A 1988 Data Center Becomes a 20 MW AI Asset The second presentation, Converting a 1990 Enterprise Data Center to 20MW AI Workloads, featured Coe alongside Ari Chernikoff, vice president of development at Legacy Investing, and Dan Amundson, project manager at Gardner Builders. The project centered on 1001 Third Avenue South in downtown Minneapolis, a […]

A 1988 Data Center Becomes a 20 MW AI Asset

The second presentation, Converting a 1990 Enterprise Data Center to 20MW AI Workloads, featured Coe alongside Ari Chernikoff, vice president of development at Legacy Investing, and Dan Amundson, project manager at Gardner Builders.

The project centered on 1001 Third Avenue South in downtown Minneapolis, a financial-services computing facility originally constructed in 1988. The building had supported earlier generations of enterprise computing before portions were converted to commercial office space and smaller colocation operations. Although its remaining operating data center load had declined to approximately 500 kilowatts by the time the AI redevelopment began, the property retained substantial infrastructure inherited from its original mission-critical design.

Tall ceilings, robust floor loading, raised access floors, existing medium-voltage substations, and established utility connections made the building an unusually strong candidate for conversion. These characteristics, Chernikoff explained, can determine whether an existing building offers a practical path to high-density computing or proves economically unsuitable for redevelopment.

Legacy Investing had identified a market opportunity in what Chernikoff called the industry’s “missing middle”: facilities generally ranging from 20 MW to 80 MW, rather than the 100 MW-plus campuses increasingly associated with hyperscale and frontier AI development. The company viewed existing buildings with available power and favorable infrastructure characteristics as potential shortcuts to deployment, particularly where demand for AI inference and other latency-sensitive workloads favored proximity to major urban markets.

Following an AI tenant commitment in summer 2024, the development team faced an aggressive initial requirement: Deliver the first 5 MW of capacity by the end of that year. The first phase was ready for service approximately four months after Gardner’s involvement became formalized, followed by another 5 MW in 2025 and an expansion program ultimately reaching 20 MW over roughly 20 months.

All of this had to be accomplished while keeping existing data center customers and commercial tenants operational.

For Coe, the complexity was well matched to his professional experience. He’s a data center “OG” in the best sense of the term—a respected industry veteran with approximately 31 years of design experience, reaching back to an era before highly standardized facility templates became commonplace, when individual projects often demanded specialized approaches to equipment integration and infrastructure design. Coe had already demonstrated that perspective during DCF’s coverage of Vertiv’s Peter Panfil at 7×24 Exchange Spring 2026.

“Because data centers used to be one of a kind, I’m one of the few specialists left that can take unique buildings and find parts and pieces and the best optimum way to upgrade them,” Coe told the audience in San Antonio last Tuesday.

That institutional knowledge became an essential resource as the team confronted a building containing multiple generations of electrical and mechanical infrastructure.

The original facility included aging UPS equipment, an assortment of generators, eight medium-voltage substations, and chillers approaching or exceeding their intended service lives. Rather than replacing everything in a single construction campaign, the project required successive operating configurations that could deliver new AI capacity while maintaining existing loads.

Chernikoff described the team’s willingness to depart from conventional design and procurement sequences as another important element of its strategy.

“We always try to let procurement wag the design dog,” he said.

Instead of establishing a fixed equipment specification and waiting for manufacturers to deliver every component, Legacy aggressively sourced available equipment and worked with Syska Hennessy and Gardner Builders to adapt the designs accordingly. The project incorporated a mixture of existing generators, used Caterpillar equipment, new MTU units, and alternative electrical distribution components selected partly because they could meet the required schedule.

Coe described using Square D panelboards in place of conventional busway because busway lead times were incompatible with the deployment timetable. Existing generator arrangements were reconfigured, older systems were integrated with newer UPS equipment, and electrical distribution evolved through successive phases as additional capacity became available.

The result was not an exercise in abandoning engineering discipline. Rather, it demonstrated how experienced engineers could accommodate nonstandard equipment combinations while maintaining the necessary system-level reliability.

Amundson acknowledged that the speed of the first phase sometimes created problems requiring additional work during subsequent stages. Integrating new chillers with existing equipment involving different water temperatures, flow rates, and operating characteristics proved especially challenging, as did modifying the building’s older electrical systems while portions remained energized and in service.

The process demanded constant collaboration among the owner, engineers, construction managers, subcontractors, equipment suppliers, and building operations personnel.

It also provided a concrete illustration of Mahmood’s argument that the ability to finance or announce an ambitious infrastructure project is not equivalent to the ability to deliver and operate it.

Engineering AI Into an Occupied Downtown Building

The physical constraints of the Minneapolis project were particularly formidable. The building occupies an entire downtown block, with essentially no adjacent land available for new generators, cooling equipment, or other major infrastructure. Expansion therefore required repurposing existing floors and installing additional equipment within the building or on its roof.

Five generators were eventually installed on a rooftop structure using an enormous mobile hydraulic crane transported from Iowa. According to Amundson, the crane required 21 truckloads and two days of assembly, with the lift plan accounting for different generator weights, a roughly 185-foot reach from the sidewalk to the installation area, and underground vaults and basement structures near the crane setup locations.

The mechanical work was equally demanding. To install three new 1,500-ton chillers, the team temporarily removed sections of the building’s fifth-floor curtain wall and used detailed three-dimensional modeling to establish equipment paths, piping routes, and construction sequences. Existing cooling systems had to continue serving operational data halls throughout the installation, requiring a carefully phased approach in which new equipment was brought online as additional electrical capacity became available.

The computing equipment introduced further complications. The deployment incorporated Cerebras AI systems with substantial liquid-cooling requirements, including cabinets drawing approximately 55 kW each, with most of the heat load removed through liquid cooling. Associated networking infrastructure relied on a different thermal approach.

Chernikoff explained that Cerebras had encountered humidity and condensation challenges at other deployments where liquid-cooled AI equipment and air-cooled networking systems operated in close proximity. The Minneapolis building’s layout allowed the engineering team to separate those environments, placing AI computing equipment on one floor and associated networking infrastructure on another.

The strategy reflects a broader push to extract AI capacity from existing facilities. As DCF reported in its coverage of Corvex’s liquid-cooled AI retrofit strategy, operators are exploring alternative thermal architectures to deploy high-density accelerators within buildings originally designed around conventional air cooling, sometimes avoiding extensive facility-wide mechanical reconstruction.

The Minneapolis installation incorporated coolant distribution units, buffer tanks, rear-door cooling equipment, and extensive flow-control instrumentation. Coe described the use of hundreds of Belimo valves to provide detailed monitoring and control of water temperatures and flow rates serving the computing systems.

Even the choice of piping materials revealed the complexity of adapting conventional construction practices to specialized AI requirements. The team selected carbon-steel piping with Victaulic fittings to accelerate installation, then encountered stringent requirements for iron content in the cooling-water system. Working with chemical treatment specialists, the contractors developed flushing and passivation procedures intended to satisfy Cerebras’ water-quality specifications.

These challenges reinforced Mahmood’s earlier observation that the future of cooling will not be determined by a single favored technology. The effective solution depends on the workload, available infrastructure, maintainability, and the ability to deliver dependable thermal performance under actual operating conditions.

But perhaps the most impressive accomplishment was maintaining uninterrupted service throughout the conversion.

Amundson explained that the project’s later phases required construction immediately adjacent to operating data halls, including modifications to power distribution and chilled-water infrastructure supporting active equipment. During the second major deployment phase, the team issued more than 100 maintenance advisories involving work that affected operating systems or their redundant feeds.

“We didn’t cause any outages, but we did touch the redundancy over 100 times,” Amundson said.

Coe described the corresponding electrical challenges, including changes to UPS configurations, power distribution panels, and individual cabinet circuits as the building evolved toward the required eight-path power architecture. The work relied on the redundancy built into the installed computing systems to keep workloads running while portions of the supporting infrastructure were modified.

With approximately 28.5 MW of utility capacity available for the 20 MW IT deployment, operating efficiency was also essential. Coe reported that the facility generally achieved a PUE of approximately 1.30 to 1.31, while Chernikoff identified a further improvement target of 1.26 to 1.27.

The achievement illustrated the physical counterpart to Mahmood’s warning about autonomous infrastructure management. Whether decisions are made by experienced engineers or intelligent control systems, critical infrastructure must be understood as a collection of interacting systems in which changes to one component can have consequences throughout the operating environment.

For the Minneapolis team, the responsibility was to execute an unusually aggressive construction program without allowing those interactions to interrupt service.

The Grid, the Community, and the Social License to Operate

Power availability was central to the Minneapolis redevelopment strategy. Chernikoff explained that Legacy worked with Xcel Energy to secure incremental capacity from existing downtown electrical distribution infrastructure, rather than waiting for entirely new generation or transmission facilities to be developed.

According to the project team, the incremental nature of those capacity additions allowed the development to avoid regional transmission organization studies associated with certain larger power requests. The approach was particularly well suited to Legacy’s focus on facilities within the 20 MW-to-80 MW range, where available distribution capacity and strategic site selection can offer advantages over larger greenfield developments.

The building’s downtown location also created significant regulatory and construction challenges. The installation of lithium-ion UPS batteries above the 75-foot building-height threshold, for example, required extensive coordination with Minneapolis officials over code compliance and fire protection. The team ultimately incorporated multiple safeguards, including temperature and gas detection and specialized battery protection equipment, while working through an iterative approval process with the city’s fire marshal.

These experiences connected to a broader argument Mahmood had advanced about the industry’s relationship with the communities hosting its infrastructure.

One of the Fifth Compute’s greatest challenges, he suggested, may be social rather than purely technical. The industry has historically designed data centers to be largely invisible, allowing the public to use the services they enable without much awareness of the buildings, power systems, and resources behind them.

That invisibility becomes a liability when data center development begins affecting local electricity systems, water supplies, construction activity, land use, or neighborhood expectations.

Mahmood argued that developers should treat communities as partners in infrastructure planning rather than stakeholders to be engaged only after major project decisions have already been made. He emphasized that a government permit and sustained public acceptance are not the same thing, and that community trust requires ongoing transparency about a facility’s benefits and impacts.

“A community may grant us permission to build,” Mahmood said, “but we have to earn the privilege of remaining.”

One of his more provocative proposals was what he called the “nutritional internet”: a standardized disclosure framework that would make the characteristics and impacts of data center developments more understandable to the public.

Borrowing from the familiar nutritional labels on packaged foods, Mahmood envisioned disclosures describing a facility’s energy demand and sources, water consumption, potential grid impacts, opportunities for waste heat recovery, and contributions to employment, education, and local economic development. Such a framework, he argued, could give communities and policymakers more consistent information with which to evaluate proposed projects and monitor commitments over time.

The concept was not presented as a finished regulatory standard, but as a challenge to an industry that has become highly sophisticated at measuring infrastructure performance while remaining less effective at communicating its broader physical footprint.

For Mahmood, the Fifth Compute will require the industry to become better integrated with the systems surrounding its facilities, rather than treating power, water, community acceptance, and public policy as external concerns.

The Minneapolis redevelopment offered a narrower but tangible example of the value of existing infrastructure and local coordination. Its conversion ultimately also produced a commercial outcome: In January 2026, Cloud Capital and Arcapita announced the acquisition of the facility, describing a 21 MW property with plans for a further 10 MW expansion.

For Legacy Investing, the transaction demonstrated the potential investment value of repositioning older computing facilities for new AI workloads. For the broader industry, it underscored the commercial importance of sites capable of delivering power and computing capacity without requiring an entirely new development cycle.

From Orbital Data Centers to the Next Generation of Engineers

Mahmood’s keynote ultimately ranged well beyond terrestrial infrastructure.

He explored the possibility that computing could eventually become a critical component of humanity’s expansion into space, with orbital platforms, lunar systems, and interplanetary networks supporting autonomous operations, scientific research, and communication across increasingly distant environments.

The rationale was not simply to move conventional data centers into orbit. Mahmood identified several potential drivers, including extended access to solar energy in certain orbital configurations, processing data closer to space-based sensors and spacecraft, and providing intelligence capable of supporting activities where communication delays make constant human intervention impractical.

The engineering challenges, however, remain formidable. Heat rejection in space differs fundamentally from terrestrial cooling, radiation introduces new reliability requirements, launch costs constrain equipment design, and conventional maintenance assumptions collapse when technicians and replacement components cannot readily reach the installation.

Mahmood acknowledged those limitations and resisted treating orbital data centers as an inevitable substitute for facilities on Earth. Instead, he argued that emerging space activities could eventually create specialized computing requirements that justify developing new infrastructure beyond the planet.

Those possibilities also illustrated a larger point about the evolution of computing: Each new environment requires an underlying ecosystem of power, communications, operations, and reliability before increasingly sophisticated applications can be supported.

In that respect, the engineering challenges of a lunar computing installation and the conversion of an aging Minneapolis data center share a fundamental concern. Both require the integration of computing capabilities with physical infrastructure adapted to the demands of a particular operating environment.

Yet Mahmood also identified a resource that cannot be manufactured or deployed at the speed of computing hardware: experienced people.

Citing the Uptime Institute Global Data Center Survey 2025, Mahmood noted that 46% of operators reported difficulty finding qualified candidates for open positions, while 37% reported challenges retaining personnel. The figures reinforced his argument that the expansion of digital infrastructure depends not only on securing equipment and electrical capacity, but also on developing the people capable of building, managing, and maintaining increasingly sophisticated facilities.

During the keynote Q&A, an attendee raised a related concern: If AI begins displacing junior engineers and other early-career technical professionals, what happens to the traditional learning process through which experienced personnel transfer knowledge to the next generation?

Mahmood’s response emphasized the responsibility of industry veterans to collect, preserve, and share the practical knowledge developed throughout their careers. He also encouraged the industry to seek talent beyond conventional educational and professional backgrounds, including veterans, skilled tradespeople, community college students, and career changers.

That argument created perhaps the strongest connection between Mahmood’s vision and the Minneapolis case study.

Coe’s decades of engineering experience enabled him to recognize the potential in equipment and building systems inherited from earlier generations of data center design. At the same time, Gardner Builders entered the project without extensive prior data center experience, requiring its team to work closely with established engineering and construction specialists.

Coe described that unfamiliarity as a potential advantage, saying he had enjoyed working with first-time data center general contractors because they approached individual challenges without assuming that conventional solutions were necessarily the only solutions.

“They don’t make any assumptions, they study every issue,” he said.

The Minneapolis project was therefore not simply a demonstration of legacy infrastructure being adapted for AI. It was also an example of experienced engineering judgment being combined with fresh perspectives, intense collaboration, and a willingness to depart from conventional approaches when circumstances required it.

That combination may become increasingly valuable as the industry confronts the overlapping demands of accelerated construction, new computing architectures, evolving thermal requirements, and the need to preserve reliability across increasingly complex environments.

The Fifth Compute Still Depends on First Principles

The contrast between Mahmood’s keynote and Coe’s engineering case study ultimately revealed a shared understanding of the industry’s future.

The Fifth Compute may introduce systems capable of acting with increasing autonomy, processing information through novel architectures, and operating in environments far beyond today’s terrestrial computing infrastructure. Those developments could fundamentally alter the relationship between technology and society.

But the resulting infrastructure must still be engineered, constructed, commissioned, maintained, and operated within real-world constraints.

Not every older building can become a modern AI data center. The Minneapolis project benefited from unusually strong structural characteristics, existing electrical infrastructure, available utility capacity, and a project team prepared to manage an exceptionally complicated conversion. Its success does not establish a universally repeatable shortcut around the industry’s power and construction bottlenecks.

What it does demonstrate is the continuing relevance of engineering adaptability, experienced judgment, and operational discipline in an era increasingly focused on standardized AI factories, gigawatt-scale campuses, and ambitious deployment schedules.

Mahmood’s central message was similarly grounded. The promise of increasingly intelligent systems does not relieve the industry of responsibility for their consequences. Greater autonomy requires stronger accountability. More powerful computing demands more sophisticated infrastructure planning. And continued technological advancement places a premium on the human knowledge and institutional experience required to make new capabilities dependable.

For an industry whose facilities increasingly underpin essential economic and social functions, those responsibilities extend beyond the technical boundaries of the data center itself.

Toward the end of his keynote, Mahmood offered a warning that captured this broader obligation: “Just because we can build something doesn’t automatically mean that we should.”

The question, he suggested, is not simply how much computing capacity the industry can create, but what humanity ultimately accomplishes with it—and whether that progress justifies the resources and responsibilities involved.

The Minneapolis conversion provided a practical answer to one part of that challenge. Coe and his colleagues showed how the accumulated expertise of earlier computing generations could be applied to a radically different set of requirements, creating new capacity without abandoning the reliability principles that made the original facility valuable.

In the end, the intersection of traditional and AI data centers may be less about replacing the industry’s past than about determining which of its principles, practices, and accumulated knowledge will remain essential as the boundaries of computing continue to expand.

The Fifth Compute may eventually take data centers beyond Earth. For now, its future remains closely tied to engineers who know how to keep critical systems running while rebuilding the infrastructure around them.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Chevron preps for big 2027 exploration capex ramp

Chevron Corp., Houston, could increase its exploration capital budget by more than $500 million in 2027 as executives look to capitalize on strong commodity markets and build on an organizational shuffle that has centralized and accelerated decision-making. Speaking after Chevron reported its third-quarter results, vice-chairman Mark Nelson told analysts that

Read More »

New Cisco firewall zero-day being actively exploited

A high-severity flaw in the Remote Access SSL VPN service of Cisco Secure Firewall Adaptive Security Appliance (ASA) and Cisco Secure Firewall Threat Defense (FTD) is under active exploitation to crash vulnerable devices. The vulnerability, tracked as CVE-2026-76418 and rated 8.6 in severity, is due to logic errors when secondary

Read More »

Shell adds to Gulf of Mexico production with Silvertip Phase 3 startup

@import url(‘https://fonts.googleapis.com/css2?family=Inter:wght@100..900&display=swap’); .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; color: color-mix(in srgb, currentColor

Read More »

DOE’s Office of Critical Minerals and Energy Innovation Launches PROSPECT Implementation Prize To Expand America’s Mining and Critical Minerals Workforce

WASHINGTON—The U.S. Department of Energy’s (DOE) Office of Critical Minerals and Energy Innovation today launched the PROSPECT Implementation Prize, which will award up to $70 million to support universities in expanding the skilled workforce required to domestically produce, process, recover, and recycle critical minerals. This prize competition is part of DOE’s broader up to $100 million Providing Opportunities for Specialized Education in Critical Technologies (PROSPECT) initiative, which delivers on President Trump’s bold agenda to restore American energy dominance, secure long term economic growth, rebuild domestic supply chains, and reduce reliance on foreign adversaries for critical minerals. “DOE has laid the groundwork for growing America’s critical minerals workforce—and now we’re turning those plans into reality. Universities are taking the necessary steps to deliver measurable results, from expanding student support through scholarships to modernizing curricula with new training modules, certificates, and Super Intelligence,” said Assistant Secretary of Energy Audrey Robertson. “The Trump Administration is committed to freeing America from dependence on foreign sources of critical minerals that are essential to powering our economy, and creating good-paying, fulfilling jobs for Americans.” PROSPECT has established a near-term goal of doubling the number of graduates with mining, minerals, and associated supply chain credentials within two years. The PROSPECT Implementation Prize follows the recently completed PROSPECT Planning Prize, which awarded funding to universities for developing comprehensive workforce-expansion plans. The Implementation Prize focuses on putting workforce development programs into action and demonstrating measurable results. The U.S. faces a growing shortage of skilled mining and critical minerals professionals, with an estimated 6,000 new mining engineers needed over the next decade. Expanding America’s talent pipeline is essential to strengthening domestic supply chains and reducing reliance on foreign nations for critical materials. Mining and geological engineering careers offer strong earning potential, with a median annual wage of $106,220 in 2025.

Read More »

Energy Department Announces Over $230 Million Funding Opportunity to Strengthen America’s Grid Supply Chain and Lower Electricity Costs

WASHINGTON— The U.S. Department of Energy (DOE) today announced a $237 million funding opportunity to boost American manufacturing and strengthen supply chains for critical electric grid components. The investment is expected to deliver an estimated $125 million in annual utility savings and keep an estimated $50 million per year in the U.S. economy that would otherwise go to foreign suppliers. The investments will help facilitate the reliable flow of electricity for American families and businesses and position the U.S. as a global leader in foundational technologies, by incentivizing the refurbishment and reuse of critical equipment and encouraging the adoption of alternative materials and subcomponents that are sourced and made in America. These efforts will lower costs, strengthen grid reliability, and meet growing electricity demand.  “President Trump is bringing American industry and manufacturing back home, including the critical equipment and components needed to power our nation,” said U.S. Secretary of Energy Chris Wright. “The Energy Department is investing in American-made technologies and modernizing our grid to reduce reliance on foreign suppliers and deliver affordable, reliable, electricity.” This funding opportunity will support projects in two key areas:  Up to $50 million will be provided to projects that promote greater refurbishment and reuse of existing grid equipment and materials; Up to $187 million will be provided to projects that will increase the use of alternative materials and subcomponents sourced and made in the U.S, reducing dependence on imports.  “America should never have to rely on foreign suppliers to keep the lights on,” said Office of Electricity Assistant Secretary Katie Jereza. “We’re putting American ingenuity to work, developing next-generation grid technologies that strengthen our domestic supply chain, help lower costs, and make our grid more reliable. The power to secure our energy future should be in our own hands.” The Grid Supply Chain Alternatives to

Read More »

States must take a critical eye to gas plants proposed over clean energy

Listen to the article 5 min This audio is auto-generated. Please let us know if you have feedback. Will Scott is the North Carolina policy director of the Environmental Defense Fund. Hudson Kingston is the legal director at CURE, a nonprofit rural environmental and energy democracy organization in Minnesota. The data center boom has become a cash cow for investor-owned utilities across the country. Many utility companies are seeking approval for costly new gas plants and other fossil fuel infrastructure based on uncertain projections of future demand for data centers and other large customers. If those projections fall short, ratepayers are left with 30 years of payments for projects that are increasingly expensive to build and slow to develop. We can’t let phantom projections for new data centers leave regular ratepayers with the bill. Hudson Kingston Historically, state regulators have given utilities significant latitude to pursue new generation. Yet, as heating and cooling bills become painfully unaffordable for families and local businesses, utility regulators are increasingly skeptical of proposals that could leave them paying for decades of dirty and expensive fossil fuel infrastructure, when clean, renewable energy and batteries provide a reliable, homegrown and affordable alternative. Indeed, a recent study found that batteries are now cheaper than gas peaker plants, globally. Will Scott While customers are forced to pay increasingly higher energy bills, utility shareholders are guaranteed profits on centralized fossil energy projects. The bigger and more costly the construction, the more money energy corporations make. Once new energy infrastructure is approved by state regulators, utilities can start recovering the costs through customer rates even before the project is built and in use. Because utilities make profits off the infrastructure they build, and not the energy they sell, executives have a financial incentive to keep building to benefit shareholders.  To

Read More »

TotalEnergies farms out partial interest in block offshore Nigeria ahead of appraisal

TotalEnergies agreed to farm out a 40% participating interest in Block OPL257 offshore Nigeria to South Atlantic Petroleum Ltd. (SAPETRO). Upon completion of the deal, TotalEnergies will hold a 50% operated interest in the block with SAPETRO (40%) and Conoil (10%) as partners. TotalEnergies became operator of the block following a 2025 asset interest exchange with Conoil. OPL257 lies 150 km offshore Nigeria and covers an area of about 370 sq km. The block is adjacent to PPL261 where TotalEnergies (24%) and its partners, including SAPETRO, discovered Egina South oil field in 2005, which lies in 1,650 m of water and straddles both blocks. Drilling of an Egina South appraisal well is expected in the coming months on the OPL257 side. The field is expected to be developed as a tie-back to the Egina FPSO about 30 km away. The project has the potential to deliver up to 140 million bbl of oil reserves, according to SAPETRO. Consolidating the partnership “paves the way for a quick appraisal campaign and subsequent development of Egina South in the success case,” said Mike Sangster, senior vice-president Africa exploration and production at TotalEnergies. Completion of the farm-out agreement is subject to customary conditions, including regulatory approvals.

Read More »

Valero to acquire former LyondellBasell Houston oil refinery, restart 165,000 b/d by end-2027

Valero Energy Corp. plans to acquire a former LyondellBasell Industries NV Houston refinery and restart 165,000 b/d of light sweet crude oil processing by yearend 2027. Valero Refining-Texas LP has agreed to acquire the shuttered full-conversion refinery from LyondellBasell for $320.5 million. The transaction includes about 700 acres on the Houston Ship Channel adjacent to the Valero Houston Refinery, 13.5 million bbl of storage capacity, and logistics infrastructure including marine docks, rail-loading facilities, and truck racks. The acquisition will help address intermediate feedstock shortages across Valero’s US Gulf Coast refining system, reducing reliance on third-party purchases while creating opportunities to integrate refining and logistics operations, the company said in an Oct. 30 presentation. Incremental FCC and hydrocracker feed production would reduce external feedstock sourcing, while excess hydrotreating capacity could be used to upgrade intermediates from other Valero US Gulf Coast refineries, the company said. By yearend 2027, Valero expects to restart light sweet crude oil processing and said the site could support future investment in heavy sour crude processing, according to chairman, chief executive officer, and president Lane Riggs. The company did not provide financial details or a timetable for potential heavy sour crude processing projects. LyondellBasell announced plans in April 2022 to cease operation of subsidiary Houston Refining LP’s 268,000-b/d refinery as part of its exit from the crude oil refining business. Following delays, the refinery was shuttered in March 2025. Over the years, LyondellBasell evaluated options for the site, including a potential plan to transition the refinery into a hydrogen production site. Ultimately, the company said, it determined selling the asset “offered the most compelling opportunity” to advance the company’s priorities. Closing of the transaction is expected by yearend, subject to customary closing conditions.

Read More »

Celebrate National Bioenergy Day: Explore the Possibilities of Biomass

How can biomass power new possibilities for energy innovation and the products we use every day?  Today is National Bioenergy Day, an annual opportunity to recognize the role biomass and innovative technologies can play in strengthening the U.S. bioeconomy. Bioenergy is a form of energy produced from alternative feedstocks called biomass. These resources, which include agricultural and forestry residues, purpose-grown crops, algae, and waste materials, can be converted into chemicals, fertilizers, alternative fuels, and other materials to support farmers, ranchers, and consumers while also lowering prices through increased supply. The United States has an abundant supply of biomass. The U.S. Department of Energy’s (DOE) Alternative Fuels and Feedstocks Office (AFFO) Billion-Ton Report establishes America’s potential to produce more than 1 billion tons of biomass annually, highlighting the scale of resources available to support a growing bioeconomy and energy security and dominance.  In celebration of National Bioenergy Day, AFFO is highlighting recent investments, research accomplishments, and resources that demonstrate the possibilities of biomass and the innovative technologies that transform these resources into valuable products. Exploring Bioenergy in Action What does that transformation look like? Explore AFFO resources that cover the basics of bioenergy and offer a closer look at how researchers are advancing technologies across the bioenergy supply chain.  Watch the Bioenergy 101 video to learn how biomass is broken down and refined through various methods, including combustion, gasification, and fermentation, to advance technology development and innovation across the entire biomass-to-bioenergy supply chain.  Take a look inside the Idaho National Laboratory’s Biomass Feedstock National User Facility, which offers technology and expertise to help the U.S. bioenergy industry overcome challenges associated with the scale-up and integration of biomass preprocessing facilities. Investing in Emerging Chemical Technologies  These efforts are part of a broader push to move promising technologies from research to commercial application. AFFO recently announced the Accelerating Scale-up

Read More »

7×24 Fall 2026: AI Frontier Futurist Meets Data Center OG

A 1988 Data Center Becomes a 20 MW AI Asset The second presentation, Converting a 1990 Enterprise Data Center to 20MW AI Workloads, featured Coe alongside Ari Chernikoff, vice president of development at Legacy Investing, and Dan Amundson, project manager at Gardner Builders. The project centered on 1001 Third Avenue South in downtown Minneapolis, a financial-services computing facility originally constructed in 1988. The building had supported earlier generations of enterprise computing before portions were converted to commercial office space and smaller colocation operations. Although its remaining operating data center load had declined to approximately 500 kilowatts by the time the AI redevelopment began, the property retained substantial infrastructure inherited from its original mission-critical design. Tall ceilings, robust floor loading, raised access floors, existing medium-voltage substations, and established utility connections made the building an unusually strong candidate for conversion. These characteristics, Chernikoff explained, can determine whether an existing building offers a practical path to high-density computing or proves economically unsuitable for redevelopment. Legacy Investing had identified a market opportunity in what Chernikoff called the industry’s “missing middle”: facilities generally ranging from 20 MW to 80 MW, rather than the 100 MW-plus campuses increasingly associated with hyperscale and frontier AI development. The company viewed existing buildings with available power and favorable infrastructure characteristics as potential shortcuts to deployment, particularly where demand for AI inference and other latency-sensitive workloads favored proximity to major urban markets. Following an AI tenant commitment in summer 2024, the development team faced an aggressive initial requirement: Deliver the first 5 MW of capacity by the end of that year. The first phase was ready for service approximately four months after Gardner’s involvement became formalized, followed by another 5 MW in 2025 and an expansion program ultimately reaching 20 MW over roughly 20 months. All of this had to

Read More »

Gartner warns $3.5T in AI infrastructure spending could be at risk by 2030

Musk predicted that more than 200 neocloud companies could face significant financial distress, predicting that only a small number would survive the coming shakeout. He also said SpaceX would not acquire any of the companies, describing such purchases as “pointless.” The chickens are already coming home to roost on the neoclouds. CoreWeave, Nebius, Applied Digital and TeraWulf have reported quarterly losses over the past year, while IREN has failed to turn a profit in its past three quarters. Shares of CoreWeave, Nebius and IREN have fallen more than 30% during October, according to Reuters. Building AI data centers requires substantial upfront investment in GPUs, networking equipment, power systems, cooling infrastructure and facilities. Operators must then generate enough revenue from leasing computing capacity to cover operating expenses, interest payments and equipment replacement.

Read More »

The 50-Gigawatt Test: SemiAnalysis Sees a Historic Data Center Surge in 2027

The global data center industry is approaching a potentially historic test of its ability to turn artificial intelligence investment into operational infrastructure. In a provocative new forecast, semiconductor and AI infrastructure research firm SemiAnalysis predicts that approximately 51.2 gigawatts of net data center IT capacity will be added globally, excluding China, during 2027. That would represent more than double the 25 GW the firm expects to be added in 2026. Published October 19, the report, Datacenters 2027: The Year of Acceleration, +50GW in a Single Year, makes a forceful argument that much of this unprecedented expansion is already visible in the industry’s construction pipeline. Authored by Jeremie Eliahou Ontiveros, Reyk Knuhtsen and Dylan Patel, the analysis draws on SemiAnalysis’ proprietary tracking of construction starts, individual buildings, hyperscale leasing commitments, equipment procurement and project financing. Its researchers identify more than 60 GW of data center capacity under construction. Among the 40 largest campuses they examined, more than 24 GW is reportedly in advanced stages of development, with much of that capacity expected to be delivered in 2027. The forecast is not entirely composed of projects already under construction, however. SemiAnalysis’ capacity chart includes approximately 11.9 GW of 2027 additions associated with projects still classified as planned. The remainder is associated with facilities already operating or under construction, according to the model’s building-status categories. SemiAnalysis argues that the volume and maturity of projects already underway make a dramatic acceleration increasingly likely, despite well-documented constraints involving electricity, construction labor, equipment and capital. But the prediction has also become the subject of a revealing industry debate, with competing forecasts and new corporate disclosures raising questions about how much infrastructure can actually be delivered on schedule. The disagreement is no longer principally about whether AI infrastructure demand is real. It is about whether the industrial

Read More »

HPE’s Quantum Computing Bet: A Multi-Vendor Path to the Data Center

QuEra Deal Targets On-Premises Quantum Integration Under the expanded collaboration, HPE and QuEra intend to develop integrated testbeds, software interoperability, hybrid algorithms and performance benchmarks to support future quantum deployments alongside HPE Cray supercomputing infrastructure. The work is intended to address the practical requirements of coordinating quantum processors with the classical computing systems that prepare workloads, process results and support quantum error correction. QuEra Chief Commercial Officer Yuval Boger, who previously discussed the development of hybrid quantum-classical infrastructure on the DCF Show, emphasized that integrating quantum hardware into an HPC environment presents different engineering challenges than providing access through the cloud. Boger said, “HPE’s deep experience in supercomputing gives organizations the benefit of working with a partner who can solve that problem at the scale they need.” The collaboration envisions deploying future fault-tolerant quantum hardware at customer facilities rather than requiring organizations to rely exclusively on cloud-based quantum computing services. That option could appeal to national laboratories, defense organizations, pharmaceutical researchers and other institutions managing classified information, proprietary intellectual property or data subject to sovereignty requirements. QuEra’s neutral-atom architecture uses individual atoms as qubits, manipulating them with lasers and electromagnetic controls. Unlike superconducting quantum processors, which generally require dilution refrigerators operating at temperatures measured in millikelvin, neutral-atom systems can operate without extreme cryogenic refrigeration. They still require specialized laser systems, vacuum equipment, precision optics and environmental controls, presenting facility requirements substantially different from those of conventional servers. On-premises quantum-HPC integration is already being tested. In Japan, the National Institute of Advanced Industrial Science and Technology (AIST) operates QuEra’s 260-physical-qubit Gemini neutral-atom computer as part of its ABCI-Q research platform, which also incorporates an NVIDIA H100-based AI supercomputer. An October 26 case study published by QuEra describes Gemini operating in a separate building approximately 350 meters from the main GPU installation,

Read More »

At 7×24 Exchange, AI Data Center Growth Confronts New Realities of Power, Grid Reliability and Community Trust

DC BLOX: Community Engagement Must Go Beyond Public Relations The afternoon program shifted attention from electrical infrastructure to the growing challenges surrounding data center development and community acceptance. In a discussion moderated by Juli Ierulli, strategic account manager at Environmental Air Systems and vice president of 7×24 Exchange International, Michael Clark, senior vice president of data center construction at DC BLOX, described how the company has revised its approach to engaging communities as it expands into new markets. Clark acknowledged that DC BLOX had encountered significant opposition after entering markets where it lacked the established relationships that had supported earlier developments across the Southeast. “We made multiple stumbles in some of those new markets,” he said, describing how the company sometimes found itself responding to negative publicity rather than presenting a clear explanation of its plans and commitments. The experience led DC BLOX to develop a more systematic approach to community engagement, emphasizing early communication, site-specific websites, accessible explanations of resource consumption and written commitments that residents and officials can evaluate. Clark also pointed to what he called the industry’s “NDA hangover,” reflecting years of development activity conducted under confidentiality agreements that frequently left neighboring communities unaware of what was being planned. But perhaps the most revealing moment came when Clark recounted a conversation with residents near a DC BLOX development in Rockdale County, Georgia. After the company outlined the countywide economic and community benefits expected from the project, one neighbor challenged the distribution of those benefits. “So the rest of the county gets the benefit and we have to pay all the costs,” the resident observed, according to Clark. The question captured a fundamental tension in the industry’s community engagement efforts: tax revenues and economic development benefits may extend across a county, while nearby residents experience the immediate effects

Read More »

NVIDIA’s DSX POD Pushes AI Factory Construction Toward the Assembly Line

Crusoe Brings an Established Modular Model to DSX POD For Crusoe, NVIDIA’s announcement builds on a modular computing strategy already in operation. In its October 21 announcement, Crusoe confirmed that its Spark modular AI data center platform will support DSX POD, extending a manufacturing and deployment approach the company says it has pursued since 2020. Crusoe has expanded its manufacturing capabilities through the acquisition of electrical equipment specialist Easter-Owens Electric and the development of its 352,000-square-foot Crusoe Spark Factory in Brighton, Colorado. The company also introduced Crusoe Spark Liquid, a sixth-generation modular system engineered for ultra-high-density infrastructure, including NVIDIA Vera Rubin NVL72. Next-generation liquid-cooled units are planned for 2027. Crusoe’s vertically integrated model connects infrastructure design and manufacturing with deployment and cloud operations through Crusoe Cloud. The company says it can deliver productive AI capacity in as little as three months, although that timeline is distinct from NVIDIA’s narrower 14-day prepared-site deployment claim. “Modular isn’t a new strategy or pivot for us. It’s been in our DNA since our founding,” said Bryan Schramm, Crusoe’s head of Spark. Crusoe’s involvement demonstrates that the manufacturing model predates DSX POD. NVIDIA is not inventing modular data center infrastructure; it is attempting to establish a common architecture around capabilities that suppliers such as Crusoe have already spent years developing. That distinction matters as the industry evaluates whether standardized AI factory designs can deliver manufacturing efficiencies at a scale beyond individual suppliers’ existing operations. Vertiv and Polar Put the Deployment Model to Work in Norway The European dimension of NVIDIA’s announcement is reflected in a deployment involving Vertiv and Polar Data Centers at Herøya, Norway. According to Vertiv’s October 21 announcement, Polar is applying a factory-built infrastructure approach to the initial 41 MW phase of a multiphase AI data center campus designed to scale to

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »