Utilities Race to Meet Surging Data Center Demand With New Power Models

Over the last 18 months or so, the energy generation industry and its public utilities have been significantly impacted by the AI data center boom. It has been demonstrated across North America that the increase in demand for power, as driven by the demand for hyperscale and AI data centers, greatly exceeds the ability of […]

Over the last 18 months or so, the energy generation industry and its public utilities have been significantly impacted by the AI data center boom. It has been demonstrated across North America that the increase in demand for power, as driven by the demand for hyperscale and AI data centers, greatly exceeds the ability of the industry to actually generate and deliver power to meet the demand.

We have covered many of the efforts being made to control the availability of power. In response, utilities and regulators have begun rethinking how to manage power availability through means such as: temporary moratoriums on new data center interconnections; the creation of new rate classes; cogeneration and load-sharing agreements; renewable integration; and power-driven site selection strategies. 

But the bottom line is that in many locations utilities will need to change the way they work and how and where they spend their CAPEX budgets. The industry has already realized that their demand forecast models are hugely out of date, and that has had a ripple effect on much of the planning done by public utilities to meet the next generation of power demand.

Most utilities now acknowledge that their demand forecasting models have fallen behind reality, triggering revisions to Integrated Resource Plans (IRPs) and transmission buildouts nationwide. This mismatch between forecast and actual demand is forcing a fundamental rethink of capital expenditure priorities and long-term grid planning.

Spend More, Build Faster

Utilities are sharply increasing CAPEX and rebalancing their resource portfolios—not just for decarbonization, but to keep pace with multi-hundred-megawatt data center interconnects. This trend is spreading across the industry, not confined to a few isolated utilities. Notable examples include:

  • Duke Energy raised its five-year CAPEX plan to $83 billion (a 13.7% increase) and plans to add roughly 5 GW of natural gas capacity by 2029 to meet accelerating data center and industrial load growth.

  • Dominion Energy lifted its five-year capital plan to $50.1 billion, citing data centers as a primary driver while warning of potential rate pressure from grid modernization and capacity expansion.

  • NV Energy’s 2024 Integrated Resource Plan explicitly models about 5.9 GW of bundled-service data center requests by 2033, supported by new gas, storage, and renewable additions.

  • Salt River Project (Phoenix) is advancing a mixed portfolio of peaking gas and clean capacity, including the Coolidge Generating Station Expansion—a 575-MW project approved and now under construction—with additional peak resources under review.

  • Tennessee Valley Authority (TVA) is moving forward on advanced nuclear for long-duration firming, including a BWRX-300 small modular reactor application for the Clinch River site, and a power purchase agreement with Kairos Power’s Hermes-2 test reactor expected to support Google data centers around 2030.

These CAPEX expansions fund both new generation capacity in the form of modern combined-cycle and combustion-turbine plants, nuclear pilots, and renewables, and grid-side investments to move bulk power to where data centers are locating. This demand is now an explicit planning driver in utility integrated resource plans (IRPs) and board approvals. It’s important to note that these investments encompass both generation and transmission infrastructure.

New Rate Designs and Risk-Transfer Contracts Shift More Responsibility to Data Centers

Utilities are retooling tariffs to protect existing ratepayers and de-risk megawatt-scale customers. With a goal of protecting consumer rate payers, a number of different tariff designs have been put forth.

The goal is to ensure that the cost of new capacity and infrastructure upgrades falls primarily on large commercial users – particularly data centers -rather than being spread across residential and small-business customers. Several new tariff structures explicitly define data center capacity obligations and cost recovery terms. Examples include:

  • New data center rate class: Dominion Energy has proposed a dedicated rate category for customers ≥25 MW with ≥75% load factor, featuring 14-year take-or-pay–style commitments to cover stranded-cost risk and ensure “full cost of service.”

  • Take-or-pay / minimum-take provisions: Duke Energy is pursuing minimum-take contracts (requiring payment regardless of utilization) and up-front contributions for network upgrades tied to data center interconnections—part of a broader shift toward “contribution in aid of construction” (CIAC) requirements.

  • Standby and curtailable service riders: Large-load customers are increasingly directed toward standby-generator and curtailable-service schedules to formalize flexibility. Dominion’s Schedule SG and Schedule CS are examples under their targeted sector programs.

The net effect of these evolving tariffs is that utilities are socializing less risk from speculative or timing-uncertain AI loads, while providing greater queue certainty for data center developers willing to shoulder their share of capital costs.

Changing the Relationship Between Data Centers and Utilities

A major shift is underway: load flexibility is becoming a formal part of interconnection agreements. New legislation and regulatory frameworks across multiple regions are requiring data centers to demonstrate the ability to adjust or curtail power consumption during grid stress events.

From on-site cogeneration and load balancing to demand-response participation and remote-curtailment capabilities, utilities and regulators are increasingly embedding flexibility requirements into contracts and permitting. Examples include:

  • Under Texas SB 6, ratified in June 2025:  Beginning December 31, 2025, new large-load customers (≥75 MW) must be able to remotely curtail load or switch to on-site generation during emergencies. ERCOT will also begin procuring demand reductions from major customers. Interconnection agreements are expected to include fees, disclosure of backup power systems, and cost-sharing provisions as standard components.

  • PJM and SPP: Both grid operators are fast-tracking policies to curtail or manage large loads during scarcity events. The SPP “HILL/CHILL” framework establishes a 90-day expedited interconnection path when large-load customers pair with generation resources, defining curtailable service classes for planning and market participation.

  • Voluntary demand-response partnerships: To preempt mandatory curtailment mandates, some hyperscalers are signing voluntary flexibility agreements. Google, for instance, has reached demand-flexibility deals with Indiana Michigan Power and the Tennessee Valley Authority (TVA) to shift or reduce AI workloads during peak grid demand—an emerging model for bridging near-term capacity gaps.

Collectively, these developments signal a new era of active coordination between utilities and data centers, in which grid reliability, flexibility, and cost allocation are shared operational priorities.

Upgrading Power Transmission: Accelerate, Reconductor, Right-Size

Serving today’s multi-gigawatt data centers and campus-scale developments requires both new transmission lines and rapid capacity upgrades along existing corridors. With data center interconnection queues expanding across nearly every regional transmission organization (RTO), utilities and regulators are under pressure to streamline approvals and unlock capacity faster.

  • PJM approved $5.9–$6.7 billion in near-term transmission projects in 2025, explicitly citing data center–driven load growth and resource shifts as key justifications.

  • Advanced conductors: Google and CTC Global have partnered with utilities to reconduct existing lines using ACCC® (Aluminum Conductor Composite Core) technology, boosting transmission capacity in months rather than years. Priority is being given to reconductoring lines that unlock capacity for new data center sites.

  • Aggressive planning upgrades: PJM’s evolving Regional Transmission Expansion Plan (RTEP) process aims to “right-size” near-term fixes for long-term needs. The DOE and NREL have identified Grid-Enhancing Technologies (GETs) such as Dynamic Line Rating (DLR) and topology optimization as practical, near-term pathways for unlocking transmission capacity without lengthy new-build timelines.

  • Federal rulemaking: Two FERC orders are reshaping how utilities and RTOs plan for both new generation and surging load growth:

    • FERC Order 2023 (2023): Requires cluster-based interconnection studies with enforceable deadlines and penalties, designed to reduce the interconnection backlog and expedite capacity additions.

    • FERC Order 1920/A/B (2024–2025): Mandates 20-year regional transmission plans, state involvement in cost allocation, and greater transparency, giving utilities a framework to plan around structural load growth driven by AI and industrial electrification.

  • Process innovation: SPP is implementing a 90-day fast-track path for “high-impact large loads” paired with new generation under its HILL/CHILL policy framework.

Together, these measures reflect a system-wide acceleration of transmission modernization, combining new lines, smarter planning, and digital tools to move power where AI and hyperscale demand is rising fastest.

Green Tariffs and “Bring-Your-Own-Clean-Power” Programs Are Changing How Data Centers Source Energy

Utilities are expanding subscription-based renewable programs and custom clean-energy constructs that enable data centers to meet sustainability and carbon-reduction goals within regulated tariffs. For large-scale operators, the challenge lies in navigating a fragmented landscape: each utility administers its own program, requiring project-specific power purchase agreements (PPAs) and regional tailoring to reflect local policy and grid conditions.

Examples of key programs include:

  • Duke Energy – Green Source Advantage (GSA / GSA Choice, North and South Carolina): Allows large customers to contract utility-backed renewable projects through long-term agreements. The program was expanded in 2024 to add new capacity and greater flexibility for participants.

  • Georgia Power – CRSP / CARES: The Clear and Renewable Energy Subscription Program offers 1,000–2,100 MW of utility-procured renewables for large-customer subscription. QTS Data Centers subscribed to approximately 350 MW under CRSP for its Atlanta-area facilities.

  • Dominion Energy – Schedule RG / Schedule CFG: Provides utility-sourced carbon-free and renewable energy options for large commercial and industrial (C&I) customers. Schedule RG (approved in 2018) and the newer Schedule CFG (for projects ≥1 MW) are voluntary programs that allow customers to directly procure renewable generation through Dominion-backed assets.

A growing number of utilities are evolving from pass-through energy suppliers to active counterparties, developing or contracting clean-energy assets that are directly matched to data center load profiles. This integrated approach (where power buyers participate in generation planning) aims to improve efficiency, transparency, and reliability in how large loads source renewable energy.

Regional Utility Responses Are Diverging

Not all power generation, and not all regulatory response, is created equal. Across the U.S., states and regional transmission operators (RTOs) are adapting to data center–driven load growth in markedly different ways, reflecting local politics, resource mixes, and grid constraints.

  • Virginia (PJM): Data centers now account for approximately 25% of statewide electricity consumption, according to Dominion’s filings and state reports. Dominion’s Integrated Resource Plan (IRP) and new large-load rate class proposals formally recognize data centers as the primary driver of load growth and cost allocation debates. Transmission capacity remains the chokepoint, making advanced conductor pilots and PJM’s RTEP expansion windows key to sustaining growth.

  • Texas (ERCOT): Senate Bill 6 (2025) effectively resets the social contract for large loads—requiring operators to flex or face emergency curtailment—and is expected to push wider adoption of on-site generation, energy storage, and hybrid PPAs. Other utilities and cooperatives across the state are expected to mirror ERCOT’s flexibility protocols in their own tariffs.

  • Arizona (SRP / APS): Rapid regional growth is driving a buildout of gas peaker plants paired with battery storage, alongside stricter queue management and prioritization. Salt River Project’s Coolidge Expansion exemplifies a reliability-first strategy, with clean-energy components layered in to support long-term decarbonization goals.

  • Midwest (MISO / Indiana): The Indiana Utility Regulatory Commission (IURC) has approved new large-load interconnection rules, while utilities such as Indiana Michigan Power (I&M) are signing demand-response agreements—including with Google—to mitigate peak load. Policymakers are advancing cost-sharing requirements for new generation supporting big-load customers.

  • SPP (Plains states): The Southwest Power Pool (SPP) is actively marketing the region to High Impact Large Load (HILL) customers through accelerated interconnection studies and firm/curtailable service classes, aiming to attract data center development away from saturated hubs like Virginia and northern Texas.

Regional differences in regulation and resource strategy are now shaping the geography of new data center investment, rewarding jurisdictions that can align policy agility, grid capacity, and clean-power availability.

What This Means for Data Center Developers

Over the next several years, the structure of power procurement deals for data centers is likely to evolve significantly. Utilities will increasingly require greater up-front financial participation from customers, shifting capital and risk onto large-load developers. Expect to see:

  • Contribution-in-aid-of-construction (CIAC) payments or similar up-front contributions to fund new substations, network upgrades, and capacity expansions.

  • Minimum-take or take-or-pay obligations to guarantee long-term revenue recovery for utilities.

  • Extended contract terms—typically 10 to 15 years—to secure capacity and protect other ratepayers from stranded-cost exposure.

Flexibility will become a baseline requirement. Interconnection agreements may now mandate curtailment capabilities, demand-response participation, and certified backup generation. In ERCOT, for example, new large loads ≥75 MW must be equipped for remote disconnection or on-site generation under Senate Bill 6 (2025).

Transmission-friendly regions will rise in priority for new site development. Locations within PJM subregions or along SPP’s HILL corridor, where reconductoring and RTEP upgrades can unlock capacity quickly, will gain competitive advantage as interconnection bottlenecks persist elsewhere.

Data center developers will also need to maintain ongoing visibility into utility and regulatory planning cycles, tracking updates from individual utilities, regional transmission operators (RTOs), and federal agencies such as FERC. Understanding how generation mix, transmission planning, and tariff reform interact will be essential to long-term siting and investment strategy.

In short, the path to power is becoming more capital-intensive, flexible, and policy-dependent, requiring data center developers to act as active partners in the evolving utility ecosystem.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Leap second proposal will keep software stacks in sync

“That means an enterprise does not only have to worry about what its own servers do. It has to consider what happens when its cloud provider, operating system, identity provider, database, external APIs, and on premises systems interpret the same moment differently,” Kolev said. “This is precisely the type of

Read More »

Cisco bundles fixes for multiple vulnerabilities, some critical, into one patch

CVE-2026-20274 and CVE-2026-20279 both address lifetime resource control issues, such as inappropriate certificate validation, incorrect or missing authorization for critical functions, resource operation after release or expiration, out-of-bounds read or write, initialization of resources with insecure details, and resource allocation without throttling limits. The five other vulnerabilities are rated between

Read More »

Shell, partners sign agreement for Angola offshore blocks

Shell, QatarEnergy, and Sonangol E&P signed Heads of Terms regarding the Risk Service Contracts for Blocks 8 and 22 offshore Angola, with Angola’s National Agency for Oil, Gas and Biofuels (ANPG).  The move is a step in evaluating offshore potential and building on Angola’s established role in Africa’s energy sector, Shell said in a release Sept. 9. Alioune Sourang, country chair of Shell Angola, said the signing is “another positive step in Shell’s renewed engagement with Angola,” and that it “builds on the momentum from exploration block entries with Chevron, Equinor, and Sonangol P&P.”  Under the agreement, Shell will be operator with 50% interest, QatarEnergy will hold 30% working interest, and Sonangol will hold 20% in the two offshore blocks. Shell’s participation in the Heads of Terms is through BG International Ltd. – Sucursal em Angola, a Shell company. The agreement was signed in the Angolan capital Luanda on the sidelines of the Angola Oil & Gas Conference. It is subject to the relevant governmental approvals and final contractual arrangements.

Read More »

Barclays conference: Chevron eyes ‘factory-type’ development in Venezuela; Exxon says operators matter more than ever

Executives from Chevron Corp. and ExxonMobil Corp. spoke at the Barclays 40th Annual Energy-Power Conference in New York this week, expanding on how they’re approaching the next phase of upstream growth, highlighting opportunities from Venezuela to Guyana, and offering clues about how major operators are evaluating future resource development opportunities. As OGJ did following , we’ve gathered notable comments from company leaders about the opportunities and challenges shaping their businesses. Chevron Unsurprisingly, a significant share of the conversation between Barclays analyst Betty Jiang and Chevron Corp. chief financial officer Eimear Bonner focused on the company’s ambitions in Venezuela, where the company last week signed a deal to over the next 5 years. Bonner reiterated the attractive financial picture for Chevron, pointing to operating costs below $20/bbl and a goal of hitting 600,000 b/d in 2031 (from today’s roughly 280,000 b/d) just from primary recovery. Chevron teams expect that production will plateau between 600,000 and 700,000 b/d for most, if not all, of the 2030s. “There’s a lot more upside there,” Bonner said. “This is growth at low cost and very attractive returns.” Helping to solidify Chevron’s financial equation, Bonner added, is that the company’s existing infrastructure in Venezuela is in good shape and that its expansion plans won’t require major capital projects but will instead lean on pipeline and utility expansion work. “The best way to think about this is we are developing or intend to develop this like the way we develop the Permian,” Bonner said. “It really is just another factory-type development. There will be a period of investment and a period of plateau. We’re looking forward to adopting and scaling and implementing all the lessons learned from the factory experience that we have.” ExxonMobil With a next quarter in the Stabroek block offshore Guyana, ExxonMobil Corp. is

Read More »

Hydrocarbons and Geothermal Energy Office Announces $300,000 to Help Identify Hidden Geothermal Systems

WASHINGTON — The U.S. Department of Energy’s (DOE) Hydrocarbons and Geothermal Energy Office (HGEO) today announced the $300,000 Geologic Enhanced Mapping System (GEMS) Prize to help identify hidden geothermal systems by using geophysical data to identify faults and structures indicative of geothermal resources. Activities enabled by this prize will help deliver on President Trump’s Executive Order, Unleashing American Energy, by advancing geothermal exploration, in turn supporting the potential for geothermal to provide affordable, reliable, around-the-clock domestic electricity to Americans. “Unlocking America’s vast geothermal potential is essential to securing our energy dominance and providing the reliable, dispatchable baseload power our nation needs,” said DOE Acting Assistant Secretary of the Hydrocarbons and Geothermal Energy Office Curt Coccodrilli. “By challenging innovators to map hidden geothermal resources, the GEMS Prize will boost efforts to strengthen grid stability, reduce utility expenses for U.S. households, and deliver the secure, steady electricity required to fuel our domestic manufacturing resurgence and next-generation AI data centers.” The GEMS Prize challenges competitors to develop, train, and test algorithms that generate enhanced geologic fault datasets—which, in turn, can support mapping and modeling for geothermal and critical mineral resources. By using real-world datasets and testing ideas against geophysical data, the GEMS Prize is expected to accelerate discoveries of new, commercially viable hidden geothermal systems while reducing exploration and development risks. The competition comprises two rounds, with prizes ranging from $15,000 to $100,000. Both individual and group competitors can participate, and submissions are due December 3, 2026. Learn more on the competition website. Learn how HGEO is unleashing the full potential of America’s hydrocarbon and geothermal resources to provide affordable, reliable, and secure energy here.

Read More »

EIA sees Brent near $90/bbl in second-half 2026 amid Middle East disruptions

Global crude oil prices are expected to remain elevated through yearend 2026 as Middle East production disruptions and constrained exports continue to draw down inventories, the US Energy Information Administration (EIA) said in its September Short-Term Energy Outlook (STEO). EIA forecasts Brent crude oil spot prices will average about $90/bbl in second-half 2026, $8/bbl higher than projected in its August outlook. Brent averaged $91/bbl in August, up $7/bbl from July, as constrained Middle East exports led to additional production shut-ins. Middle East crude production shut-ins averaged an estimated 6.7 million b/d in August, up from 5.0 million b/d in July. EIA expects disruptions to ease gradually but remain substantial, with shut-in volumes averaging about 5.7 million b/d in fourth-quarter 2026. Oil flows through the Strait of Hormuz and Bab el-Mandeb remain constrained, although producers and shippers are increasingly using pipeline and overland bypass routes and ship-to-ship transfers. Stay updated on oil price volatility, shipping disruptions, LNG market analysis, and production output through OGJ’s Iran war content hub. Renewed US blockade of Iranian exports after Iran’s tanker attacks in Hormuz, plus the Treasury Department’s Office of Foreign Assets Control (OFAC) sanctions against Iranian economic and oil interests, will cut Iran’s exports and production, EIA said. In addition, attacks in Bab el-Mandeb roughly halved August loadings at Yanbu, the Red Sea port that bypasses Hormuz, according to Vortexa estimates. Saudi Arabia has rerouted barrels through the Suez Canal—longer and costlier for Asian buyers—and reportedly started ship-to-ship transfers outside the Persian Gulf, but EIA expects Red Sea constraints to cap Saudi supply near term. The disruptions have led to sharp inventory draws. EIA estimates global oil inventories fell by an average 3.9 million b/d in second-quarter 2026 and forecasts additional draws of 3.0 million b/d in the third quarter and 1.7 million b/d

Read More »

Woodside, PEMEX take initial step toward expanded partnership in Mexico

@import url(‘https://fonts.googleapis.com/css2?family=Inter:wght@100..900&display=swap’); .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; color: color-mix(in srgb, currentColor 60%, transparent); } #onetrust-pc-sdk [id*=btn-handler], #onetrust-pc-sdk [class*=btn-handler] { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-policy a, #onetrust-pc-sdk a, #ot-pc-content a { color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-pc-sdk .ot-active-menu { border-color: #c19a06 !important; } #onetrust-consent-sdk #onetrust-accept-btn-handler, #onetrust-banner-sdk #onetrust-reject-all-handler, #onetrust-consent-sdk #onetrust-pc-btn-handler.cookie-setting-link { background-color: #c19a06 !important; border-color: #c19a06 !important; } #onetrust-consent-sdk .onetrust-pc-btn-handler { color: #c19a06 !important; border-color: #c19a06 !important; } Woodside Energy and Petróleos Mexicanos (PEMEX) will explore opportunities to expand oil and gas projects through a newly signed non-binding Memorandum of Understanding (MoU). The MoU will allow analysis of potential opportunities for exploration and extraction of hydrocarbons in Mexico’s deepwater and will enable an exchange of technical knowledge, experience, and industry best practices in the oil and gas sector, the companies said in a release Sept. 3. Woodside and PEMEX are jointly developing the Trion oil project about 180 km off Mexico’s coastline and 30 km south of the US-Mexico maritime border. The project, about 64% complete as of June 30, 2026, lies in the Perdido Fold Belt at depths in 2,500–2,600 m of water. Mexico’s first ultra-deepwater oil development, Trion is designed for 24 subsea wells connected to a new 100,000 b/d floating production unit (Tláloc) and 950,000-bbl floating storage and offloading unit (Chalchi). Through estimated total capital investment of $7.2 billion, the development is targeting 479 MMboe of best estimate (2C) contingent oil and gas with first oil targeted for 2028. Woodside is operator at Trion with a 60% interest. PEMEX holds the remaining 40% interest. Trion field was

Read More »

Diversified Energy to acquire Birch Permian in $1.8-billion deal

Diversified Energy Co. has agreed to acquire Birch Permian Holdings Inc. and certain affiliated companies from affiliates of Elliott Investment Management LP for about $1.8 billion, expanding its position in the Permian basin and adding operated, producing assets to its portfolio. The acquisition is expected to increase Diversified’s production by about 35%, the company said in a release Sept. 2. Following closing, Diversified said operated gross production volumes are expected to total about 2.5 bcefd, or roughly 1.6 bcfed net. Birch’s assets currently produce about 68,000 boe/d net (about 409 MMcfed), consisting of 38% oil, 32% natural gas liquids, and 30% natural gas. The portfolio includes about 480 net wells across 46,000 net mineral acres in the Permian basin. The acquired properties contain proved reserves of about 1.17 tcfe and a reported PV-10 value of about $2 billion. The transaction also includes gathering, processing, and water-handling infrastructure. Midstream assets comprise 12 central production facilities, nine well gathering facilities, more than 60 miles of gathering pipeline, and five water disposal facilities connected by more than 80 miles of disposal and recycling pipelines. Processing capacity includes up to 345,000 b/d of oil and 310 MMcfd of gas. Diversified said the acquisition establishes a platform for further consolidation of mature, producing Permian assets consistent with its strategy of acquiring and managing proved developed producing (PDP) properties. The company also cited enhanced oil recovery (EOR) potential, noting the acquired position includes more than 150 permitted EOR locations. “This $1.8 billion acquisition is our largest in the company’s 25-year history,” said chairman and chief executive officer Rusty Hutson Jr. He said the assets provide a concentrated operated position in the Permian basin with integrated infrastructure and predictable cash flow characteristics. The acquisition is expected to be funded primarily through a privately rated asset-backed securitization originated

Read More »

Nvidia invests $3.5B in MediaTek to extend its grip on AI

AI infrastructure: MediaTek will work with Nvidia’s NVLink Fusion ecosystem to enable customers to develop custom AI infrastructure designed to integrate with Nvidia rack-scale systems and AI factories. Local AI computing: The companies will continue to collaborate on multiple generations of Nvidia RTX Spark and DGX Spark PC chips, powering consumer PCs, AI developer supercomputers, and enterprise-class workstations, that integrate Nvidia GPUs with MediaTek SoCs. Automotive: MediaTek and Nvidia will continue developing platforms for AI-powered, software-defined vehicles in the era of physical AI.  “MediaTek is one of the world’s great semiconductor companies, with exceptional expertise in system-on-chip design, connectivity, leading performance and power efficiency,” said Jensen Huang, founder and CEO of Nvidia, in a statement. “Together, we’re building platforms that bring Nvidia accelerated computing to new markets and give customers the freedom to create differentiated AI systems at enormous scale.” NVLink is a high-performance interface, but this move also helps lock in customers to the Nvidia platform, since NVLink Fusion is not about to hook up to AMD processors. For MediaTek, the Nvidia investment provides a big pile of cash and access to Nvidia’s infrastructure as it attempts to establish itself as a major supplier of custom data center silicon.

Read More »

AI Puts Fiber on the Critical Path

Fiber Becomes Part of the Build A decade ago, DC Blox might have prioritized land near existing fiber from AT&T, Verizon, Zayo or another established network provider. That calculation is different today. As data center campuses have grown and hyperscalers have become a larger share of the customer base, Wabik said connectivity has increasingly become another construction package associated with the project itself. “If Zayo or Verizon or AT&T just happens to be there close by, that’s a good thing,” he said. “But fiber construction is inherently anymore just part of the construction component.” That changes the site-selection question from Is there fiber nearby? to Can fiber be built here at the scale and diversity the customer requires? For DC Blox, Wabik said that can mean assessing whether sufficient public right-of-way exists to establish three or sometimes four diverse fiber paths into a data center. That distinction is important, as AI workloads push infrastructure into markets where power, land and energy options may be more abundant than established carrier density. The hyperscalers themselves have also become major network builders. Wabik characterized them provocatively as today’s telecom providers, pointing to the scale of terrestrial fiber they commission as well as the growing role of companies such as Amazon, Google and Meta in subsea cable development. The point is less that traditional carriers have disappeared than that hyperscalers increasingly design, commission and control enormous portions of the connectivity required to support their own infrastructure. DC Blox now sees requests for 864-count fiber as routine and, in some cases, 1,728-count cable. That would have been difficult to imagine during an earlier era when a handful of fibers from an established carrier could satisfy a data center’s connectivity requirements. AI-Scale Fiber Gets Physical The scale becomes clearer when the discussion moves from abstract network

Read More »

Power First: AI Data Centers Become Energy Systems

For decades, data centers consumed electricity much like other large commercial customers: power arrived from the utility, while batteries and diesel generators stood behind it to protect the load. AI is starting to break that model. As data center campuses grow toward hundreds of megawatts and, in some cases, gigawatt scale, developers are increasingly taking responsibility for an energy system that once sat largely outside the data center boundary. Natural gas supply, onsite generation, fuel cells, batteries, controls and the behavior of the compute load itself are increasingly becoming parts of the same infrastructure system. That was the central thread running through “Power First: The New Playbook for Delivering AI Data Centers,” an Aug. 4 session at the Data Center Frontier Trends Summit 2026 in Reston, Virginia. Moderated by Fengrong Li, Senior Managing Director at FTI Consulting, the panel brought together Jim Summers, CEO of GPC Infrastructure; Shankar Achanta, EVP and Chief Product and Technology Officer at FuelCell Energy; Judith Judson, Executive Vice President at Calibrant Energy; and Yuval Bachar, Founder and CEO of EdgeCloudLink. The discussion began with the immediate constraint — the grid cannot deliver capacity on the timetable AI developers increasingly require — but quickly moved beyond the familiar concept of “bridge power.” The larger question was what happens when the data center itself becomes an energy system. From Backup Power to Prime Power Behind-the-meter generation is not new. What has changed is its role and scale. “Traditionally, behind-the-meter generation has been for backup and the sizes were smaller,” Achanta said. “But what they’re seeing is the demand for the power is growing rapidly due to the data center load.” Interconnection queues, transmission limitations and equipment supply constraints are pushing onsite generation into what Achanta called the “front seat,” supplying primary power rather than waiting behind the

Read More »

NVIDIA Pushes DSX Deeper Into Data Center Infrastructure

The joint reference design appears in Trane’s Continuum Rubin DSX and Eaton’s Beam Rubin DSX platforms. The goal is a pre-coordinated architecture stretching from grid power to the chip rather than requiring developers and engineering teams to independently assemble electrical and mechanical systems for each project. The systems are also intended to exchange operating data. Rather than cooling and electrical systems responding independently, the systems can instead exchange leading indicators and respond more dynamically to changing operating requirements. This is an approach that closely mirrors NVIDIA’s larger DSX philosophy. Trane and Eaton are also designing the architecture to accommodate future liquid-cooling and direct-current power-distribution technologies. That future-proofing matters as rack power densities continue to rise. An electrical and cooling plant optimized for one GPU generation may otherwise become a constraint several hardware generations later. The Broader DSX Buildout The Lancium, Cloverleaf and Trane/Eaton agreements are part of a considerably wider expansion of the DSX ecosystem. Earlier deals show NVIDIA moving into many of the same infrastructure layers through partnerships spanning powered land, electrical design, digital twins and even project financing. In May, NVIDIA and IREN announced plans to support as much as 5 GW of DSX-aligned AI infrastructure across IREN’s global development pipeline, with the companies identifying IREN’s 2 GW Sweetwater campus in Texas as an expected flagship DSX deployment. NVIDIA also received a five-year right to purchase up to 30 million IREN shares at $70 each, representing a potential investment of as much as $2.1 billion. The infrastructure ecosystem has widened as well. Siemens, NVIDIA and Fluence, incorporating nVent design considerations, have developed a DSX Vera Rubin-aligned electrical, power and controls architecture extending from the utility connection to the rack. ABB is integrating digital models of medium-voltage switchgear, power-distribution equipment and UPS systems into the Omniverse DSX Blueprint, while Vertiv

Read More »

ERCOT Puts Texas AI Megawatts to the Test

Texas has no shortage of proposed data center megawatts. The harder question is how many of them are real. That distinction is becoming central to the Electric Reliability Council of Texas (ERCOT) as the state works through an unprecedented wave of AI, hyperscale and other large-load requests. In June, ERCOT said it was tracking more than 438 GW of proposed large loads, nearly 89% associated with data centers. By Aug. 3, Gov. Greg Abbott said ERCOT was considering approximately 474 GW of connection requests, roughly 90% from data centers and more than five times the system’s record peak demand. Neither figure represents a forecast of what will actually get built. And that is increasingly the point. ERCOT’s new Batch Zero process is beginning to put harder boundaries around Texas’ enormous development pipeline, asking which projects have enough maturity, technical information and commitment to warrant space in the transmission plan. At the same time, new requirements surrounding voltage ride-through and dynamic modeling are forcing another realization on the AI infrastructure industry: at hundreds of megawatts, a data center is no longer simply a customer at the edge of the grid. Its behavior can affect the grid itself. For developers, utilities and investors, Texas is becoming a large-scale test of what separates an announced AI campus from executable infrastructure. The Queue Is Not the Grid The sheer scale of ERCOT’s large-load queue can obscure how early many projects remain. ERCOT’s April 2026 monthly report offered a revealing snapshot. Large-load applications totaled 445.8 GW through 2033, but 321 GW had no studies submitted to ERCOT. Another 93.7 GW was under ERCOT review, while 22 GW had met the applicable Section 9.5 requirements. Against that enormous development funnel, ERCOT reported just 5.9 GW of observed energized large loads, with another 3.2 GW approved to

Read More »

DCF Trends Summit: AI Compresses the Data Center Hardware Lifecycle and Raises the Stakes for ITAD

The AI infrastructure race is largely a story about getting more computing into data centers faster. But the accelerated hardware cycle is creating an equally consequential problem at the other end of the rack: getting yesterday’s equipment back out while it is still valuable. GPU systems built around increasingly dense and specialized AI architectures are beginning to challenge traditional assumptions about IT asset disposition, or ITAD. Where conventional enterprise infrastructure might remain in service for three to five years, newer GPU platforms can face refresh cycles of 18 to 24 months, according to Josh Humm, Data Center Solutions Manager at Dynamic Lifecycle Innovations. That compression changes the economics as well as the mechanics of decommissioning. “The faster we can get the materials out of your building, the more it’s worth, the more we can return to your program,” Humm said. Humm joined DCF Contributing Editor Doug Black for a DCF Show podcast recorded at the third annual Data Center Frontier Trends Summit, held Aug. 4-6 in Reston, Virginia. Their conversation focused on a less visible part of the AI infrastructure buildout: what happens to servers, accelerators, memory, storage and networking gear when the next generation arrives. The answer increasingly touches facility operations, data security, logistics, sustainability and potentially millions of dollars in recoverable hardware value. AI Hardware Changes the Exit Path AI systems create some obvious physical challenges for decommissioning. Traditional ITAD teams accustomed to pulling 1U and 2U servers out of air-cooled racks may instead encounter liquid-cooling manifolds, substantially heavier systems and equipment requiring specialized rigging and handling procedures. Humm said some systems can weigh between 5,000 and 6,000 pounds. “We’re not pulling out just 1U, 2U servers out of racks anymore,” he said. Liquid cooling adds another layer. Removing infrastructure designed around direct-to-chip or other liquid-cooling architectures can

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »