tea. That wave of electric kettles clicking on, however, caused a different kind of stress: a huge and sudden increase in demand for electricity. But National Grid, which operates the local transmission network, was ready. Just as those kettles started heating up, an AI program sent instructions to a data center in London to slow down some of the facility’s power-hungry chips. This reduction helped make sure there was enough supply to match demand, staving off potential blackouts or damage to electrical hardware. For data centers, which normally guzzle power without consideration for anyone or anything else’s needs, it was a radical departure. It was also a simulation. In December 2025, engineers sought to test a new breed of data center built to be flexible about its electricity needs, so they re-created the energy demand facing the UK’s grid during a match from the 2020 Euro tournament. They wanted to see how their software, called Conductor, would have responded had it been online at the time. Conductor is the signature product of Emerald AI, a firm based in Washington, DC, that’s part of a wave of companies trying to figure out whether data centers can work within the confines of the existing electric grid. This year, Emerald is set to deploy Conductor in a new facility in the part of Virginia known as Data Center Alley, this time connected to the live grid. When overall demand spikes, Conductor will turn down the power used by the data center, while making sure its servers still carry out their timeliest and most important jobs. Emerald’s partners on the project—which include Nvidia and the giant data-center operator Digital Realty—bill it as one of the world’s first “power-flexible AI factories.” Demonstrating that data centers can participate in this kind of give-and-take could ease what many tech leaders identify as the bottleneck in getting facilities online: It takes far longer to get approval for, construct, and connect new power plants than to build data centers. PJM, the grid operator in Virginia and the largest one in the US, for instance, needs eight years to bring new generation online, according to RMI, an energy research and advocacy group. “We need to solve the energy equation,” says Josh Parker, head of sustainability at Nvidia. “AI factory flexibility is the bridge between the incredible demand for AI and the immediate limitations of our energy grid.” Speed, though, is only one of the issues. Once facilities do plug in, neighbors often criticize them for drawing too much electricity and contributing to rising prices. They say the data centers generate more noise than they do long-term jobs, contribute to pollution, and threaten to put people out of work. Organizers stalled over $150 billion worth of projects in 2025, according to Data Center Watch, and policymakers alert to the public mood are starting to impose limitations on development. More than a dozen states are considering bans, and local moratoriums are in effect in places like Minneapolis and DeKalb County in Georgia. At the federal level, the GRID Act, a bipartisan bill in the US Senate, proposes to sever new data centers from public grids entirely. Some operators are already moving that way by trying to develop their own power generation. Rather than rushing to build new power plants, companies could find part of the solution to the crunch right under our noses—or, more precisely, in the transmission lines under our feet and above our heads. The existing system operates near its full capacity during only a small number of high-demand hours throughout the year. This means, some grid experts argue, that if data centers can limit the power they draw during those stretches, they won’t need to wait for big infrastructure upgrades or build their own off-grid generation.  Indeed, a growing number of studies have shown there could be plenty of power available for data centers that can flex. A widely discussed 2025 report from researchers at Duke University found that the US grid could offer an additional 76 gigawatts—about 5% of its entire capacity, and about enough to accommodate projected data-center growth in the US through 2030—to facilities that are willing to reduce their usage just 0.25% of the time. That’s about 22 hours a year. And when researchers from Princeton University and two grid-modernization companies looked at locations for new data centers in the PJM region, their report, which was funded by Google, found that a 500-megawatt facility capable of flexing for less than 1% of the year could reach full operation three to five years faster than one that’s inflexible.  Flexible power connections could also help data centers address some of their PR problems. By decreasing their draw at times of grid stress, for instance, they could avoid diverting power from where it’s most needed, thus boosting stability. By using existing capacity, they might be able to reduce the need for new fossil-fuel power plants and spread fixed costs over more electricity users, pushing prices down.  The AI power pinch is attracting resources and research into strategies for grid flexibility overall, which could help negotiate a tricky period: Taken together with electric vehicles, air-conditioning, and other sectors, data centers are helping drive what analysts predict will be a 25% increase in US electricity demand by 2030 compared with 2023 levels. Ideally, flexibility gives grid operators more control over the flow of electrons, making them leaders of a harmonious ensemble rather than hostages to inflexible electricity requirements. That will help them manage demand spikes across the entire system and deal more effectively with the intermittent nature of renewables like wind and solar. “Demand flexibility is incredibly useful for power grids,” says Johanna Mathieu, a grid expert at the University of Michigan. “It helps reduce electricity costs and improve grid reliability.” But while advocates see plenty of benefits, the concept brings complexity. For data centers, compromising on energy needs can be a hard sell. Flexibility requires utilities and grid operators, which tend to be operationally conservative, to change long-held practices. And some skeptics also say that flexibility distracts from the very real need to build more grid infrastructure faster, and could even pose risks to our electricity supply.  Still, some technologists, grid operators, and utilities are hoping to show that flexibility works—not only in white papers or simulations but in real life.  The poster children for data-center growth default toward inflexibility. Hyperscalers like Microsoft and Oracle have proposed enormous new centers, many of which would rely on off-grid, natural-­gas-burning power plants. When xAI wanted to speed up the buildout of the Colossus site outside Memphis, Tennessee, it rolled up with gas turbines on flatbed trucks. The facility, now in operation, is facing blowback from regulators and residents about the spike it’s causing in emissions and other pollution. In any case, there aren’t enough gas turbines worldwide to meet the demand from data-center operators.  One big obstacle for anyone demanding a lot of power is that our grids are mostly rigid. They’re designed to supply enough power to meet total demand when it’s highest, even if that’s for only a relatively small number of hours a year. That conservative approach is a simple route to reliability, but it means that the grid has quite a bit of headroom. “The grid is already overbuilt by a lot. If you were an airline running at 30% utilization, you would not buy more planes,” says Amit Narayan, the cofounder and CEO of GridCare, a company developing flexibility technologies, referring to a 2025 Stanford study of transmission lines in western North America. “If you are running a grid at 30% utilization, there’s no scientific reason you can’t go to 60.”  “If you were an airline running at 30% utilization, you would not buy more planes. If you are running a grid at 30% utilization, there’s no scientific reason you can’t go to 60.” To be fair, the idea of flexibility isn’t entirely foreign to grid operators. For decades, they’ve practiced a technique called demand response: When it looks as if demand will get too close to supply, as it might during a heat wave when many people turn on the AC at the same time, they call large commercial or industrial facilities and ask them to shut down parts of their operations. This method can help avoid the need to fire up so-called peaker plants, which run on fossil fuels, but it’s slow, imprecise, and hard to scale. In the 2000s, as the adoption of technologies like electric cars and solar panels presented new challenges, more internet-­connected grids also provided new means of flexibility. Virtual power plants, or VPPs, offered a smarter, faster, more granular alternative. Electricity customers ranging from factories to homeowners with smart thermostats, solar panels, or big batteries would allow the utility to adjust their draw to help meet demand—often getting paid for their (frequently unnoticed) trouble.  After the generative AI boom began with the release of ChatGPT in 2022, some companies began to see flexibility as a way to get data centers set up more easily, efficiently, and affordably. If they bring AI money into existing grids and reduce or defer the need for expensive upgrades, data centers could actually help spread out fixed costs so as to lower rates for other users. A study from Duke University published this past February, for instance, found that flexibility could reduce rates by 0.5% to 2.8%.  PETRA PÉTERFFY The trick is figuring out how data centers, notorious power hogs, can keep operating when their flexible connections are throttled. Flexibility specialists envision three possible ways. The simplest is for the new data center to install on-site backup power storage or generation to tap when the grid is maxed out—at their own expense, of course. A facility could also fill the gap by drawing on a VPP. The utility would turn down the electricity going to users who signed up for the VPP, and the data center would pay them for their flexibility. This method wouldn’t require any major infrastructure, but it would require the utility to have a big VPP program and to coordinate the exchange at a time when the grid was under stress. While VPPs exist to some extent in nearly 40 states, the rules governing them vary widely, and they are empowered to do more in some areas than in others.  Finally, a data center could simply use less power at peak times. The conventional wisdom is that they won’t go for such limits, particularly when every number-­crunching server can feel like a goose potentially laying little golden eggs. But some experts are betting that the value of getting up and running quickly is enough to change their minds. “There is a clear and growing trend,” says Ayse Coskun, chief scientist at Emerald AI. “Operators are increasingly willing to trade some level of flexibility for faster grid interconnection.”  GridCare, a startup based in Silicon Valley, was one of the first companies to use flexibility to get data centers online quickly. Instead of looking at grids only in worst-case scenarios when electricity demand is highest, the company analyzes the system under all conditions, explains CEO Narayan, who studied smart grids at Stanford. It feeds every part of the grid—including power plants, lines, substations, and homes—into a generative AI model that creates a “digital twin” for different grid configurations. It then picks out results that could unlock capacity while maintaining reliability, and it feeds those into another model trained on the physics of electrical components like resistors and capacitors to make sure they’re realistic. GridCare found its first customer in the Silicon Forest, an area in the Pacific Northwest named for the trees that dominate the landscape and the IT industry that has more recently sprouted up there. The local grid needed more capacity to support more data centers. “Data centers wanted ‘speed to power,’” says Isaac Barrow, a manager of data-center relations at Portland General Electric, or PGE, the local power generator and distributor, “but transmission buildout is a long process that’s very costly.” In 2024, Aligned Data Centers came to PGE wanting to expand its operation in Hillsboro, Oregon, and PGE followed a recommendation from GridCare. Aligned will install a 31-megawatt battery, set to be in service in May 2027, and decrease its draw by up to that amount when the grid becomes congested. Bundled with other flexibility measures, that battery has allowed PGE to increase the capacity it can offer Aligned and other nearby operators by 80 megawatts without any new power plants. Though the buildout of data centers in Hillsboro has faced plenty of pushback from locals, Barrow points out that it could have the knock-on effect of lowering costs for ratepayers, because it spreads out the tab. Other companies are promoting different flavors of flexibility. Google has been moving processing loads from facilities in areas experiencing demand spikes to those in less stressed spots since 2023. It’s signed agreements with five utilities, including the Tennessee Valley Authority and Indiana Michigan Power, that add as much as a gigawatt of flexibility.  Voltus, a major VPP provider across the US and Canada, markets a “bring your own capacity” program in which a data-­center company can fund a VPP nearby. The grid operator can use the VPP to decrease demand at busy times, and participants get a financial thank-you. “We can spin up new VPPs on the order of months,” says Emily Orvis, Voltus’s vice president of energy markets. In June, the company signed their first such data-center deal: a three-year plan in which Google will bankroll a VPP in the PJM interconnection. Of all the approaches to flexibility, Emerald AI’s may be the most ambitious: asking data centers to dial into the grid’s needs. The company’s Conductor software, which can run on premises or in the cloud, builds on the research of chief scientist Coskun. Her group at Boston University showed in a pair of 2013 papers that a data center could watch the grid and help balance big power fluctuations, such as the intermittent effects of solar and wind power. By 2022, she and her colleagues had tested their methods on a cluster of 36 research servers and shown that the system could respect power limits without breaking the processes it was running.  One of the most important questions for Conductor is deciding which AI processes can be slowed down to save energy without kneecapping performance. A lot of companies label their jobs by priority—a real-time chatbot query, for instance, might outrank something like a web search that’s part of a deep research project. When they don’t, Emerald AI tries to infer priority from the nature of the job. Conductor then analyzes the AI workload to determine how tweaking the power to a given processor will affect the performance and help meet the usage limits set by the grid operator. “The performance curve changes for different kinds of workloads,” says Coskun. “Each AI job is going to have a different location on that curve. Our intelligence is figuring out where you are on that curve.”  PETRA PÉTERFFY Last year, Emerald AI began assessing the technology’s readiness for real-world use in a series of tests, raising the difficulty each time. The trials were carried out in partnership with the Data Center Flexible Load Initiative—a collaboration among tech companies like Google and Nvidia, utilities like Duke Energy, and grid operators like PJM that aims to help establish a repeatable framework for power-­flexible data centers. The first challenge was in Phoenix, a fast-growing computing hub. For the test, Conductor took control of a group of server racks laden with 256 Nvidia A100 GPUs—hardware that can use about as much power as around 170 US homes. When presented with a simulation of a busy grid, Conductor reduced the power to the chips by 25% for three hours, while maintaining acceptable computing performance. Emerald AI and its partners reported the results in a paper in Nature Energy in December 2025. The next trial forced the system to juggle surprise grid fluctuations without advance warning and redirect AI jobs from a data center in Virginia to a less busy one in Chicago. Then, in London, Conductor took the reins of equipment beyond the main GPU processors and faced a more complicated mix of fluctuations, including very short and long bouts of congestion—plus the notorious teakettle effect. The progress so far shows that flexibility can work, at least in some situations, but only a small fraction of operators have pursued it as yet. “We’re just in the beginning innings of the game,” says Jesse Jenkins, one of the authors of the 2025 Princeton study and cofounder of Firma, a startup that works on data-center flexibility. “People are recognizing that this is a potential solution. The motivation is there; there are some bespoke examples. But there’s no uniform solution set that’s the default option, which is where we need to get.” While data centers are going up across the US, no place on Earth comes close to the accumulated computing muscle in Northern Virginia’s Data Center Alley. The region is home to around 500 compute-crunching facilities, which represent 13% of the entire world’s capacity; the next two hot spots, Beijing and Oregon, contain 6% each. There are proposals to build hundreds more facilities in Virginia, but a government study found that the state’s electricity demand will increase 183% (around 26 gigawatts) by 2040 if they all go forward, and supporting even half would be difficult. The power-flexible data center that Emerald AI, Nvidia, Digital Realty, and their partners are building in the suburb of Manassas could demonstrate how data centers can squeeze the power they need out of existing capacity. The facility, slated to come online later this year, is intended to give Conductor the chance to manage power at the largest scale yet and to respond to conditions on a live grid for the first time. In the UK demonstration, Conductor managed a 130-kilowatt AI cluster; in Manassas, it will pull the strings of a 96-megawatt hyperscale AI factory.  Some degree of flex will play a key role as we transition away from fossil fuels and toward a future that has to juggle technologies like solar and wind power, batteries, and electric cars. For PJM, the Manassas facility points to a potential path through the current power crunch. “We think data-center flexibility, in different forms, will be essential for the reliable integration of data-center load over the short to mid term,” says Scott Baker, who manages demand-side markets at PJM.  But not all grid experts are so sanguine. PJM’s market monitor, which oversees the grid operator, says there are no workarounds when it comes to adding capacity. “The notion that large amounts of data-center load can be added without adding new generation is magical thinking,” says Joseph Bowring, an economist and the head of PJM’s market monitor since 1999. One problem, he says, is that there’s no way to guarantee that a data center will actually take less power when demand is high. That is, absent any legal or regulatory push for flexibility or compliance, the utility won’t be able to step in to help prevent, say, a blackout. Utilities can rely on resources like power plants, but they can’t control or rely on data centers. “They do not want to be fully interruptible,” Bowring says of the facilities. Stephen Empedocles, an advisor for technology companies, views flexibility as more of a tool than a silver bullet. “These approaches are excellent for improving grid reliability and getting more out of the infrastructure we already have,” he says, “but they are optimization tools.” They’re not substitutes for the “generation, transmission, and distribution expansion that will still be required,” he continues. Flexibility advocates agree that over the long term, whether or not AI continues to boom, electrification will drive a need for more generation and transmission. Some degree of flex will play a key role in using grid infrastructure better as we transition away from fossil fuels and toward a future that has to juggle technologies like solar and wind power, batteries, and electric cars. A report published by the International Renewable Energy Agency in January 2026 found that grids around the world will need three times as much flexibility in 2030 as they had in 2019—and 10 times as much by 2050—to balance increasing demand with fluctuating supplies of renewable energy.  The challenge of powering AI could provide just the spark we need to do the work of designing and building smarter, more flexible grids, says Coskun. “I think with a crisis like this, there’s no quick solution,” she says. “Sometimes a crisis like this creates an opportunity to do something differently.”  Amos Zeeberg is a freelance science and technology journalist based in Bucharest. He’s developing a book about technology networks, including electric grids.

At the end of a tense and scoreless first half of a soccer match between the English men’s team and rival Germany, millions of Brits let out a collective sigh and did what they so often do in moments of stress: They made tea. That wave of electric kettles clicking on, however, caused a different kind of stress: a huge and sudden increase in demand for electricity. But National Grid, which operates the local transmission network, was ready.

Just as those kettles started heating up, an AI program sent instructions to a data center in London to slow down some of the facility’s power-hungry chips. This reduction helped make sure there was enough supply to match demand, staving off potential blackouts or damage to electrical hardware. For data centers, which normally guzzle power without consideration for anyone or anything else’s needs, it was a radical departure.

It was also a simulation. In December 2025, engineers sought to test a new breed of data center built to be flexible about its electricity needs, so they re-created the energy demand facing the UK’s grid during a match from the 2020 Euro tournament. They wanted to see how their software, called Conductor, would have responded had it been online at the time.

Conductor is the signature product of Emerald AI, a firm based in Washington, DC, that’s part of a wave of companies trying to figure out whether data centers can work within the confines of the existing electric grid.

This year, Emerald is set to deploy Conductor in a new facility in the part of Virginia known as Data Center Alley, this time connected to the live grid. When overall demand spikes, Conductor will turn down the power used by the data center, while making sure its servers still carry out their timeliest and most important jobs. Emerald’s partners on the project—which include Nvidia and the giant data-center operator Digital Realty—bill it as one of the world’s first “power-flexible AI factories.”

Demonstrating that data centers can participate in this kind of give-and-take could ease what many tech leaders identify as the bottleneck in getting facilities online: It takes far longer to get approval for, construct, and connect new power plants than to build data centers. PJM, the grid operator in Virginia and the largest one in the US, for instance, needs eight years to bring new generation online, according to RMI, an energy research and advocacy group. “We need to solve the energy equation,” says Josh Parker, head of sustainability at Nvidia. “AI factory flexibility is the bridge between the incredible demand for AI and the immediate limitations of our energy grid.”

Speed, though, is only one of the issues. Once facilities do plug in, neighbors often criticize them for drawing too much electricity and contributing to rising prices. They say the data centers generate more noise than they do long-term jobs, contribute to pollution, and threaten to put people out of work. Organizers stalled over $150 billion worth of projects in 2025, according to Data Center Watch, and policymakers alert to the public mood are starting to impose limitations on development.

More than a dozen states are considering bans, and local moratoriums are in effect in places like Minneapolis and DeKalb County in Georgia. At the federal level, the GRID Act, a bipartisan bill in the US Senate, proposes to sever new data centers from public grids entirely. Some operators are already moving that way by trying to develop their own power generation.

Rather than rushing to build new power plants, companies could find part of the solution to the crunch right under our noses—or, more precisely, in the transmission lines under our feet and above our heads. The existing system operates near its full capacity during only a small number of high-demand hours throughout the year. This means, some grid experts argue, that if data centers can limit the power they draw during those stretches, they won’t need to wait for big infrastructure upgrades or build their own off-grid generation. 

Indeed, a growing number of studies have shown there could be plenty of power available for data centers that can flex. A widely discussed 2025 report from researchers at Duke University found that the US grid could offer an additional 76 gigawatts—about 5% of its entire capacity, and about enough to accommodate projected data-center growth in the US through 2030—to facilities that are willing to reduce their usage just 0.25% of the time. That’s about 22 hours a year. And when researchers from Princeton University and two grid-modernization companies looked at locations for new data centers in the PJM region, their report, which was funded by Google, found that a 500-megawatt facility capable of flexing for less than 1% of the year could reach full operation three to five years faster than one that’s inflexible. 

Flexible power connections could also help data centers address some of their PR problems. By decreasing their draw at times of grid stress, for instance, they could avoid diverting power from where it’s most needed, thus boosting stability. By using existing capacity, they might be able to reduce the need for new fossil-fuel power plants and spread fixed costs over more electricity users, pushing prices down. 

The AI power pinch is attracting resources and research into strategies for grid flexibility overall, which could help negotiate a tricky period: Taken together with electric vehicles, air-conditioning, and other sectors, data centers are helping drive what analysts predict will be a 25% increase in US electricity demand by 2030 compared with 2023 levels.

Ideally, flexibility gives grid operators more control over the flow of electrons, making them leaders of a harmonious ensemble rather than hostages to inflexible electricity requirements. That will help them manage demand spikes across the entire system and deal more effectively with the intermittent nature of renewables like wind and solar. “Demand flexibility is incredibly useful for power grids,” says Johanna Mathieu, a grid expert at the University of Michigan. “It helps reduce electricity costs and improve grid reliability.”

But while advocates see plenty of benefits, the concept brings complexity. For data centers, compromising on energy needs can be a hard sell. Flexibility requires utilities and grid operators, which tend to be operationally conservative, to change long-held practices. And some skeptics also say that flexibility distracts from the very real need to build more grid infrastructure faster, and could even pose risks to our electricity supply. 

Still, some technologists, grid operators, and utilities are hoping to show that flexibility works—not only in white papers or simulations but in real life. 


The poster children for data-center growth default toward inflexibility. Hyperscalers like Microsoft and Oracle have proposed enormous new centers, many of which would rely on off-grid, natural-­gas-burning power plants. When xAI wanted to speed up the buildout of the Colossus site outside Memphis, Tennessee, it rolled up with gas turbines on flatbed trucks. The facility, now in operation, is facing blowback from regulators and residents about the spike it’s causing in emissions and other pollution. In any case, there aren’t enough gas turbines worldwide to meet the demand from data-center operators. 

One big obstacle for anyone demanding a lot of power is that our grids are mostly rigid. They’re designed to supply enough power to meet total demand when it’s highest, even if that’s for only a relatively small number of hours a year. That conservative approach is a simple route to reliability, but it means that the grid has quite a bit of headroom. “The grid is already overbuilt by a lot. If you were an airline running at 30% utilization, you would not buy more planes,” says Amit Narayan, the cofounder and CEO of GridCare, a company developing flexibility technologies, referring to a 2025 Stanford study of transmission lines in western North America. “If you are running a grid at 30% utilization, there’s no scientific reason you can’t go to 60.” 

“If you were an airline running at 30% utilization, you would not buy more planes. If you are running a grid at 30% utilization, there’s no scientific reason you can’t go to 60.”

To be fair, the idea of flexibility isn’t entirely foreign to grid operators. For decades, they’ve practiced a technique called demand response: When it looks as if demand will get too close to supply, as it might during a heat wave when many people turn on the AC at the same time, they call large commercial or industrial facilities and ask them to shut down parts of their operations. This method can help avoid the need to fire up so-called peaker plants, which run on fossil fuels, but it’s slow, imprecise, and hard to scale.

In the 2000s, as the adoption of technologies like electric cars and solar panels presented new challenges, more internet-­connected grids also provided new means of flexibility. Virtual power plants, or VPPs, offered a smarter, faster, more granular alternative. Electricity customers ranging from factories to homeowners with smart thermostats, solar panels, or big batteries would allow the utility to adjust their draw to help meet demand—often getting paid for their (frequently unnoticed) trouble. 

After the generative AI boom began with the release of ChatGPT in 2022, some companies began to see flexibility as a way to get data centers set up more easily, efficiently, and affordably. If they bring AI money into existing grids and reduce or defer the need for expensive upgrades, data centers could actually help spread out fixed costs so as to lower rates for other users. A study from Duke University published this past February, for instance, found that flexibility could reduce rates by 0.5% to 2.8%

PETRA PÉTERFFY

The trick is figuring out how data centers, notorious power hogs, can keep operating when their flexible connections are throttled. Flexibility specialists envision three possible ways. The simplest is for the new data center to install on-site backup power storage or generation to tap when the grid is maxed out—at their own expense, of course.

A facility could also fill the gap by drawing on a VPP. The utility would turn down the electricity going to users who signed up for the VPP, and the data center would pay them for their flexibility. This method wouldn’t require any major infrastructure, but it would require the utility to have a big VPP program and to coordinate the exchange at a time when the grid was under stress. While VPPs exist to some extent in nearly 40 states, the rules governing them vary widely, and they are empowered to do more in some areas than in others. 

Finally, a data center could simply use less power at peak times. The conventional wisdom is that they won’t go for such limits, particularly when every number-­crunching server can feel like a goose potentially laying little golden eggs. But some experts are betting that the value of getting up and running quickly is enough to change their minds. “There is a clear and growing trend,” says Ayse Coskun, chief scientist at Emerald AI. “Operators are increasingly willing to trade some level of flexibility for faster grid interconnection.” 


GridCare, a startup based in Silicon Valley, was one of the first companies to use flexibility to get data centers online quickly. Instead of looking at grids only in worst-case scenarios when electricity demand is highest, the company analyzes the system under all conditions, explains CEO Narayan, who studied smart grids at Stanford. It feeds every part of the grid—including power plants, lines, substations, and homes—into a generative AI model that creates a “digital twin” for different grid configurations. It then picks out results that could unlock capacity while maintaining reliability, and it feeds those into another model trained on the physics of electrical components like resistors and capacitors to make sure they’re realistic.

GridCare found its first customer in the Silicon Forest, an area in the Pacific Northwest named for the trees that dominate the landscape and the IT industry that has more recently sprouted up there. The local grid needed more capacity to support more data centers. “Data centers wanted ‘speed to power,’” says Isaac Barrow, a manager of data-center relations at Portland General Electric, or PGE, the local power generator and distributor, “but transmission buildout is a long process that’s very costly.”

In 2024, Aligned Data Centers came to PGE wanting to expand its operation in Hillsboro, Oregon, and PGE followed a recommendation from GridCare. Aligned will install a 31-megawatt battery, set to be in service in May 2027, and decrease its draw by up to that amount when the grid becomes congested. Bundled with other flexibility measures, that battery has allowed PGE to increase the capacity it can offer Aligned and other nearby operators by 80 megawatts without any new power plants. Though the buildout of data centers in Hillsboro has faced plenty of pushback from locals, Barrow points out that it could have the knock-on effect of lowering costs for ratepayers, because it spreads out the tab.

Other companies are promoting different flavors of flexibility. Google has been moving processing loads from facilities in areas experiencing demand spikes to those in less stressed spots since 2023. It’s signed agreements with five utilities, including the Tennessee Valley Authority and Indiana Michigan Power, that add as much as a gigawatt of flexibility. 

Voltus, a major VPP provider across the US and Canada, markets a “bring your own capacity” program in which a data-­center company can fund a VPP nearby. The grid operator can use the VPP to decrease demand at busy times, and participants get a financial thank-you. “We can spin up new VPPs on the order of months,” says Emily Orvis, Voltus’s vice president of energy markets. In June, the company signed their first such data-center deal: a three-year plan in which Google will bankroll a VPP in the PJM interconnection.

Of all the approaches to flexibility, Emerald AI’s may be the most ambitious: asking data centers to dial into the grid’s needs. The company’s Conductor software, which can run on premises or in the cloud, builds on the research of chief scientist Coskun. Her group at Boston University showed in a pair of 2013 papers that a data center could watch the grid and help balance big power fluctuations, such as the intermittent effects of solar and wind power. By 2022, she and her colleagues had tested their methods on a cluster of 36 research servers and shown that the system could respect power limits without breaking the processes it was running. 

One of the most important questions for Conductor is deciding which AI processes can be slowed down to save energy without kneecapping performance. A lot of companies label their jobs by priority—a real-time chatbot query, for instance, might outrank something like a web search that’s part of a deep research project. When they don’t, Emerald AI tries to infer priority from the nature of the job. Conductor then analyzes the AI workload to determine how tweaking the power to a given processor will affect the performance and help meet the usage limits set by the grid operator.

“The performance curve changes for different kinds of workloads,” says Coskun. “Each AI job is going to have a different location on that curve. Our intelligence is figuring out where you are on that curve.” 

PETRA PÉTERFFY

Last year, Emerald AI began assessing the technology’s readiness for real-world use in a series of tests, raising the difficulty each time. The trials were carried out in partnership with the Data Center Flexible Load Initiative—a collaboration among tech companies like Google and Nvidia, utilities like Duke Energy, and grid operators like PJM that aims to help establish a repeatable framework for power-­flexible data centers.

The first challenge was in Phoenix, a fast-growing computing hub. For the test, Conductor took control of a group of server racks laden with 256 Nvidia A100 GPUs—hardware that can use about as much power as around 170 US homes. When presented with a simulation of a busy grid, Conductor reduced the power to the chips by 25% for three hours, while maintaining acceptable computing performance. Emerald AI and its partners reported the results in a paper in Nature Energy in December 2025.

The next trial forced the system to juggle surprise grid fluctuations without advance warning and redirect AI jobs from a data center in Virginia to a less busy one in Chicago. Then, in London, Conductor took the reins of equipment beyond the main GPU processors and faced a more complicated mix of fluctuations, including very short and long bouts of congestion—plus the notorious teakettle effect.

The progress so far shows that flexibility can work, at least in some situations, but only a small fraction of operators have pursued it as yet. “We’re just in the beginning innings of the game,” says Jesse Jenkins, one of the authors of the 2025 Princeton study and cofounder of Firma, a startup that works on data-center flexibility. “People are recognizing that this is a potential solution. The motivation is there; there are some bespoke examples. But there’s no uniform solution set that’s the default option, which is where we need to get.”


While data centers are going up across the US, no place on Earth comes close to the accumulated computing muscle in Northern Virginia’s Data Center Alley. The region is home to around 500 compute-crunching facilities, which represent 13% of the entire world’s capacity; the next two hot spots, Beijing and Oregon, contain 6% each.

There are proposals to build hundreds more facilities in Virginia, but a government study found that the state’s electricity demand will increase 183% (around 26 gigawatts) by 2040 if they all go forward, and supporting even half would be difficult. The power-flexible data center that Emerald AI, Nvidia, Digital Realty, and their partners are building in the suburb of Manassas could demonstrate how data centers can squeeze the power they need out of existing capacity. The facility, slated to come online later this year, is intended to give Conductor the chance to manage power at the largest scale yet and to respond to conditions on a live grid for the first time. In the UK demonstration, Conductor managed a 130-kilowatt AI cluster; in Manassas, it will pull the strings of a 96-megawatt hyperscale AI factory. 

Some degree of flex will play a key role as we transition away from fossil fuels and toward a future that has to juggle technologies like solar and wind power, batteries, and electric cars.

For PJM, the Manassas facility points to a potential path through the current power crunch. “We think data-center flexibility, in different forms, will be essential for the reliable integration of data-center load over the short to mid term,” says Scott Baker, who manages demand-side markets at PJM. 

But not all grid experts are so sanguine. PJM’s market monitor, which oversees the grid operator, says there are no workarounds when it comes to adding capacity. “The notion that large amounts of data-center load can be added without adding new generation is magical thinking,” says Joseph Bowring, an economist and the head of PJM’s market monitor since 1999.

One problem, he says, is that there’s no way to guarantee that a data center will actually take less power when demand is high. That is, absent any legal or regulatory push for flexibility or compliance, the utility won’t be able to step in to help prevent, say, a blackout. Utilities can rely on resources like power plants, but they can’t control or rely on data centers. “They do not want to be fully interruptible,” Bowring says of the facilities.

Stephen Empedocles, an advisor for technology companies, views flexibility as more of a tool than a silver bullet. “These approaches are excellent for improving grid reliability and getting more out of the infrastructure we already have,” he says, “but they are optimization tools.” They’re not substitutes for the “generation, transmission, and distribution expansion that will still be required,” he continues.

Flexibility advocates agree that over the long term, whether or not AI continues to boom, electrification will drive a need for more generation and transmission. Some degree of flex will play a key role in using grid infrastructure better as we transition away from fossil fuels and toward a future that has to juggle technologies like solar and wind power, batteries, and electric cars. A report published by the International Renewable Energy Agency in January 2026 found that grids around the world will need three times as much flexibility in 2030 as they had in 2019—and 10 times as much by 2050—to balance increasing demand with fluctuating supplies of renewable energy. 

The challenge of powering AI could provide just the spark we need to do the work of designing and building smarter, more flexible grids, says Coskun. “I think with a crisis like this, there’s no quick solution,” she says. “Sometimes a crisis like this creates an opportunity to do something differently.” 

Amos Zeeberg is a freelance science and technology journalist based in Bucharest. He’s developing a book about technology networks, including electric grids.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Practical quantum computers are over a decade away, says NEC

A practical, commercial quantum computer is over a decade away, executives at Japanese IT services company NEC are reported as saying. That’s why, according to Japanese news publication The Mainichi, company has pulled the plug on its plans to develop a quantum computer — although it will still continue research

Read More »

Huawei aims to deliver faster AI chips, faster

Huawei is accelerating its AI chips development, bringing forward the release of the next two models in the family powering its AI computing clusters by three to nine months. Its Ascend 960 chip family is a major component of supercomputing portfolio. It now plans to release the Ascend 960DT in

Read More »

Energy Department Announces $99 Million for 21 Projects to Advance U.S. Geothermal Energy Development

WASHINGTON—The U.S. Department of Energy (DOE) today announced more than $99 million for 21 projects selected to advance geothermal energy development across the United States. The projects will conduct field-scale tests of next-generation geothermal technologies and exploration drilling to characterize and potentially confirm promising geothermal resources.  Thanks to President Trump’s leadership, the Energy Department is advancing American geothermal innovation to unlock the nation’s abundant domestic energy resources. Geothermal can provide reliable, around-the-clock power to help meet growing demand while strengthening U.S. energy security. “These projects will empower American innovators to unlock the tremendous geothermal resources beneath our feet,” said DOE Under Secretary of Energy Kyle Haustveit. “Under President Trump’s leadership, we’re advancing next-generation geothermal technologies that can lower costs, strengthen American energy dominance, and turn more of our vast domestic geothermal resources into reliable and affordable power.” The 21 projects will advance geothermal development in two key areas. Five projects will conduct field-scale enhanced geothermal systems (EGS) tests to validate technologies under real-world conditions, while 16 additional projects will conduct exploration drilling to identify and characterize promising next-generation geothermal resources. Together, these efforts will help reduce technical and development risk and provide the information needed to support future commercial projects and investment.   Data generated by these projects will be publicly available through DOE’s Geothermal Data Repository (GDR), giving industry, researchers, and other stakeholders access to information from the field tests and geothermal exploration activities. Making these data available can extend the value of the projects beyond individual sites by helping inform future technology development and geothermal exploration across the industry.  Learn more about the selected projects here.  Selection for award negotiations is not a commitment by DOE to issue an award or provide funding. Before funding is issued, DOE and the applicants will undergo a negotiation process, and DOE may cancel negotiations and rescind the

Read More »

INA commissions new delayed coker at Rijeka refinery

Croatia’s INA Industrija Nafte DD has started up a new delayed coking unit (DCU) at its 90,000-b/d Rijeka refinery along the northern part of the Adriatic Sea, marking a major milestone in the refinery’s upgrading project. Following mechanical completion and commissioning, INA introduced feedstock into the DCU on Sept. 1, beginning production, majority owner MOL Group said in a release Sept. 21. The unit has operated continuously since startup and has reached about 70% of design capacity, the company said. The DCU—which  converts heavy refinery residues into higher-value products—has produced all key products at required quality and is anticipated to increase diesel production by as much as 30% from the same crude volume. MOL Group said the new DCU unit—once fully operable—also will eliminate Croatia’s need to import vacuum gas oil (VGO). The Rijeka refinery upgrade represents an investment of nearly €700 million, which is included in a combined €1.3-billion joint investment by INA and MOL Group in refining and logistics modernization during the past 12 years. “The start-up of the new unit went really well,” said Zsuzsanna Ortutay, president of INA’s management board, adding that the DCU would improve the sustainability and profitability of INA’s refining business while supporting energy supply in Croatia and the surrounding region. INA  plans to increase throughput and optimize process performance at the new unit gradually, with stable operation anticipated by yearend, followed by final plant performance testing and project closeout activities. Rijeka DCU project background INA awarded a lump-sum, turnkey engineering, procurement, and construction contract for the project to Maire Tecnimont SPA subsidiary KT-Kinetics Technology SPA in December 2019. The contract covered a new delayed coking complex with coke handling and ship-loading facilities, a sour-water stripper, and amine recovery units. It also included modifications to the existing hydrocracker, sulfur recovery unit, utilities, and

Read More »

Oil prices retreat as Middle East supply concerns ease amid diplomatic talks

Oil prices fell on Monday, Sept.21, with Brent extending its retreat from recent highs, as recovering Saudi crude exports and hopes for renewed US-Iran diplomacy eased fears of an immediate Middle East supply crunch. Brent crude futures and US West Texas Intermediate (WTI) crude dipped below $100/bbl to their lowest since Sept. 9. The move extends a four-session retreat from the recent surge in crude prices as traders reassess how severely regional conflict is constraining physical oil flows. Despite the continued uncertainty in the Middle East, news of a major rebound in Saudi crude oil exports in September weighed on prices. Saudi Arabia has increased shipments through the Strait of Hormuz to compensate for disruptions to its East-West pipeline following Houthi attacks on Saudi energy infrastructure. Saudi crude flows through the strait have averaged roughly 2.9 million b/d over the past 6 days, compared with about 700,000 b/d in August, according to satellite data cited by JPMorgan analysts. US Central Command Commander Admiral Brad Cooper confirmed on Sept.19 that, thanks to US naval escorts and mine-clearance efforts, oil and LNG shipments through the Strait of Hormuz in the past 2 weeks reached the highest level in 6 months. The recovery in Gulf exports has helped ease fears that attacks on Saudi infrastructure would translate into a prolonged loss of barrels from the global market. Meanwhile, investors are closely monitoring signs of potential diplomatic progress between Washington and Tehran during this week’s UN General Assembly. US President Donald Trump has expressed a willingness to meet with Iranian President Masoud Pezeshkian, while Iran has reportedly conveyed the conditions for resuming negotiations. Expectations that talks could eventually reduce regional tensions have removed some of the geopolitical risk premium that pushed crude prices higher earlier this month. Still, physical oil markets remain strained. Middle Eastern producers

Read More »

Trump Administration Moves to Keep Indiana Coal Plants Operating to Support Grid Reliability

WASHINGTON—U.S. Secretary of Energy Chris Wright issued emergency orders to keep two Indiana coal plants operational to ensure Americans in the Midwest region of the United States have continued access to affordable, reliable, and secure electricity. The orders direct the Northern Indiana Public Service Company (NIPSCO), CenterPoint Energy, and the Midcontinent Independent System Operator, Inc. (MISO) to take all measures necessary to ensure specified generation units at both the R.M. Schahfer and F.B. Culley generating stations in Indiana are available to operate. Certain generation units at these coal plants were scheduled to shut down at the end of 2025.  The orders will minimize the risk of unnecessary blackouts for the American people. Since the U.S. Department of Energy’s (DOE) original orders were issued on December 23, 2025, the Schahfer and Culley coal plants have proven critical to MISO’s operations, operating during periods of high energy demand and low levels of intermittent energy production, including during Winter Storm Fern.   “Forcing reliable, dispatchable coal generation off the grid would compromise energy reliability and needlessly raises energy costs for Americans,” said Energy Secretary Wright. “Midwestern families should not be forced to pay the price for the misguided energy subtraction policies of the past. They deserve affordable, reliable, and secure energy, regardless of the wind blowing or the sun shining.” Thanks to President Trump’s leadership, coal generating plants across the country are being saved from premature retirement. For example, in 2025, more than 17 gigawatts of coal power electricity generation were saved from going offline.  The availability of R.M. Schahfer and F.B. Culley generating stations to operate will continue to be an asset to maintain reliability in the MISO region and is necessary to address elevated reliability risks in that region during extreme weather and reduce the risk of power outages that could threaten public health and safety. As

Read More »

Energy Secretary Secures Carolinas’ Grid Amidst Hot Weather Conditions

WASHINGTON—The U.S. Department of Energy (DOE) issued an emergency order to mitigate the risk of blackouts in the Carolinas amid hot weather conditions. Issued pursuant to Section 202(c) of the Federal Power Act, the order authorizes Duke Energy Carolinas, LLC (Duke) to dispatch specified resources and to order their operation as needed to maintain reliability. The order also authorizes Duke, in collaboration with its Transmission Owners, to direct backup generation resources to operate as a last resort before declaring an Energy Emergency Alert (EEA) 3 or during an EEA 3. This order was issued pursuant to an application from Duke submitted on September 18, 2026. “Today’s order will help secure reliable electricity access for millions of American families and businesses across North and South Carolina by making additional power generation, including backup power, available to use as needed,” said U.S. Secretary of Energy Chris Wright. “It should come as no surprise that during the end of summer and early fall, there are fewer hours of daylight—and therefore, less power generation from solar power. The North American Electric Reliability Corporation and others have warned of the potential dangers late summer temperature spikes can pose to the grid when leaders prematurely retire reliable power sources. While past leaders’ energy subtraction policies have made the grid more vulnerable to blackouts when the sun doesn’t shine or the wind doesn’t blow, this administration remains committed to using every available tool to prevent blackouts.”  DOE estimates more than 35 GW of unused backup generation remains available nationwide.  The order is in effect upon issuance on September 18, 2026, through September 21, 2026. 

Read More »

Enbridge launches open season for West Texas Express natural gas pipeline

Enbridge has launched a non-binding open season for its proposed 2-bcfd West Texas Express (WTX) natural gas pipeline project, designed to transport Permian basin supply west from the Waha area to markets in and around El Paso, Tex. The proposed project responds to growing demand for reliable natural gas supplies from proposed power generation, utilities, generators, and industrial customers such as data centers across west Texas and downstream markets in Mexico, New Mexico, and Arizona, Enbridge said. WTX is currently expected to include more than 150 miles of new 42-in. OD pipeline. The project could also include laterals serving Hudspeth County, Tex., and delivery points at the US-Mexico border. Enbridge said WTX can be designed to connect with existing pipeline infrastructure based on customer requirements identified through the open season. Final capacity, routing, receipt and delivery points, and system design will be informed by market interest. Subject to securing sufficient commercial support and obtaining required approvals, Enbridge is targeting a fourth-quarter 2029 in-service date. The open season will close at 5 p.m. CDT, Sept. 25, 2026. Enbridge last week agreed to acquire Tallgrass Energy LP’s crude oil business for $2.55 billion in cash.

Read More »

Data Centre West 2026: Alberta Moves From Data Center Ambition to Execution

Firm Power Is an Architecture That brought the morning back to its recurring problem: What counts as available power? During the “Solving for Power” panel, moderator Lillian Kasa of Metlen Energy & Metals argued that data centers cannot operate on announcements. They need reliable electricity delivered on a schedule and backed by a commercial structure that can be financed. Margarita Patria of Charles River Associates made the distinction even sharper. Firm power is not merely generation. It is generation, transmission and fuel availability working together. Todd Detling of FortisAlberta added an important Alberta-specific qualification. Despite perceptions that the province had substantial transmission capacity available for new development, FortisAlberta is encountering constraints, particularly around the Edmonton and Calgary fringes. At the distribution level, the demand is already material. Detling said FortisAlberta has connected nearly 80 MW of data center load over the past several years, has approximately another 80 MW in the build queue, and has received roughly 300 MW in additional requests. Those smaller increments matter in a market dominated rhetorically by gigawatt announcements. They are another indication that developers are searching for power pathways they can execute now. AI Is Not Just a Bigger Load Tesla’s Sean Jones added another technical wrinkle: AI training loads can change extremely quickly. Data center power planning traditionally focuses heavily on annual consumption, peak demand and hourly load. GPU clusters can create significant changes at the second or even sub-second level. Jones described AI training demand falling from full load to around 30% in less than a second. That kind of movement can be difficult for onsite turbines and reciprocating generators to follow and potentially disruptive to the grid. Battery energy storage is therefore taking on a different role. The familiar data center battery story is backup power. The emerging AI story is

Read More »

Local AI is getting small enough to make every app multilingual

On-device translation used to mean a separate model for every language you wanted to support. English to French, English to German, and so on. However, that becomes unsustainable at a global scale when you’re talking about thousands of possible language pairs. Add to that the fact that most developers have to either send translation requests to the cloud to get fast, accurate results, or keep it local with restricted language support. Tether’s AI Research team has developed a family of multilingual translation models, TranslatePsy-EuroNano, that each support nine European languages, with deployment built around a pair of multilingual models rather than separate bilingual models for every language pair. What makes this possible Supporting a full European market on-device has previously meant bundling dozens of separate model files, but this is impractical for mobile apps and those building them. Tether AI’s multilingual open‑source edge translation models set the standard for efficiency, quality, and speed. For developers, the possibilities are endless. Using English as a pivot, the models remain comparable to Mozilla Firefox’s Bergamot-based translation system while dramatically reducing the size of on-device translation. At its smallest tier, Tether’s deployment is 17.6 times smaller while maintaining comparable translation quality. Tether’s deployment takes up 36MB to 89MB, depending on the tier you use. By comparison, the equivalent Firefox setup requires 18 separate bilingual models totaling 633MB to provide the same language coverage. The models are small enough to run efficiently on edge devices while supporting nine European languages from a single multilingual deployment, making multilingual experiences practical for a much wider range of software. Potential applications include travel and navigation apps, educational platforms that present lessons and resources on-device. The models are also designed for academics and researchers. Because the weights are openly available, researchers can fine-tune them for specialized domains, like customer

Read More »

AI Infrastructure Is Redrawing the Data Center Services Landscape

For gigawatt-scale AI developments, the developer may be involved with substations, transmission interconnections, generation plants, batteries or other behind-the-meter infrastructure long before servers arrive. Solaris now describes its overall portfolio as including generation, distribution, installation and commissioning, aftermarket support, and operations and maintenance. The arrival of companies with roots in energy and heavy industrial services suggests that the data center supplier base itself is changing as projects begin to resemble large industrial infrastructure developments. The Pattern Extends Across the Services Stack The transactions involving T5, Limbach, JK Technology Services and Solaris are hardly isolated. A wider wave of acquisitions and partnerships is pushing equipment manufacturers, contractors, engineering firms and specialist service providers toward broader roles across the data center lifecycle. Vertiv provided perhaps the clearest parallel in September, announcing an agreement to acquire UtilityInnovation Group for approximately $1.45 billion in cash, with additional consideration tied to performance. UIG brings microgrid controls, onsite-generation orchestration, specialized switchgear and behind-the-meter power architecture. The deal also extends a broader 2026 acquisition push by Vertiv that has added liquid-cooling specialist Strategic Thermal Labs, chiller manufacturer ThermoKey and prefabricated infrastructure provider Bmarko as the company builds out more of the AI data center infrastructure stack. Vertiv described the move as extending its portfolio upstream from the critical power and cooling systems inside the facility toward the grid interconnection and onsite generation itself — effectively creating a path from power source to chip. Days later, Flex announced a $4.4 billion agreement to acquire EPC Power, adding grid-forming and power-conversion technology designed for data centers, utility-scale energy storage and microgrids. EPC Power’s platform includes rectifiers and DC-DC conversion for emerging 800-volt data center architectures, with solid-state transformer development also planned. The company says it has more than 15 GW deployed across 62 countries and expects its annual U.S.

Read More »

From Announcements to Delivery: What Separates Real AI Data Center Projects From the Rest

The AI infrastructure market has become very good at announcing gigawatts. Delivering them is another matter. That distinction framed one of the closing sessions of Day 1 at the Data Center Frontier Trends Summit 2026 (Aug. 4-6), where Sean Farney, vice president of data center strategy at JLL and a member of the Data Center Frontier Editorial Advisory Board, moderated a discussion on why some AI data center projects advance from concept to construction while others remain little more than ambitious site plans. Farney was joined by Lawrence Vo, vice president of M&A and capex at Csquare; John Day, chief commercial officer at CleanArc Data Centers; Justin Loth, executive director of power development at Provident Data Centers; and Roshan Shah, co-founder and CEO of Decimal Digital. The question Farney put before the group was straightforward: amid a market moving at what he called “the speed of light,” what separates the developers that actually get projects done from those that do not? The answers repeatedly came back to the same point. In the current market, land, capital and an announcement are no longer enough. Developers have to prove that power is deliverable, infrastructure is ready, regulatory processes are moving, communities are receptive, talent is available and the commercial model can withstand changing conditions. A Gigawatt on Paper Is Not a Gigawatt of Capacity For Loth, who spent roughly 15 years on the utility side before joining Provident, the scale of current data center proposals alone should force the industry to think differently about what constitutes a credible project. Before the hyperscale and AI expansion, he noted, gigawatts were a measure more commonly associated with cities than individual loads. “A 3.5 gigawatt campus,” Loth said, is roughly equivalent to the native load of Austin or San Antonio. That scale makes the distinction

Read More »

The Future of Data Centers: Biomimicry and Community-Centric Design

As a result, Microsoft has said six additional data centers planned in the region are being designed around biomimicry principles rather than treating landscaping as something added after the engineering work is finished. The change, from landscaping as decoration to ecology as a design input, is now being applied elsewhere. There is already a significant US example, set in Mecklenburg County, Virginia, where Microsoft originally announced the Chase City Conservancy in 2022, as part of a data center development south of Chase City. The completed project, which opened in April 2025, protects more than 230 acres from development. It includes more than eight acres of wetlands, over 16,300 linear feet of restored streams, 185 acres of native pollinator habitat, more than 25,000 planted trees and over three miles of publicly accessible walking trails. Local environmental organizations helped shift the design away from what the company describes as a more conventional recreational area toward biodiversity and habitat conservation illustrating the community-engagement side of Microsoft’s model, which, given the current temperature of such relationships, can’t be understated. For data center developers, that may be as important as the ecological results. Community impact is no longer being evaluated on just tax revenue and jobs. Turning portions of a site into protected wetlands, forests, trails or habitat potentially creates a visible local benefit in ways that renewable-energy contracts hundreds of miles away cannot. Microsoft’s commitment to the local community has been led by their Community First AI Infrastructure Plan announced in January 2026. Wetlands in Wisconsin, Screening in Georgia At Microsoft’s massive Mount Pleasant, Wisconsin, AI data center development, the company is working with the Root-Pike Watershed Initiative Network on restoration projects involving wetlands, native prairie and forested riparian buffers. One element involves returning previously straightened streams to more natural, winding channels, improving aquatic

Read More »

Axelera Europa targets enterprise data centers with far more efficient AI

Software is still the gatekeeper Axelera In terms of software enablement, Axelera’s Voyager SDK spans its existing Metis products and the new Europa architecture, providing a common environment across embedded, edge and server deployments, with support for a multitude of computer vision models, LLMs, VLMs, diffusion models, speech and other AI workloads. To automate setup, Axelera’s Voyager Wingman uses natural-language prompts to help developers create or port inference pipelines, while AxeleraScript, or AxScript, provides a Python-enabled domain-specific language with lower-level AIPU control for custom operators and transformer models. This could prove every bit as important as Europa’s performance and efficiency. Enterprises already have models, development environments and application stacks. Extensive rewriting or specialized expertise adds development and operational costs that can quickly undermine savings on hardware and power.

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »