Stay Ahead, Stay ONMINE

Utilities Race to Meet Surging Data Center Demand With New Power Models

Over the last 18 months or so, the energy generation industry and its public utilities have been significantly impacted by the AI data center boom. It has been demonstrated across North America that the increase in demand for power, as driven by the demand for hyperscale and AI data centers, greatly exceeds the ability of […]

Over the last 18 months or so, the energy generation industry and its public utilities have been significantly impacted by the AI data center boom. It has been demonstrated across North America that the increase in demand for power, as driven by the demand for hyperscale and AI data centers, greatly exceeds the ability of the industry to actually generate and deliver power to meet the demand.

We have covered many of the efforts being made to control the availability of power. In response, utilities and regulators have begun rethinking how to manage power availability through means such as: temporary moratoriums on new data center interconnections; the creation of new rate classes; cogeneration and load-sharing agreements; renewable integration; and power-driven site selection strategies. 

But the bottom line is that in many locations utilities will need to change the way they work and how and where they spend their CAPEX budgets. The industry has already realized that their demand forecast models are hugely out of date, and that has had a ripple effect on much of the planning done by public utilities to meet the next generation of power demand.

Most utilities now acknowledge that their demand forecasting models have fallen behind reality, triggering revisions to Integrated Resource Plans (IRPs) and transmission buildouts nationwide. This mismatch between forecast and actual demand is forcing a fundamental rethink of capital expenditure priorities and long-term grid planning.

Spend More, Build Faster

Utilities are sharply increasing CAPEX and rebalancing their resource portfolios—not just for decarbonization, but to keep pace with multi-hundred-megawatt data center interconnects. This trend is spreading across the industry, not confined to a few isolated utilities. Notable examples include:

  • Duke Energy raised its five-year CAPEX plan to $83 billion (a 13.7% increase) and plans to add roughly 5 GW of natural gas capacity by 2029 to meet accelerating data center and industrial load growth.

  • Dominion Energy lifted its five-year capital plan to $50.1 billion, citing data centers as a primary driver while warning of potential rate pressure from grid modernization and capacity expansion.

  • NV Energy’s 2024 Integrated Resource Plan explicitly models about 5.9 GW of bundled-service data center requests by 2033, supported by new gas, storage, and renewable additions.

  • Salt River Project (Phoenix) is advancing a mixed portfolio of peaking gas and clean capacity, including the Coolidge Generating Station Expansion—a 575-MW project approved and now under construction—with additional peak resources under review.

  • Tennessee Valley Authority (TVA) is moving forward on advanced nuclear for long-duration firming, including a BWRX-300 small modular reactor application for the Clinch River site, and a power purchase agreement with Kairos Power’s Hermes-2 test reactor expected to support Google data centers around 2030.

These CAPEX expansions fund both new generation capacity in the form of modern combined-cycle and combustion-turbine plants, nuclear pilots, and renewables, and grid-side investments to move bulk power to where data centers are locating. This demand is now an explicit planning driver in utility integrated resource plans (IRPs) and board approvals. It’s important to note that these investments encompass both generation and transmission infrastructure.

New Rate Designs and Risk-Transfer Contracts Shift More Responsibility to Data Centers

Utilities are retooling tariffs to protect existing ratepayers and de-risk megawatt-scale customers. With a goal of protecting consumer rate payers, a number of different tariff designs have been put forth.

The goal is to ensure that the cost of new capacity and infrastructure upgrades falls primarily on large commercial users – particularly data centers -rather than being spread across residential and small-business customers. Several new tariff structures explicitly define data center capacity obligations and cost recovery terms. Examples include:

  • New data center rate class: Dominion Energy has proposed a dedicated rate category for customers ≥25 MW with ≥75% load factor, featuring 14-year take-or-pay–style commitments to cover stranded-cost risk and ensure “full cost of service.”

  • Take-or-pay / minimum-take provisions: Duke Energy is pursuing minimum-take contracts (requiring payment regardless of utilization) and up-front contributions for network upgrades tied to data center interconnections—part of a broader shift toward “contribution in aid of construction” (CIAC) requirements.

  • Standby and curtailable service riders: Large-load customers are increasingly directed toward standby-generator and curtailable-service schedules to formalize flexibility. Dominion’s Schedule SG and Schedule CS are examples under their targeted sector programs.

The net effect of these evolving tariffs is that utilities are socializing less risk from speculative or timing-uncertain AI loads, while providing greater queue certainty for data center developers willing to shoulder their share of capital costs.

Changing the Relationship Between Data Centers and Utilities

A major shift is underway: load flexibility is becoming a formal part of interconnection agreements. New legislation and regulatory frameworks across multiple regions are requiring data centers to demonstrate the ability to adjust or curtail power consumption during grid stress events.

From on-site cogeneration and load balancing to demand-response participation and remote-curtailment capabilities, utilities and regulators are increasingly embedding flexibility requirements into contracts and permitting. Examples include:

  • Under Texas SB 6, ratified in June 2025:  Beginning December 31, 2025, new large-load customers (≥75 MW) must be able to remotely curtail load or switch to on-site generation during emergencies. ERCOT will also begin procuring demand reductions from major customers. Interconnection agreements are expected to include fees, disclosure of backup power systems, and cost-sharing provisions as standard components.

  • PJM and SPP: Both grid operators are fast-tracking policies to curtail or manage large loads during scarcity events. The SPP “HILL/CHILL” framework establishes a 90-day expedited interconnection path when large-load customers pair with generation resources, defining curtailable service classes for planning and market participation.

  • Voluntary demand-response partnerships: To preempt mandatory curtailment mandates, some hyperscalers are signing voluntary flexibility agreements. Google, for instance, has reached demand-flexibility deals with Indiana Michigan Power and the Tennessee Valley Authority (TVA) to shift or reduce AI workloads during peak grid demand—an emerging model for bridging near-term capacity gaps.

Collectively, these developments signal a new era of active coordination between utilities and data centers, in which grid reliability, flexibility, and cost allocation are shared operational priorities.

Upgrading Power Transmission: Accelerate, Reconductor, Right-Size

Serving today’s multi-gigawatt data centers and campus-scale developments requires both new transmission lines and rapid capacity upgrades along existing corridors. With data center interconnection queues expanding across nearly every regional transmission organization (RTO), utilities and regulators are under pressure to streamline approvals and unlock capacity faster.

  • PJM approved $5.9–$6.7 billion in near-term transmission projects in 2025, explicitly citing data center–driven load growth and resource shifts as key justifications.

  • Advanced conductors: Google and CTC Global have partnered with utilities to reconduct existing lines using ACCC® (Aluminum Conductor Composite Core) technology, boosting transmission capacity in months rather than years. Priority is being given to reconductoring lines that unlock capacity for new data center sites.

  • Aggressive planning upgrades: PJM’s evolving Regional Transmission Expansion Plan (RTEP) process aims to “right-size” near-term fixes for long-term needs. The DOE and NREL have identified Grid-Enhancing Technologies (GETs) such as Dynamic Line Rating (DLR) and topology optimization as practical, near-term pathways for unlocking transmission capacity without lengthy new-build timelines.

  • Federal rulemaking: Two FERC orders are reshaping how utilities and RTOs plan for both new generation and surging load growth:

    • FERC Order 2023 (2023): Requires cluster-based interconnection studies with enforceable deadlines and penalties, designed to reduce the interconnection backlog and expedite capacity additions.

    • FERC Order 1920/A/B (2024–2025): Mandates 20-year regional transmission plans, state involvement in cost allocation, and greater transparency, giving utilities a framework to plan around structural load growth driven by AI and industrial electrification.

  • Process innovation: SPP is implementing a 90-day fast-track path for “high-impact large loads” paired with new generation under its HILL/CHILL policy framework.

Together, these measures reflect a system-wide acceleration of transmission modernization, combining new lines, smarter planning, and digital tools to move power where AI and hyperscale demand is rising fastest.

Green Tariffs and “Bring-Your-Own-Clean-Power” Programs Are Changing How Data Centers Source Energy

Utilities are expanding subscription-based renewable programs and custom clean-energy constructs that enable data centers to meet sustainability and carbon-reduction goals within regulated tariffs. For large-scale operators, the challenge lies in navigating a fragmented landscape: each utility administers its own program, requiring project-specific power purchase agreements (PPAs) and regional tailoring to reflect local policy and grid conditions.

Examples of key programs include:

  • Duke Energy – Green Source Advantage (GSA / GSA Choice, North and South Carolina): Allows large customers to contract utility-backed renewable projects through long-term agreements. The program was expanded in 2024 to add new capacity and greater flexibility for participants.

  • Georgia Power – CRSP / CARES: The Clear and Renewable Energy Subscription Program offers 1,000–2,100 MW of utility-procured renewables for large-customer subscription. QTS Data Centers subscribed to approximately 350 MW under CRSP for its Atlanta-area facilities.

  • Dominion Energy – Schedule RG / Schedule CFG: Provides utility-sourced carbon-free and renewable energy options for large commercial and industrial (C&I) customers. Schedule RG (approved in 2018) and the newer Schedule CFG (for projects ≥1 MW) are voluntary programs that allow customers to directly procure renewable generation through Dominion-backed assets.

A growing number of utilities are evolving from pass-through energy suppliers to active counterparties, developing or contracting clean-energy assets that are directly matched to data center load profiles. This integrated approach (where power buyers participate in generation planning) aims to improve efficiency, transparency, and reliability in how large loads source renewable energy.

Regional Utility Responses Are Diverging

Not all power generation, and not all regulatory response, is created equal. Across the U.S., states and regional transmission operators (RTOs) are adapting to data center–driven load growth in markedly different ways, reflecting local politics, resource mixes, and grid constraints.

  • Virginia (PJM): Data centers now account for approximately 25% of statewide electricity consumption, according to Dominion’s filings and state reports. Dominion’s Integrated Resource Plan (IRP) and new large-load rate class proposals formally recognize data centers as the primary driver of load growth and cost allocation debates. Transmission capacity remains the chokepoint, making advanced conductor pilots and PJM’s RTEP expansion windows key to sustaining growth.

  • Texas (ERCOT): Senate Bill 6 (2025) effectively resets the social contract for large loads—requiring operators to flex or face emergency curtailment—and is expected to push wider adoption of on-site generation, energy storage, and hybrid PPAs. Other utilities and cooperatives across the state are expected to mirror ERCOT’s flexibility protocols in their own tariffs.

  • Arizona (SRP / APS): Rapid regional growth is driving a buildout of gas peaker plants paired with battery storage, alongside stricter queue management and prioritization. Salt River Project’s Coolidge Expansion exemplifies a reliability-first strategy, with clean-energy components layered in to support long-term decarbonization goals.

  • Midwest (MISO / Indiana): The Indiana Utility Regulatory Commission (IURC) has approved new large-load interconnection rules, while utilities such as Indiana Michigan Power (I&M) are signing demand-response agreements—including with Google—to mitigate peak load. Policymakers are advancing cost-sharing requirements for new generation supporting big-load customers.

  • SPP (Plains states): The Southwest Power Pool (SPP) is actively marketing the region to High Impact Large Load (HILL) customers through accelerated interconnection studies and firm/curtailable service classes, aiming to attract data center development away from saturated hubs like Virginia and northern Texas.

Regional differences in regulation and resource strategy are now shaping the geography of new data center investment, rewarding jurisdictions that can align policy agility, grid capacity, and clean-power availability.

What This Means for Data Center Developers

Over the next several years, the structure of power procurement deals for data centers is likely to evolve significantly. Utilities will increasingly require greater up-front financial participation from customers, shifting capital and risk onto large-load developers. Expect to see:

  • Contribution-in-aid-of-construction (CIAC) payments or similar up-front contributions to fund new substations, network upgrades, and capacity expansions.

  • Minimum-take or take-or-pay obligations to guarantee long-term revenue recovery for utilities.

  • Extended contract terms—typically 10 to 15 years—to secure capacity and protect other ratepayers from stranded-cost exposure.

Flexibility will become a baseline requirement. Interconnection agreements may now mandate curtailment capabilities, demand-response participation, and certified backup generation. In ERCOT, for example, new large loads ≥75 MW must be equipped for remote disconnection or on-site generation under Senate Bill 6 (2025).

Transmission-friendly regions will rise in priority for new site development. Locations within PJM subregions or along SPP’s HILL corridor, where reconductoring and RTEP upgrades can unlock capacity quickly, will gain competitive advantage as interconnection bottlenecks persist elsewhere.

Data center developers will also need to maintain ongoing visibility into utility and regulatory planning cycles, tracking updates from individual utilities, regional transmission operators (RTOs), and federal agencies such as FERC. Understanding how generation mix, transmission planning, and tariff reform interact will be essential to long-term siting and investment strategy.

In short, the path to power is becoming more capital-intensive, flexible, and policy-dependent, requiring data center developers to act as active partners in the evolving utility ecosystem.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Vår Energi lets 3-year contract for harsh-environment rig for NCS work

@import url(‘https://fonts.googleapis.com/css2?family=Inter:[email protected]&display=swap’); a { color: var(–color-primary-main); } .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; font-family: Inter; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style

Read More »

CERT-EU blames Trivy supply chain attack for Europa.eu data breach

Back door credentials The Trivy compromise dates to February, when TeamPCP exploited a misconfiguration in Trivy’s GitHub Actions environment, now identified as CVE-2026-33634, to establish a foothold via a privileged access token, according to Aqua Security. Discovering this, Aqua Security rotated credentials but, because some credentials remain valid during this

Read More »

French government take Bull by horns for €404 million

It’s the second time that Bull has been nationalized: The first time, in 1982 was to save it from bankruptcy. Atos, has had financial troubles of its own. In August 2024, it tried — and failed — to sell its legacy infrastructure management business. The company had already staved off

Read More »

Cisco fixes critical IMC auth bypass present in many products

Cisco has released patches for a critical vulnerability in its out-of-band management solution, present in many of its servers and appliances. The flaw allows unauthenticated remote attackers to gain admin access to the Cisco Integrated Management Controller (IMC), which gives administrators remote control over servers even when the main OS

Read More »

Latin America returns to the energy security conversation at CERAWeek

With geopolitical risk central to conversations about energy, and with long-cycle supply once again in focus, Latin America’s mix of hydrocarbons and export potential drew renewed attention at CERAWeek by S&P Global in Houston. Argentina, resource story to export platform Among the regional stories, Argentina stood out as Vaca Muerta was no longer discussed simply as a large unconventional resource, but whether the country could turn resource quality into sustained export capacity.  Country officials talked about scale: more operators, more services, more infrastructure, and a larger industrial base around the unconventional play. Daniel González, Vice Minister of Energy and Mining for Argentina, put it plainly: “The time has come to expand the Vaca Muerta ecosystem.” What is at stake now is not whether the basin works, but whether the country can build enough above-ground capacity and regulatory consistency to keep development moving. Horacio Marín, chairman and chief executive officer of YPF, offered an expansive version of that argument. He said Argentina’s energy exports could reach $50 billion/year by 2031, backed by roughly $130 billion in cumulative investment in oil, LNG, and transportation infrastructure. He said Argentine crude output could reach 1 million b/d by end-2026. He said Argentina wants to be seen less as a recurrent frontier story and more as a future supplier with scale. “The time to invest in Vaca Muerta is now,” Marín said. The LNG piece is starting to take shape. Eni, YPF, and XRG signed a joint development agreement in February to move Argentina LNG forward, with a first phase planned at 12 million tonnes/year. Southern Energy—backed by PAE, YPF, Pampa Energía, Harbour Energy, and Golar LNG—holds a long-term agreement with SEFE for 2 million tonnes/year over 8 years. The movement by global standards is early-stage and relatively modest, but it adds to Argentina’s export

Read More »

Market Focus: LNG supply shocks expose limited market flexibility

@import url(‘https://fonts.googleapis.com/css2?family=Inter:[email protected]&display=swap’); a { color: var(–color-primary-main); } .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; font-family: Inter; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; opacity: .6; } #onetrust-pc-sdk [id*=btn-handler], #onetrust-pc-sdk [class*=btn-handler] { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-policy a, #onetrust-pc-sdk a, #ot-pc-content a { color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-pc-sdk .ot-active-menu { border-color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-accept-btn-handler, #onetrust-banner-sdk #onetrust-reject-all-handler, #onetrust-consent-sdk #onetrust-pc-btn-handler.cookie-setting-link { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-consent-sdk .onetrust-pc-btn-handler { color: #c19a06 !important; border-color: #c19a06 !important; } In this Market Focus episode of the Oil & Gas Journal ReEnterprised podcast, Conglin Xu, managing editor, economics, takes a look into the LNG market shock caused by the effective closure of the Strait of Hormuz and the sudden loss of Qatari LNG supply as the Iran war continues. Xu speaks with Edward O’Toole, director of global gas analysis, RBAC Inc., to examine how these disruptions are intensifying global supply constraints at a time when European inventories were already under pressure following a colder-than-average winter and weaker storage levels. Drawing on RBAC’s G2M2 global gas market model, O’Toole outlines disruption scenarios analyzed in the firm’s recent report and explains how current events align with their findings. With global LNG production already operating near maximum utilization, the market response is being driven by higher prices and reduced consumption. Europe faces sharper price pressure due to storage refill needs, while Asian markets are expected to see greater demand reductions as consumers switch fuels. O’Toole underscores the importance of scenario-based modeling and supply diversification as geopolitical risk exposes structural vulnerabilities in the LNG market—offering insights for stakeholders navigating an increasingly uncertain global

Read More »

Libya’s NOC, Chevron sign MoU for technical study for offshore Block NC146

@import url(‘https://fonts.googleapis.com/css2?family=Inter:[email protected]&display=swap’); a { color: var(–color-primary-main); } .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; font-family: Inter; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; opacity: .6; } #onetrust-pc-sdk [id*=btn-handler], #onetrust-pc-sdk [class*=btn-handler] { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-policy a, #onetrust-pc-sdk a, #ot-pc-content a { color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-pc-sdk .ot-active-menu { border-color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-accept-btn-handler, #onetrust-banner-sdk #onetrust-reject-all-handler, #onetrust-consent-sdk #onetrust-pc-btn-handler.cookie-setting-link { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-consent-sdk .onetrust-pc-btn-handler { color: #c19a06 !important; border-color: #c19a06 !important; } The National Oil Corp. of Libya (NOC) signed a memorandum of understanding (MoU) with Chevron Corp. to conduct a comprehensive technical study of offshore Block NC146. The block is an unexplored area with “encouraging geological indicator that could lead to significant discoveries, helping to strengthen national reserves,” NOC noted Chairman Masoud Suleman as saying, noting that the partnership is “a message of confidence in the Libyan investment environment and evidence of the return of major companies to work and explore promising opportunities in our country.” According to the NOC, Libya produces 1.4 million b/d of oil and aims to increase oil production in the coming 3-5 years to 2 million b/d and then to 3 million b/d following years of instability that impacted the country’s production.   Chevron is working to add to its diverse exploration and production portfolio in the Mediterranean and Africa and continues to assess potential future opportunities in the region.  The operator earlier this year entered Libya after it was designated as a winning bidder for Contract Area 106 in the Sirte basin in the 2025 Libyan Bid Round. That followed the January 2026 signing of a

Read More »

Finder Energy advances KTJ Project with development area approval

Finder Energy Holdings Ltd. received regulatory approval for a development area covering the Kuda Tasi and Jahal oil fields offshore Timor‑Leste, enabling progression toward field development. Autoridade Nacional do Petróleo (ANP) approved an 88‑sq km development area over the Kuda Tasi and Jahal oil fields (KTJ Project) within PSC 19‑11 offshore Timor‑Leste, representing the first stage of the regulatory approvals process for the project. The declaration of the development area is a precursor to the field development plan (FDP), which Finder is currently preparing for submission to ANP in second‑quarter 2026. Upon approval of the FDP, the development area would secure tenure for up to 25 years or until production ceases, allowing Finder to conduct development and production operations within the area, subject to applicable regulatory approvals and conditions. The company said its upside strategy centers on the potential for the Petrojarl I FPSO to serve as a central processing and export hub for future tiebacks of surrounding discoveries, contingent on successful appraisal and/or exploration activities within PSC 19‑11. Alternatively, longer tie‑back distances could be accommodated through a secondary standalone development in the southern portion of the PSC. Finder is continuing technical evaluation of appraisal and exploration opportunities to generate drilling targets. PSC 19‑11 lies within the Laminaria High oil province of Timor‑Leste. The KTJ Project contains an estimated 25 million bbl of gross 2C contingent resources, with identified upside of an additional 23 million bbl gross 2C contingent resources and 116 million bbl gross 2U prospective resources. Finder operates PSC 19‑11 with a 66% working interest.

Read More »

Newly formed Polar LNG aims to develop nearshore LNG project on Alaska’s North Slope

Polar Train LNG LLC, a newly launched company aiming to build an LNG plant (Polar LNG) on Alaska’s North Slope, has appointed Joel Riddle as president and chief executive officer. “Alaska’s North Slope holds one of the most significant undeveloped natural gas resources in the world,” said Riddle, adding “Polar LNG is uniquely positioned to bring this resource online—delivering reliable energy for Alaska and a strategic supply for the United States… and provides trusted energy to our allies.” In a release Mar. 31, the company said it is advancing a nearshore project at Prudhoe Bay, citing “one of the shortest LNG shipping routes from North America to key Asian markets, approximately 3,600 miles to Japan compared to over 10,000 miles from the US Gulf Coast.” The company is aiming for first LNG from the 7-million tonnes/year plant—to be developed nearshore with modular infrastructure—in 2029-2030 at a cost of $8–9 billion. According to Polar LNG, natural gas would be sourced from existing infrastructure at Prudhoe Bay and transported via a short pipeline to a nearshore plant. There, a modular gravity-based structure would process and liquefy the gas. LNG would then be loaded onto specialized ice-class carriers for year-round export. The company is exploring potential repurposing of sanctioned equipment built for Russia’s Arctic LNG 2 project and is seeking permission from the US govenment to acquire parts impacted by the sanctions, according to reports. Before joining Polar LNG, Riddle served as managing director and chief executive officer of Tamboran Resources Ltd.

Read More »

Asia bears brunt of energy shock as Middle East war disrupts liquid flows

Asia is facing a dual energy crisis marked by both soaring prices and physical supply disruptions as escalating war in the Middle East constrains flows through the Strait of Hormuz, according to a new report by Morningstar DBRS. The report highlights that roughly one-fifth of global crude oil and LNG supply has been affected by disruptions at the critical chokepoint, with Asia absorbing the majority of the impact due to its heavy dependence on imported hydrocarbons. About 83% of oil and LNG shipments passing through Hormuz are destined for Asian markets, amplifying the region’s exposure. Asia’s structural reliance on Middle Eastern energy imports has intensified the shock. Countries such as Japan and South Korea import nearly all of their energy needs, while China and India depend heavily on foreign supplies, much of it sourced from the Gulf. This dependence, combined with limited alternative shipping routes, has turned what initially appeared to be a price-driven shock into a broader supply and logistics crisis. Governments across the region have begun implementing emergency measures, including fuel rationing, price controls, and strategic reserve releases, to manage shortages and rising costs. Policy responses vary In North Asia, policymakers are leveraging stronger buffers. Japan has tapped strategic oil reserves and introduced subsidies to cushion consumers, while South Korea is relying on LNG stockpiles and fuel-switching capabilities. China has deployed administrative controls to stabilize domestic fuel prices and restrict refined product exports. By contrast, parts of South and Southeast Asia are more vulnerable. India has introduced tax relief and prioritized gas allocation, while countries such as the Philippines and Vietnam have declared energy emergencies and rolled out conservation measures. Several ASEAN (the Association of Southeast Asian Nations) economies have even implemented partial work-from-home policies to curb fuel consumption. Broader economic spillovers intensify Beyond energy markets, the disruption

Read More »

Nscale Expands AI Factory Strategy With Power, Platform, and Scale

Nscale has moved quickly from startup to serious contender in the race to build infrastructure for the AI era. Founded in 2024, the company has positioned itself as a vertically integrated “neocloud” operator, combining data center development, GPU fleet ownership, and a software stack designed to deliver large-scale AI compute. That model has helped it attract backing from investors including Nvidia, and in early March 2026 the company raised another $2 billion at a reported $14.6 billion valuation. Reuters has described Nscale’s approach as owning and operating its own data centers, GPUs, and software stack to support major customers including Microsoft and OpenAI. What makes Nscale especially relevant now is that it is no longer content to operate as a cloud intermediary or capacity provider. Over the past year, the company has increasingly framed itself as an AI hyperscaler and AI factory builder, seeking to combine land, power, data center shells, GPU procurement, customer offtake, and software services into a single integrated platform. Its acquisition of American Intelligence & Power Corporation, or AIPCorp, is the clearest signal yet of that shift, bringing energy infrastructure directly into the center of Nscale’s business model. The AIPCorp transaction is significant because it gives Nscale more than additional development capacity. The company said the deal includes the Monarch Compute Campus in Mason County, West Virginia, a site of up to 2,250 acres with a state-certified AI microgrid and a power runway it says can scale beyond 8 gigawatts. Nscale also said the acquisition establishes a new division, Nscale Energy & Power, headquartered in Houston, extending its platform further into power development. That positioning reflects a broader shift in the AI infrastructure market. The central bottleneck is no longer simply access to GPUs. It is the ability to assemble power, cooling, land, permits, data center

Read More »

Google Research touts memory-compression breakthrough for AI processing

The last time the market witnessed a shakeup like this was China’s DeepSeek, but doubts emerged quickly about its efficacy. Developers found DeepSeek’s efficiency gains required deep architectural decisions that had to be built in from the start. TurboQuant requires no retraining or fine-tuning. You just drop it straight into existing inference pipelines, at least in theory. If it works in production systems with no retrofitting, then data center operators will get tremendous performance gains on existing hardware. Data center operators won’t have to throw hardware at the performance problem. However, analysts urge caution before jumping to conclusions. “This is a research breakthrough, not a shipping product,” said Alex Cordovil, research director for physical infrastructure at The Dell’Oro Group. “There’s often a meaningful gap between a published paper and real-world inference workloads.” Also, Dell’Oro notes that efficiency gains in AI compute tend to get consumed by more demand, known as the Jevons paradox. “Any freed-up capacity would likely be absorbed by frontier models expanding their capabilities rather than reducing their hardware footprint.” Jim Handy, president of Objective Analysis, agrees on that second part. “Hyperscalers won’t cut their spending – they’ll just spend the same amount and get more bang for their buck,” he said. “Data centers aren’t looking to reach a certain performance level and subsequently stop spending on AI. They’re looking to out-spend each other to gain market dominance. This won’t change that.” Google plans to present a paper outlining TurboQuant at the ICLR conference in Rio de Janeiro running from April 23 through April 27.

Read More »

Amazon Middle East datacenter suffers second drone hit as Iran steps up attacks

Amazon was contacted for comment on the latest Bahrain drone incident, but said it had nothing to add beyond the statement in its current advisory. Denial of infrastructure Doing the damage is the Shaheed 136, a small and unsophisticated drone designed to overwhelm defenders with numbers. If only one in twenty reaches its target, the price-performance still exceeds that of more expensive systems. When aimed at critical infrastructure such as datacenters, the effect is also psychological; the threat of an attack on its own can be enough to make it difficult for organizations to continue using an at-risk facility.  Iran’s targeting of the Bahrain datacenter is unlikely to be random. Amazon opened its ME-SOUTH-1 AWS presence in 2019, and it is still believed to be the company’s largest site in the Middle East. Earlier this week, the Islamic Revolutionary Guard Corps (IRGC) Telegram channel explicitly threatened to target at least 18 US companies operating in the region, including Microsoft, Google, Nvidia, and Apple. This follows similar threats to an even longer list of US companies made on the IRGC-affiliated Tasnim News Agency in recent weeks. That strategy doesn’t bode well for US companies that have made large investments in Middle Eastern datacenter infrastructure in recent years, drawn by the growing wealth and influence of countries in the region. This includes Amazon, which has announced plans to build a $5.3 billion datacenter in Saudi Arabia, due to become available in 2026. If this is now under threat, whether by warfare or the hypothetical possibility of attack, that will create uncertainty.

Read More »

Data Center Jobs: Engineering, Construction, Commissioning, Sales, Field Service and Facility Tech Jobs Available in Major Data Center Hotspots

Each month Data Center Frontier, in partnership with Pkaza, posts some of the hottest data center career opportunities in the market. Here’s a look at some of the latest data center jobs posted on the Data Center Frontier jobs board, powered by Pkaza Critical Facilities Recruiting. Looking for Data Center Candidates? Check out Pkaza’s Active Candidate / Featured Candidate Hotlist Power Applications Engineer Pittsburgh, PA This position is also available in: Denver, CO and Andrews, SC.  Our client is a leading provider and manufacturer of industrial electrical power equipment used in industrial applications for mission critical operations. They help their customers save money by reducing energy and operating costs and provide solutions for modernizing their customer’s existing electrical infrastructure. This company provides cooling solutions to many of the world’s largest organizations and government facilities and enterprise clients, colocation providers and hyperscale companies. This career-growth minded opportunity offers exciting projects with leading-edge technology and innovation as well as competitive salaries and benefits. Electrical Commissioning Engineer Ashburn, VA This traveling position is also available in: New York, NY; White Plains, NY;  Dallas, TX; Richmond, VA; Montvale, NJ; Charlotte, NC; Atlanta, GA; Hampton, GA; New Albany, OH; Cedar Rapids, IA; Phoenix, AZ; Salt Lake City, UT;  Kansas City, MO; Omaha, NE; Chesterton, IN or Chicago, IL. *** ALSO looking for a LEAD EE and ME CxA Agents and CxA PMs. ***  Our client is an engineering design and commissioning company that has a national footprint and specializes in MEP critical facilities design. They provide design, commissioning, consulting and management expertise in the critical facilities space. They have a mindset to provide reliability, energy efficiency, sustainable design and LEED expertise when providing these consulting services for enterprise, colocation and hyperscale companies. This career-growth minded opportunity offers exciting projects with leading-edge technology and innovation as well as competitive

Read More »

No joke: data centers are warming the planet

The researchers also made use of a database provided by the International Energy Agency (IEA) that the authors pointed out contains more than 11,000 locations worldwide, of which 8,472 have been detected to dwell outside of highly dense urban areas. The latter locations were then used to “quantify the effect of data centers on the environment in terms of the LST gradient that could be measured on the areas surrounding each data center.” Asking the wrong question Asked if AI data centers are really causing local warming, or if this phenomenon is overstated, Sanchit Vir Gogia, chief analyst at Greyhound Research, said, “the signal is real, but the industry is asking the wrong question. The research shows a consistent rise in land surface temperature of around 2°C  following the establishment of large data centre facilities.” The debate, however, “has quickly shifted to causality: whether this is driven by operational heat from compute, or by land transformation during construction. That distinction matters scientifically, but it does not change the strategic implication.” Land surface temperature, said Gogia, is not the same as air temperature, and that gap will be used to challenge the findings. “But dismissing the signal on that basis would be a mistake,” he noted. “Data centers concentrate energy use, replace natural surfaces with heat-retaining materials, and continuously reject heat into the environment. Those are known drivers of thermal change.” He added, “the uncomfortable truth is this: Even if the exact mechanism is debated, the outcome aligns with first principles. Infrastructure at this scale alters its surroundings. The industry does not yet have a clean way to separate construction impact from operational impact, and that ambiguity makes the risk harder to model, not easier. This is not overstated, it is under-interpreted.” Location strategy must change But will the findings change

Read More »

Schneider Electric Maps the AI Data Center’s Next Design Era

The coming shift to higher-voltage DC That internal power challenge led Simonelli to one of the most consequential architectural topics in the interview: the likely transition toward higher-voltage DC distribution at very high rack densities. He framed it pragmatically. At current density levels, the industry knows how to get power into racks at 200 or 300 kilowatts. But as densities rise toward 400 kilowatts and beyond, conventional AC approaches start to run into physical limits. Too much cable, too much copper, too much conversion equipment, and too much space consumed by power infrastructure rather than GPUs. At that point, he said, higher-voltage DC becomes attractive not for philosophical reasons, but because it reduces current, shrinks conductor size, saves space, and leaves more room for revenue-generating compute. “It is again a paradigm shift,” Simonelli said of DC power at these densities. “But it won’t be everywhere.” That is probably right. The transition will not be universal, and the exact thresholds will evolve. But his underlying point is powerful. As rack densities climb, electrical architecture starts to matter not only for efficiency and reliability, but for physical space allocation inside the rack. Put differently, power distribution becomes a compute-enablement issue. Distance between accelerators matters, too. The closer GPUs and TPUs can be kept together, the better they perform. If power infrastructure can be compacted, more of the rack can be devoted to dense compute, improving the economics and performance of the system. That is a strong example of how AI is collapsing traditional boundaries between facility engineering and compute architecture. The two are no longer cleanly separable. Gas now, renewables over time On onsite power, Simonelli was refreshingly direct. If the goal is dispatchable onsite generation at the scale now being contemplated for AI facilities, he said, “there really isn’t an alternative

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »