Stay Ahead, Stay ONMINE

PORTS-Pike Takes Shape as an 8-GW AI Infrastructure Model

Back on March 31, 2026, we discussed we discussed SoftBank and SB Energy’s plans to redevelop the former Portsmouth Gaseous Diffusion Plant site near Piketon as a 10-GW artificial intelligence data center campus supported by almost an equal amount of new power generation. At the time, the plan called for as much as 10 GW […]

Back on March 31, 2026, we discussed we discussed SoftBank and SB Energy’s plans to redevelop the former Portsmouth Gaseous Diffusion Plant site near Piketon as a 10-GW artificial intelligence data center campus supported by almost an equal amount of new power generation. At the time, the plan called for as much as 10 GW of new generation, including 9.2 GW of natural gas capacity, along with approximately $4.2 billion of high-voltage transmission infrastructure developed with AEP Ohio. An initial 800-MW data center phase was targeted for service in 2028.

The March story was notable because Pike County appeared to offer a preview of a new model for building hyperscale infrastructure: develop the generation, transmission and data center simultaneously rather than wait for an increasingly congested regional grid to deliver multiple gigawatts of capacity. Not to mention the reuse of a brownfield site with the encouragement of the federal government.

Since then, almost every important part of the project has moved forward, and on August 17, the most consequential missing pieces fell into place.

NVIDIA announced that it will become the exclusive AI compute infrastructure provider for the PORTS-Pike Technology Campus. OpenAI will be the data center customer, signing a 20-year lease with SB Energy for approximately 8 GW of IT capacity. NVIDIA will invest another $1.5 billion in SB Energy and provide credit support for the land, power and shell infrastructure behind an initial 4.25 GW of IT load, with an option covering approximately another 3.75 GW.

The Securities and Exchange Commission filing accompanying the announcement makes the financial commitment even more significant. NVIDIA disclosed that its aggregate payment obligation associated with its initial commitment is capped at $105 billion. That is not a conventional capital commitment to spend $105 billion building the campus, nor is it simply a guarantee of OpenAI’s rent. Rather, it is a contingent residual-value guarantee designed to protect the infrastructure owners if specified OpenAI payment or insolvency events occur.

The project has become a case study in how the AI industry may finance infrastructure measured not in hundreds of megawatts, but in multiple gigawatts.

From a Power Plan to an AI Infrastructure Stack

When DCF examined PORTS-Pike in March, many of the physical pieces were already visible; SB Energy was the developer. SoftBank was behind the investment strategy. DOE was making federal property associated with the former Portsmouth uranium enrichment complex available for redevelopment. AEP Ohio was working on transmission infrastructure. A massive natural gas generation program was contemplated, and an initial 800-MW phase was moving toward construction.

At that time, there was no publicly committed end user for the full campus. OpenAI’s relationship with SoftBank and the broader Stargate initiative made it an obvious possibility, but the Piketon development had not been formally established as an OpenAI campus in DCF’s March reporting.

The August 17 announcement establishes a very clear division of responsibilities:

·         SB Energy will build, own and operate the data center infrastructure.

·         OpenAI will occupy approximately 8 GW-IT under a 20-year lease.

·         NVIDIA will supply the exclusive AI computing platform and is also putting its balance sheet behind a large portion of the project’s land, power and shell infrastructure.

·         DOE provides an important component of the real-estate and redevelopment framework

·         AEP Ohio is developing the major transmission expansion needed as the project scales.

Pike County is evolving from a data center development into an integrated AI industrial ecosystem. Land, electrical generation, transmission, data center construction, compute architecture, tenant demand and credit support are being assembled as parts of the same system. That may ultimately prove more important to the data center industry than the headline 10-GW number.

NVIDIA’s $105 Billion Backstop Changes the Risk Equation

The most striking detail of the August announcement is buried in the financial structure. NVIDIA’s SEC filing says that the company’s aggregate payment obligations for its initial PORTS-Pike commitments are capped at $105 billion. But understanding what NVIDIA has actually agreed to do is essential.

OpenAI remains the tenant. The NVIDIA obligations come into play under defined trigger events, including an OpenAI insolvency that results in lease default or OpenAI’s failure to make required lease payments.

Under those circumstances, NVIDIA would generally cover the difference between a guaranteed minimum lease value and the money recovered through a replacement lease or sale of the affected assets. NVIDIA also has remedies that could include assuming a lease, helping relet the capacity or facilitating a sale. OpenAI, meanwhile, has agreed to reimburse and indemnify NVIDIA for amounts NVIDIA actually pays under the arrangements.

That makes the $105 billion figure a maximum contingent exposure, not a $105 billion check being written to SB Energy today.

Nevertheless, the structure is important for financing the campus. This is because one of the fundamental problems facing multi-gigawatt AI development is that infrastructure has to be financed years before the computing capacity begins producing revenue.

Developers have to acquire land, order transformers and switchgear, build substations, secure turbines, construct transmission, develop cooling infrastructure and erect buildings well before racks of GPUs can be installed.

Someone has to take that development risk.

At PORTS-Pike, NVIDIA is effectively using the strength of its balance sheet to reduce some of the long-term credit risk associated with building infrastructure for OpenAI. That is a notable expansion of NVIDIA’s role in the AI infrastructure market.

The company is no longer simply waiting for developers to build data centers and then sell GPUs into them. NVIDIA describes land, power and shell capacity, or LPS, as a strategic resource and says it is applying some of the same supply-chain disciplines used to secure semiconductor manufacturing capacity to securing physical AI infrastructure. That is a significant shift for the data center industry.

The Campus Is Now an NVIDIA AI Factory

NVIDIA says PORTS-Pike will use its full-stack DSX AI factory platform, including GPUs, CPUs and networking. The initial NVIDIA-backed deployment is designed around 4.25 GW of IT capacity, with NVIDIA retaining the ability to expand its involvement across the remainder of the approximately 8-GW OpenAI commitment.

No specific future GPU generation needs to be assigned to all that capacity today. In a project scheduled to develop in phases for years, the underlying accelerator technology will change repeatedly. That is why the DSX architecture matters.

Rather than treating the building and IT hardware as separate engineering exercises, NVIDIA’s AI factory approach attempts to coordinate compute, networking, power, cooling, facilities and software as an integrated platform.

PORTS-Pike looks increasingly different from the classic hyperscale campus in which a developer builds a relatively standardized shell and the tenant determines the equipment installed inside it. And at this scale, the facility itself becomes part of the computing architecture.

The size difference between the project’s electrical infrastructure and usable IT load is worth noting. The overall development continues to contemplate approximately 10 GW of new power generation while OpenAI’s announced commitment is approximately 8 GW of IT capacity. The project sponsors have not simply equated generating nameplate capacity with usable rack power.

From 800 MW to 8 GW

The first approximately 800 MW is expected to become available beginning in 2028. OpenAI says that initial phase can rely largely on existing AEP electrical infrastructure. Beyond that initial tranche it becomes considerably more complicated.

Later phases require new power plants, transmission infrastructure and additional construction. OpenAI specifically acknowledges that the broader development remains conditioned on infrastructure availability, permitting, environmental reviews and financing. That caveat reflects the reality of development at this scale.

The campus is expected to grow through multiple phases, with OpenAI describing a six-year construction program running through 2032. For the data center industry, that distinction is critical whenever gigawatt-scale announcements are evaluated. The contract may be measured in gigawatts. The physical deployment still happens transformer by transformer, substation by substation and building by building.

AEP’s Transmission Plan Takes Shape

One of the biggest changes since the original DCF coverage is that the $4.2 billion transmission plan is moving from concept into defined routing, engineering and regulatory review. AEP Ohio’s Piketon Area Improvements Project now includes a proposed Baku Substation in Pike County near Wakefield Mound Road and roughly 50 miles of new 765-kV transmission extending from Baku to the Gavin Substation near Cheshire in Gallia County.

AEP says the facilities are specifically required to serve the planned data center campus. And the company also continues to emphasize that the data center customer will pay the transmission investment required to serve the site, rather than shifting those costs into transmission rates paid by other Ohio customers.

That cost allocation has become increasingly important politically as communities and utility regulators across the country wrestle with the impact of large data centers on electricity rates.

At Pike County, the developers are attempting to make “pay your own way” part of the project’s identity. AEP conducted public meetings during the spring and has since selected a preferred transmission route following field surveys and public feedback. The project still requires approval from the Ohio Power Siting Board.

The scale of the transmission line illustrates what makes PORTS-Pike different from most data center projects. A 765-kV line is bulk-power infrastructure. The campus is not simply connecting another load to a local utility substation. Its development is forcing the construction of grid infrastructure normally associated with major power stations and interstate power transfers.

PORTS-Pike Enters the FAST-41 Permitting Process

Federal permitting has also taken a significant step since the March DCF article. In June, the Federal Permitting Improvement Steering Council announced that the PORTS Technology Campus had been accepted for coverage under the federal FAST-41 permitting program.

It became the first project listed under FAST-41’s high-performance computing, advanced computer hardware and software sector. The U.S. Army Corps of Engineers is serving as the lead federal permitting agency, with other federal agencies participating in the review.

FAST-41 does not waive environmental laws or automatically approve a project. Instead, it coordinates federal reviews, publishes milestones and attempts to keep complex projects involving multiple federal agencies on a more predictable schedule.

That distinction will be important at PORTS-Pike because the development combines data centers, wetlands issues, federal property redevelopment, transmission facilities, new generating plants and other infrastructure.

The federal permitting record reflects different layers of the larger development. The project-specific FAST-41 dashboard currently describes a roughly 1,300-acre private-land footprint adjacent to the DOE Portsmouth site and references two data center buildings with associated infrastructure. The Permitting Council’s broader project portfolio, however, describes the Portsmouth development across approximately 2,700 acres of private land, while OpenAI says the overall project spans private land and remediated land controlled by DOE.

The published federal permitting schedule has targeted late December 2026 for completion of key portions of the current environmental review and permitting process. Fast-track status does not mean frictionless permitting.

Local reporting in July indicated that Ohio EPA determined a Section 401 water-quality certification filing associated with the project was incomplete and requested additional wetlands, aquatic-resource, endangered-species and alternatives information before continuing its review.

That was not a permit denial. It was, however, an early reminder that even a nationally prioritized AI project must navigate detailed environmental documentation before construction can advance across every portion of the property.

The 9.2-GW Gas Plan Is Beginning in Smaller Pieces

Perhaps the most important power-development update involves the proposed natural gas generation. The headline plan remains enormous: at least 10 GW of new generation supporting the technology campus, including approximately 9.2 GW of natural gas generation. The official PORTS-Pike project site continues to describe roughly $33 billion associated with the gas-generation program. The regulatory path is much more incremental. Portsmouth Gas DevCo is currently advancing the PORTS Energy Center, described as an initial natural gas generating project of up to approximately 2 GW using simple-cycle and combined-cycle technology.

The developer’s present schedule calls for first-phase construction to begin during the first quarter of 2027, followed by phased commercial operations beginning in the third quarter of 2028. The plant will require a Certificate of Environmental Compatibility and Public Need from the Ohio Power Siting Board.

The 9.2-GW natural-gas figure remains the long-range campus vision. The current approximately 2-GW PORTS Energy Center represents a more immediate, permit-level generation project. It is another example of the gap between announcing a 10-GW AI campus and actually constructing one.

Power plants must be permitted. Turbines must be procured. Pipelines must be built or expanded. Transmission has to arrive at the right locations. Generation and data center schedules then have to converge within months rather than years.

Water and Cooling Plans Become More Specific

Water was another subject left relatively undefined during the project’s initial announcement, but  OpenAI has now supplied more detail.

The company says PORTS-Pike will use a closed-loop, air-cooled cooling design intended to recirculate water rather than continuously consume the volumes associated with traditional evaporative cooling towers. After the initial system fill, OpenAI says ongoing water consumption should be comparable to that of an office building supporting a similar number of people.

The project expects to use an existing DOE water system at the site while helping fund new local water infrastructure. OpenAI has also said it will publish projected water consumption once the final site design is complete.

The Jobs Forecast Has Grown Dramatically

The economic-development promises surrounding PORTS-Pike have also expanded. The initial March announcements spoke of more than 10,000 construction jobs and more than 2,000 permanent operating jobs. The latest OpenAI and project materials now forecast approximately 35,000 construction jobs over the six-year buildout through 2032 and 2,500 long-term operating positions. Those numbers should not be interpreted as 35,000 people working simultaneously at the site. They represent jobs associated with the extended construction program.

Still, even spread across years, the labor requirement is substantial for Appalachian Ohio.

OpenAI says the PORTS-Pike Campus has signed a memorandum of understanding with North America’s Building Trades Unions and plans to work with the Ohio State Building and Construction Trades Council, apprenticeship programs, schools and veterans organizations to develop the workforce required for the campus.

For Pike County, the labor question may eventually become almost as important as the power question. Building an 8-GW IT campus means finding electricians, pipefitters, ironworkers, equipment operators, controls technicians, network technicians and commissioning specialists at a scale rarely demanded by a single project in a rural region.

$80 Million for the Community and Another $84 Million in AI Credits

The developers have also put more detail behind community benefits. SB Energy previously committed $40 million to community programs. OpenAI is adding another $40 million, creating an initial $80 million community benefits fund.

The companies say spending priorities will be shaped locally and are expected to include workforce development, education, infrastructure and community services. OpenAI also says an “Ohio Community Compact” will create public commitments against which the development can be measured. Separately, OpenAI announced approximately $84 million in Codex credits, offering eligible Ohio college students $100 in credits through ChatGPT.

Community benefits are likely to remain a major part of the project narrative as construction accelerates. So will the project’s promise that its power requirements will not be subsidized by existing electricity customers.

What Has Changed Since March

The easiest way to understand the last several months is to compare the questions surrounding PORTS-Pike in March with those surrounding it today.

In March, the principal question was whether an almost unimaginably large power-and-compute campus could be assembled in southern Ohio. By August, several of the project’s biggest uncertainties have been reduced.

  •     There is now an identified 8-GW IT customer in OpenAI.
  • There is a 20-year lease structure.
  • There is an exclusive compute supplier in NVIDIA.
  • There is a $1.5 billion new NVIDIA investment in SB Energy.
  • There is a contingent NVIDIA credit support structure covering an initial 4.25 GW of IT capacity and carrying a maximum disclosed NVIDIA obligation of $105 billion.
  • There is a defined AEP transmission project centered on a roughly 50-mile, 765-kV Baku-to-Gavin connection.
  • There is a federal FAST-41 permitting schedule.
  • There is an  approximately 2-GW natural-gas project beginning to work its way toward the Ohio Power Siting Board.
  • There are more specific cooling and water plans.
  • There is now an $80 million cash community-benefit commitment accompanied by more defined workforce initiatives.

None of that means the development is guaranteed to reach its ultimate scale.

The project still has to execute multiple generations of data center construction. AEP has to build major transmission infrastructure. Gigawatts of new generation must clear siting and environmental reviews. Federal and state permits have to be completed. SB Energy has to finance each phase. Gas supply and pipeline capacity have to arrive. DOE redevelopment work has to remain synchronized with commercial construction. And an unprecedented volume of NVIDIA computing equipment will ultimately have to be manufactured, delivered, installed and repeatedly refreshed.

The difference is that PORTS-Pike is no longer simply a rendering accompanied by enormous power numbers. Its contractual and financial architecture is becoming visible, making it real.

From Power-First to Bankability-First

Our previous assessment of PORTS-Pike described a power-first approach to AI infrastructure and that description remains accurate. But the August developments add another dimension.

PORTS-Pike is becoming a bankability-first AI infrastructure project. The physical resources necessary for an AI factory — land, power, transmission, buildings, cooling and networking — are being matched to long-term customer demand and a financial structure intended to make financing those assets possible.

NVIDIA’s participation makes that especially significant. The company that dominates AI accelerators is now putting capital and credit behind the infrastructure into which those accelerators will eventually be installed. The campus now has a customer, a compute architecture, a credit structure and a timetable for turning those gigawatts into an actual AI factory.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Network architecture pay climbs amid AI shift

Network architects today must make decisions that involve multiple technologies. From topology to WAN and SD-WAN to segmentation and security, the scope of networking skills continues to evolve. Those networking decisions become more complicated as enterprises incorporate AI workloads, edge computing, Wi-Fi 7, private 5G, and more. AI and automation

Read More »

Golar contracts CIMC Raffles for fourth FLNG

Golar LNG Ltd. last week executed an engineering, procurement, and construction (EPC) contract with Yantai CIMC Raffles Offshore Ltd. (CIMC Raffles) for its fourth floating LNG (FLNG) and second MKII design FLNG vessel with an annual liquefaction capacity of 3.5 million tonnes/year (tpy). Golar’s fourth FLNG is expected to be

Read More »

Cerebras reimagines AI cluster design with switchless CS-4 architecture

Inside the Cerebras fabric, the trade-off is different. Direct Wafer Links are proprietary, so third-party accelerators cannot be added to the fabric. Scaling it requires additional Cerebras systems, Shah said. Faruqui said the operational divide may be more significant than the physical networking challenge. Existing orchestration environments are generally designed

Read More »

Energy Department Announces $500 Million to Secure America’s Critical Mineral and Battery Supply Chains

WASHINGTON—The U.S. Department of Energy’s (DOE) Office of Critical Minerals and Energy Innovation (CMEI) today announced $500 million for seven selected projects to expand critical mineral and material processing, battery manufacturing, and recycling capacity in the United States. In accordance with President Trump’s Executive Order, Unleashing American Energy, the selected projects advance the President’s agenda to strengthen America’s domestic critical minerals and materials supply chains, reduce reliance on foreign sources, bolster national security, and advance American energy dominance. “For too long, America has depended on foreign actors for critical materials essential to modern life that underpin our economy, energy security, and national security,” said U.S. Secretary of Energy Chris Wright. “President Trump is reversing that dependence by securing our critical supply chains, unleashing American industry, and bringing critical materials production and processing back to the United States.” “DOE is taking decisive action to secure the critical supply chains necessary to power our nation,” said Assistant Secretary of Energy Audrey Robertson. “These projects underscore DOE’s commitment to driving innovation, reducing reliance on foreign sources, and promoting American energy dominance.” This is the third round of funding from DOE’s Battery Materials Processing and Battery Manufacturing and Recycling programs, which support battery materials processing, recycling, and manufacturing projects. These include demonstration projects, construction of commercial-scale facilities, and retrofitting or retooling existing facilities.  Critical minerals and materials are essential to American industry, energy production, and national security. Expanding domestic capacity will help ensure the resources America needs are processed, manufactured, and recycled in the United States.  Information on the selected projects is available here and here.

Read More »

bp lets Shah Deniz compression automation contract

bp has let a contract to Emerson to deliver automation technologies for the Shah Deniz Compression project offshore Azerbaijan. Emerson will provide integrated control and safety systems aimed at enhancing production, safety, and reliability on the new offshore compression platform. The contract includes systems to provide process control, safety shutdown, fire and gas detection, and power management. Together, these systems deliver real-time visibility and remote control of critical operations, Emerson said. The $2.9 billion Shah Deniz Compression project, which includes an electrically powered, normally unattended offshore production platform, is a next stage development of the Caspian Sea Shah Deniz field. Designed to access low-pressure gas reserves and maximize overall recovery, the platform will be equipped with four 11 Mw compressors and serve as the central compression hub for gas from the Shah Deniz Alpha and Bravo platforms. The platform will operate remotely from bp’s onshore Sangachal terminal 55 km south of Baku. The project is expected to enable about 50 billion cu m of additional gas and about 25 million bbl of condensate production and export. Construction is scheduled to be completed in 2029, with first gas compression expected from the Shah Deniz Alpha platform in 2029 and from the Shah Deniz Bravo platform in 2030. The agreement follows a previous automation contract bp signed with Emerson for the Azeri Central East and Shah Deniz Stage 2 developments. bp is operator at Shah Deniz (29.99%) with partners Lukoil (19.99%), TPAO (19%), Cenub Qaz Dehlizi (16.02%), NICO (10%), and MVM (5%).

Read More »

Federal court voids Texas GulfLink license over agency’s ‘serious procedural errors’

The ruling voids the license, halting all construction or progress. Sentinel Midstream declined comment on the ruling and would not answer questions about the status of construction. GulfLink, sited about 30 miles offshore Freeport, Tex., is designed to export up to 1 million b/d via Very Large Crude Carriers (VLCCs) to the government of Japan and Freeport Commodities. The project involves a 44-mile, 42-in. OD pipeline and was scheduled to begin operations around 2028. The estimated $2.1 billion investment was funded as part of a broader trade agreement between the US and Japan. The legal battle stems from a specific rule in the Deepwater Port Act of 1974 that dictates that the federal government can only permit one crude oil deepwater port, including any supporting infrastructure, within a single designated “application area.” Because the competing SPOT project’s pipeline route physically overlaps and intersects GulfLink’s lines, the plaintiff—Citizens for Clean Air & Clean Water in Brazoria County (Better Brazoria), represented by Earthjustice—successfully argued that MARAD violated the “one port” rule when issuing GulfLink’s license in February. The three-judge panel found that MARAD “improperly drew” the map designing the project’s official boundaries to exclude the pipelines and approved two overlapping projects in the same zone instead of only licensing one. The court wrote that the scope of the error made vacatur, not the less serious remand without vacatur, the appropriate remedy. Vacatur deems the license invalid and is used when the court finds “serious procedural errors” that cannot be easily explained or fixed with minor changes. Remand without vacatur sends the decision back to the agency for corrections but leaves the current license in place in the meantime. SPOT project status The $2.5-3-billion SPOT project, developed by Enterprise Products Partners in partnership with Enbridge Inc., also lies about 30 miles from Freeport. Designed to handle VLCCs,

Read More »

IEA: Emergency reserve withdrawals slow

The International Energy Agency (IEA) member countries continued to release emergency oil stocks in July, but the pace of withdrawals slowed sharply as crude supply availability improved in parts of the Asia Pacific and the market faced increasing product tightness. IEA countries released 26 million bbl of emergency stocks in July, bringing cumulative releases to 300 million bbl since the agency announced a coordinated 400-million bbl action on Mar. 11. Government stock draws averaged 750,000 b/d in July, down from 1.5 million b/d in June and 2.5 million b/d in May. The slowdown was particularly pronounced among IEA members in Asia Oceania, which released 4 million bbl from emergency stocks in July, compared with 8 million bbl in June and 44 million bbl in May. The decline reflected improved crude oil supply availability in Japan and Korea. The US also reduced the pace of emergency stock releases. Withdrawals from the Strategic Petroleum Reserve totaled 17 million bbl in July, roughly half the volume released in June. More than 100 million bbl of the emergency stocks committed under the IEA’s 400-million bbl coordinated action has yet to reach the market. The timing of the remaining releases will depend on market developments and broader oil supply security considerations in coming months, according to the agency. Most of the remaining emergency stocks consist of crude oil, however, limiting their ability to ease increasingly tight oil product markets, IEA said. At the same time, global observed oil inventories fell sharply in July amid severely constrained shipping through the Strait of Hormuz. Stocks declined by 69 million bbl, equivalent to 2.2 million b/d, with oil on water accounting for more than 90% of the decline. Oil on water fell by 63 million bbl, or about 2 million b/d, reflecting higher arrivals and lower exports amid

Read More »

Devon takes FID on 4.5-bcfd Permian pipeline

Devon Energy Corp. has taken final investment decision (FID) on the Solitude Pipeline System, a WhiteWater-led joint venture that will build two 48-in. OD natural gas pipelines connecting the Permian basin to Katy, Tex. Devon describes Solitude as the latest in a series of steps it has taken to integrate and consolidate the infrastructure supporting its Delaware basin position. Solitude is designed for a phased build-out of 2.25 bcfd entering service second-half 2029, followed by a similarly sized second phase in 2030 and the ability to expand further to meet shipper demand. Construction and in-service timing remain subject to customary regulatory approvals. Devon has secured firm transportation capacity and will hold a 25% equity interest in the joint venture, alongside WhiteWater (50%), MPLX (10%), Diamondback Energy (7.5%) and Western Midstream Partners (7.5%). Permian producers have long absorbed volatile and periodically negative pricing at the Waha hub, where takeaway capacity has repeatedly failed to keep pace with associated gas growth. Devon says the pipeline will move the majority of its Delaware gas out of Waha and into markets that will be tied to expanding LNG export and power generation. Devon has initiated the process of securing international LNG-linked pricing, including a 100-MMcfd agreement beginning in 2027 and an additional 150 MMcfd in 2028. “Solitude is not a standalone investment; it is the next step in an integrated model we have been building for years,” said Clay Gaspar, Devon’s president and chief executive officer. “We have taken the hardest constraints in the Delaware [b]asin: water, processing, compression, takeaway and power, and have de-risked the physical constraints turning each one into a source of value rather than a tax on our returns. The company’s integrated model continues to lower our cost of supply, driving free cash flow higher and deepening our peer-leading Delaware

Read More »

JAPEX begins drilling second well for Tomakomai CCS Project

@import url(‘https://fonts.googleapis.com/css2?family=Inter:wght@100..900&display=swap’); .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; opacity: .6; } #onetrust-pc-sdk [id*=btn-handler], #onetrust-pc-sdk [class*=btn-handler] { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-policy a, #onetrust-pc-sdk a, #ot-pc-content a { color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-pc-sdk .ot-active-menu { border-color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-accept-btn-handler, #onetrust-banner-sdk #onetrust-reject-all-handler, #onetrust-consent-sdk #onetrust-pc-btn-handler.cookie-setting-link { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-consent-sdk .onetrust-pc-btn-handler { color: #c19a06 !important; border-color: #c19a06 !important; } Japan Petroleum Exploration (JAPEX) began drilling its second exploratory well for carbon dioxide (CO2) storage to advance the Tomakomai carbon capture and storage (CCS) project in the Tomakomai area of Hokkaido. Undertaken for drilling on Aug. 15, the well utilizes extended reach drilling from a drilling rig in Masago-cho, Tomakomai City, toward the seabed to confirm the existence of formations suitable for CO2 storage. Drilling of this second exploratory well follows start of exploratory drilling for the project in late 2025. Launched for initial study in 2023, the Tomakomai CCS project aims to separate and capture CO2 from Idemitsu Kosan Co. Ltd.’s Hokkaido refinery and Hokkaido Electric Power Co. Inc.’s Tomato Atsuma power station. The CO2 will be injected underground by JAPEX. While JAPEX said it intends to make a final investment decision (FID) on the Tomakomai CCS project based on combined results of both exploratory wells, the company did not specify a timeframe for when FID would occur. The partners previously said they intend to achieve a CO2-storage volume of 1.5-2 million tonnes/year in 2030. 

Read More »

PJM’s New Data Center Power Equation

PJM Interconnection has now filed one of the most consequential proposed changes yet in the relationship between data centers and the electric grid. Rather than simply treating a new hyperscale or AI facility like any other customer whose demand will be backed through regional capacity procurement, PJM is proposing a framework under which the largest new loads would need to be supported by new capacity, have their needs covered through the Reliability Backstop Procurement, or face potential curtailment when the regional power system is short of supply. The approach has been developing since PJM launched its Critical Issue Fast Path process for large loads in 2025, but it became substantially more concrete in late July and August 2026. PJM filed its proposed Reliability Backstop Procurement with FERC on July 31 and began accepting applications that day for its FERC-approved Expedited Interconnection Track. On Aug. 13, PJM filed its proposed Interim Resource Adequacy Service, or IRAS, along with the Large Load Registry that would support it. The immediate numbers explain the urgency. PJM’s July 2026 capacity auction for the 2028/2029 delivery year procured 138,318 MW of unforced capacity through the centralized auction. Even after including Fixed Resource Requirement resources, however, PJM came up 6,831 MW short of its reliability requirement. The auction cleared at the FERC-approved $325/MW-day price cap. It was the second consecutive auction in which the PJM region failed to procure its full reliability requirement, something that had not happened before these two auctions. That gap is occurring while demand continues to accelerate. PJM’s 2026 long-term forecast projects summer peak demand growing at an average 3.6% annually over the next decade, compared with just 0.3% in the comparable forecast issued in 2021. Summer peak demand is projected to rise by nearly 66 GW over 10 years. Data centers are

Read More »

Zayo, NVIDIA Build the Long-Haul Backbone for Distributed AI

The data center industry’s increasingly power-first approach to site selection has created a follow-on question: Once the megawatts are found, is there enough network infrastructure to make the site useful at AI scale? Zayo and NVIDIA are putting real infrastructure behind that question. Zayo said it is working with NVIDIA to expand network capacity supporting AI factories across North America, including an 8,000-route-mile program targeting some of the fastest-growing AI corridors in the United States. The project encompasses six new long-haul routes along with overbuilds of existing network across 10 high-demand corridors. The announcement arrives as AI data center development moves beyond the largest established hubs toward markets where power and land may be more readily available, but fiber capacity cannot necessarily be taken for granted. That geography is increasingly important. NVIDIA has separately developed “scale-across” networking technology designed to allow AI infrastructure distributed among different buildings — or even data centers separated by hundreds of kilometers — to operate as a more unified computing environment. Put together, the developments suggest that networking is becoming inseparable from the AI factory buildout itself. Power may determine where the next generation of AI infrastructure can be built. Fiber will increasingly determine how effectively those sites can participate in the larger AI ecosystem. Fiber Follows the Power Zayo CEO Steve Smith said AI demand is changing both where network infrastructure is needed and how aggressively capacity must be deployed ahead of development. “AI is fundamentally reshaping where and how network infrastructure needs to be built across the U.S.,” Smith said. The company’s 8,000-mile program is more nuanced than that top-line number might suggest. Zayo disclosed in April that the expansion includes approximately 3,000 route miles across six new long-haul routes, plus more than 5,000 route miles of overbuilds across 10 existing corridors. Zayo

Read More »

Southern’s 17 GW Pipeline Puts AI Power Demand Into Utility Math

The headline number from Southern Company’s latest earnings report is hard to miss: electricity use by data centers across the utility’s system increased 55% in the second quarter compared with a year earlier. But the more consequential numbers may be the ones sitting behind it. Southern now has more than 1.2 GW of operating data center load, up by more than 500 MW from a year ago. At the same time, its electric utilities have signed contracts and large-load agreements totaling more than 17 GW by the mid-2030s, with another 8 GW in late-stage development and a prospective pipeline of large industrial and data center projects exceeding 75 GW. That leaves an enormous gap between the data center megawatts consuming electricity today and the load Southern has contractually positioned itself to serve during the next decade. For the data center industry, that gap may be the most important part of Southern’s second-quarter story. It offers a look at how utilities are beginning to convert the AI infrastructure boom from forecasts and campus announcements into contracts, generation procurement, transmission investment and eventually energized capacity. From Contracts to Megawatts Southern added roughly 6 GW of contracted large load during the quarter alone. Alabama Power signed three projects representing about 3 GW, while Georgia Power reached a 25-year agreement to serve OpenAI’s planned project in Effingham County near Savannah. That facility is expected to require approximately 3.2 GW and begin taking electric service in phases in 2028. The numbers nevertheless require an important distinction. Seventeen gigawatts contracted does not mean 17 GW will suddenly appear on Southern’s grid. Large data center campuses ramp gradually, often over several years, and Southern executives acknowledged that actual customer ramp schedules do not always match the assumptions made when projects are first approved. CEO Chris Womack said

Read More »

PORTS-Pike Takes Shape as an 8-GW AI Infrastructure Model

Back on March 31, 2026, we discussed we discussed SoftBank and SB Energy’s plans to redevelop the former Portsmouth Gaseous Diffusion Plant site near Piketon as a 10-GW artificial intelligence data center campus supported by almost an equal amount of new power generation. At the time, the plan called for as much as 10 GW of new generation, including 9.2 GW of natural gas capacity, along with approximately $4.2 billion of high-voltage transmission infrastructure developed with AEP Ohio. An initial 800-MW data center phase was targeted for service in 2028. The March story was notable because Pike County appeared to offer a preview of a new model for building hyperscale infrastructure: develop the generation, transmission and data center simultaneously rather than wait for an increasingly congested regional grid to deliver multiple gigawatts of capacity. Not to mention the reuse of a brownfield site with the encouragement of the federal government. Since then, almost every important part of the project has moved forward, and on August 17, the most consequential missing pieces fell into place. NVIDIA announced that it will become the exclusive AI compute infrastructure provider for the PORTS-Pike Technology Campus. OpenAI will be the data center customer, signing a 20-year lease with SB Energy for approximately 8 GW of IT capacity. NVIDIA will invest another $1.5 billion in SB Energy and provide credit support for the land, power and shell infrastructure behind an initial 4.25 GW of IT load, with an option covering approximately another 3.75 GW. The Securities and Exchange Commission filing accompanying the announcement makes the financial commitment even more significant. NVIDIA disclosed that its aggregate payment obligation associated with its initial commitment is capped at $105 billion. That is not a conventional capital commitment to spend $105 billion building the campus, nor is it simply a

Read More »

Nvidia scales back financing guarantee for OpenAI data center

Nvidia is scaling back a proposed financial guarantee tied to a massive OpenAI data center project in Ohio, reducing its initial commitment from as much as $250 billion to less than $120 billion, according to report in the Wall Street Journal. Earlier this month, Nvidia announced partnerships with major financial firms including Apollo Global Management, BlackRock, Blackstone, Brookfield Asset Management, Goldman Sachs and KKR, aimed at mobilizing more than $500 billion in capital for AI computing infrastructure. The change represents a significant restructuring of Nvidia’s role in financing the planned facility, which is being developed by SB Energy, a subsidiary of SoftBank. Under the revised arrangement, Nvidia would guarantee financing for the project’s first phase, representing roughly 5 gigawatts of capacity, or half of the total proposed capacity. Financing for the remaining capacity would be considered separately at a later stage.

Read More »

Texas Tightens Oversight of Data Center Development

Texas has spent the past decade building one of the most data center-friendly policy environments in the United States. But the state’s political posture is tightening. The emerging message from Austin is that continued data center growth will face greater scrutiny over grid costs, water use, tax incentives and community impacts. What is interesting about this policy conversation is that the Texas Legislature is not in regular session. The 89th regular session ended June 2, 2025, and the 90th Legislature does not convene until January 12, 2027. What has occurred instead is a concentrated period of interim committee work, gubernatorial recommendations, implementation of Senate Bill 6, calls for a special session, and regulatory action by the Public Utility Commission of Texas and the Electric Reliability Council of Texas. Together, those efforts are creating the framework for a broader legislative debate in 2027 while already affecting projects seeking ERCOT interconnection, infrastructure costs and site-selection decisions. Abbott Sets Out a New Policy Framework The policy shift accelerated June 10, when Gov. Greg Abbott directed the PUCT to require data centers to fully fund the electric infrastructure needed to serve their operations and directed PUCT and ERCOT to identify additional actions available under existing authority. Separately, Abbott pledged to work with lawmakers in 2027 on legislation requiring data centers to add electric capacity, use water-efficient cooling systems, report electricity and water use, phase out outdated tax incentives and adopt additional protections for neighboring communities. The most consequential shift began June 10, when Gov. Greg Abbott sent state electricity regulators a sweeping list of data center policy priorities. Abbott called for future legislation requiring new facilities to add generation to the Texas grid, pay the full cost of their interconnection and related infrastructure, use closed-loop or similarly water-efficient cooling systems, and file annual reports

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »

Mother tongue

“Daddy?” Theo curled against my side in bed. “Where do words go when they die?” I’d orchestrated the bedtime routine flawlessly: bath (taken), teeth (brushed),

Read More »