Land & Expand: North America’s Data Center Pipeline Expands Under Pressure

Land & Expand is Data Center Frontier’s periodic look at the latest data center development news, including new sites, land acquisitions and campus expansions across North America. This latest installment finds the development pipeline continuing to expand, even as the requirements for bringing large-scale projects online grow more complicated. Developers are securing land, planning new […]

Land & Expand is Data Center Frontier’s periodic look at the latest data center development news, including new sites, land acquisitions and campus expansions across North America.

This latest installment finds the development pipeline continuing to expand, even as the requirements for bringing large-scale projects online grow more complicated. Developers are securing land, planning new power infrastructure and advancing campuses measured in hundreds of megawatts or more. At the same time, local governments and residents are demanding greater clarity on electricity costs, water consumption, noise, tax incentives and the long-term effects of industrial-scale computing facilities.

A succession of development disclosures and project milestones through September and early October 2026 illustrates both the geographical reach of North America’s expanding data center pipeline and the growing difficulty of measuring how much proposed capacity will ultimately be delivered.

The projects range from preliminary discussions and newly secured development sites to campuses already under construction. Some are advancing through formal permitting and power studies; others remain contingent on customers, financing or local approvals. Together, they reveal an industry still expanding aggressively, but operating under increasingly complex development conditions.

Fluidstack: Cameron County, Texas — Up to 1.5 GW

One of the largest newly disclosed projects is Fluidstack’s AI data center development in Cameron County in the Rio Grande Valley. The project surfaced publicly September 10 when Cameron County announced that it had issued Fluidstack a worksite permit for property near Harlingen. The permit authorizes preliminary site work, including grading, utilities and related infrastructure, rather than construction of the data center buildings themselves.

Fluidstack subsequently disclosed considerably more detail on September 21, saying construction had begun on a $4 billion first phase capable of supporting as much as 1.5 GW.

Fluidstack expects the project to generate more than 2,500 construction jobs and several hundred permanent positions.  The company has placed unusual emphasis on the project’s local infrastructure impact. It says it requested no local property-tax abatements and intends to pay for the energy, water and infrastructure necessary to serve the campus. Cooling will use a recirculating closed-loop system.

At up to 1.5 GW in its announced first phase, Cameron County represents a major addition to the Texas AI development pipeline, reflecting the increasingly industrial scale of projects designed to support advanced computing.

Microsoft ATL50: Union City, Georgia

A new filing for Microsoft’s ATL50 campus entered Georgia’s Development of Regional Impact review process on September 15. Microsoft filed plans for ATL50, a new data center campus at 5235 Stonewall Tell Road in Union City, southwest of Atlanta. Plans call for two three-story data center buildings totaling approximately 910,000 square feet on 88 acres. The filing projects completion in 2032.

Microsoft already has a substantial Georgia footprint, with development activity in Fairburn, Douglasville, Palmetto, Rome, East Point and other communities. ATL50 represents another proposed campus in the greater Atlanta market rather than entry into a new region. No electrical capacity has been disclosed.

Project Gravel: Pima County, Arizona

Another proposed development emerged through public-records reporting rather than a corporate announcement. Documents obtained in September disclosed Project Gravel, an eight-building data center campus being evaluated on approximately 160 acres of vacant land in unincorporated Pima County west of Sahuarita, Arizona.

Plans show eight buildings of roughly 203,000 square feet each, producing a potential campus of approximately 1.6 million square feet, along with a dedicated electrical substation, roads and parking infrastructure. Project documents contemplate full buildout by 2029, contingent on the development advancing through the necessary approvals.

County staff had reportedly been evaluating the proposal for months before details became public. Neither the developer nor a prospective tenant has been publicly identified, and the planned electrical load remains undisclosed. The disclosure has already generated local concern: Residents gathered September 29 to discuss the project’s potential effects on water, energy use and the surrounding environment. Sahuarita officials subsequently clarified that the proposed site lies outside town boundaries, under Pima County jurisdiction.

Project Gravel also illustrates the difficulty in determining the true size of the U.S. development pipeline. Large sites can remain in engineering, environmental and land-use review for months before appearing in conventional industry announcements.

Gray Oak Power: Undisclosed South Texas Campus

Another visible development appeared September 25, although considerably less is known about it. Gray Oak Power disclosed that a South Texas data center campus had advanced through ERCOT’s Studied Load Batch Zero process. The company has not disclosed the community, tenant or ultimate campus capacity.

Advancement through ERCOT’s Studied Load Batch Zero process confirms that another large-load development is progressing through the Texas interconnection review system, although it does not represent final grid-connection approval. Gray Oak’s proposed strategy calls for the campus to begin operating with dedicated onsite generation, followed by a utility grid connection and the eventual ability to supply electricity back to the grid. The company targets initial power in 2028 and utility grid service in 2029. Until the location, electrical load and customer are disclosed, the project remains an early-stage development.

Lambda: Mayes County, Oklahoma

On September 27, AI cloud provider Lambda announced an entirely new data center at the MidAmerica Industrial Park in Mayes County, Oklahoma, near Chouteau.

Lambda has not disclosed either the capital cost or megawatt capacity of the facility, but expects development to support as many as 1,000 construction jobs and 100 permanent positions. The company estimates the project could produce approximately $500 million in taxes over its first decade at current rates.

Unlike many data center announcements of several years ago, Lambda’s disclosure immediately addressed electricity costs and water consumption. The company says it will pay the full cost of the energy and infrastructure required to serve the facility, consistent with Oklahoma’s Data Center Customer Ratepayer Protection Act. Lambda also plans to use closed-loop cooling to reduce water consumption and is examining ways to shift or reduce certain computing workloads during periods of peak grid demand.

Google/Crusoe: Armstrong County, Texas

One of September’s most consequential disclosures concerned a project already well into construction. Google had announced plans for an Armstrong County data center in November 2025, but on September 28, Crusoe identified itself as the developer of the Google AI campus outside Amarillo. Crusoe said construction began in June 2025 and that more than 5,500 skilled workers were now on site daily.

The campus has direct connections to Serena’s adjacent 265.5 MW Goodnight 1 wind farm and the 265.5 MW Goodnight 2 project now under construction. Crusoe says excess wind generation can flow to the grid when production exceeds campus requirements. Neither Google nor Crusoe has disclosed the full electrical capacity of the data center campus. Those generation figures should not be confused with the data center’s electrical load, which has not been publicly disclosed.

The disclosure illustrates how construction can advance well beyond the initial project announcement before the full development structure becomes public. It also reflects the growing importance of colocating AI infrastructure with large-scale energy resources.

Clean Cloud Energy: Mahomet, Illinois

Illinois offered a different illustration of the pressures shaping data center development. On September 28, the Village of Mahomet disclosed that Clean Cloud Energy had approached the community about a potential data center campus on rural property west of Champaign. Discussions were preliminary but had advanced to include draft language for a possible development agreement. No formal project capacity or investment amount had been announced.

Those discussions came to an abrupt end. On October 5, the village announced that it would no longer pursue the development opportunity with Clean Cloud Energy, citing extensive public opposition. Residents had raised concerns about proximity to homes, noise, lighting, infrastructure requirements and potential impacts on the Mahomet Aquifer. Village President Jason Tompkins said community feedback had played a significant role in the decision not to proceed.
Mahomet provides a counterpoint to the larger projects advancing elsewhere.

The village’s decision ended its negotiations with the developer, although it does not establish that Clean Cloud Energy has abandoned broader development ambitions in the region. It also demonstrates that community opposition is no longer simply a public-relations challenge. In some jurisdictions, it can decisively alter the development process before formal permitting begins.

Zone Frontier: Potter County, Texas — 200 MW to 500+ MW

Zone Frontier announced a 30-year ground lease covering approximately 4,077 acres in Potter County, Texas, including land that could support as much as 800 acres of data center development.

The initial concept is approximately 200 MW, with the potential to expand beyond 500 MW. At least 1,800 acres could be used for solar generation, battery storage and associated energy infrastructure. The company has also secured a long-term water agreement. The property also surrounds Southwestern Public Service Company’s existing 345 kV Potter County substation, which Zone Frontier identifies as a potential route to grid interconnection alongside its proposed onsite generation resources.

Zone Frontier has not yet secured a tenant, and construction remains contingent on customer commitments, permitting, power arrangements and financing. The lease establishes substantial site control, not a committed construction schedule. Nevertheless, securing more than 4,000 acres with an envisioned development path beyond 500 MW places Potter County firmly within the emerging hyperscale development pipeline.

Beyond the Initial Disclosures: North America’s Development Pipeline Widens

The latest development news extends well beyond the projects disclosed during September. Across North America, hyperscalers and infrastructure developers are advancing additional campuses, expanding power commitments and exploring new regional markets. The activity ranges from redevelopment of former industrial properties to sovereign AI infrastructure and entirely new greenfield projects.

AWS Details 36-Building Plan at Pennsylvania’s Homer City

In Pennsylvania, additional details have emerged about Amazon Web Services’ proposed campus at the former Homer City coal-generating station. An October 6 report described AWS’s preliminary land-development plan for 36 data center buildings spread across approximately 1,100 acres in Indiana County, divided among six development areas.

The proposed buildings would each encompass approximately 225,000 square feet, with construction proceeding in four phases. Under the submitted schedule, work could begin in December 2026, with the final phase starting in 2032 and overall completion targeted for 2036. The proposal also includes electrical substations, supporting infrastructure and redundant generation.

As DCF previously reported, Homer City Redevelopment is building a multigigawatt natural-gas generating complex at the former coal plant site, with AWS positioned as a prospective principal power customer. The power development is already under construction, while AWS’s data center plans remain subject to the applicable land-use and construction approvals.

The newly detailed building program underscores the scale of the transformation: A retired coal-generation complex could become a long-term, integrated power and computing campus, provided the development and generation timelines converge.

Bell Expands Saskatchewan AI Ambitions Toward 1.2 GW

Canada’s emerging AI infrastructure market produced another major development in September when Bell Canada and the Government of Saskatchewan announced a nonbinding agreement to explore up to 900 MW of additional capacity for Bell AI Fabric.

The proposed expansion would build on Bell’s previously announced 300 MW campus near Regina, creating a potential 1.2 GW AI infrastructure hub. The company says total investment associated with a full buildout, including data centers, tenant computing equipment and related power generation, could exceed C$50 billion.

The additional capacity is expected to depend on partner-developed natural-gas generation, while Bell says its proposed facilities will use closed-loop cooling without municipal water requirements. Expansion timing will depend on securing customer commitments.

The significance extends beyond the capacity figure. Bell is positioning Saskatchewan as a center of Canadian-controlled AI infrastructure, reflecting the growing importance of data sovereignty alongside power availability and computing scale. However, the additional 900 MW remains a development objective under a nonbinding agreement, not committed operating capacity.

TeraWulf Accelerates Kentucky’s Muskie Campus Toward 1 GW

In eastern Kentucky, TeraWulf announced October 5 that it had expanded its contracted power arrangements with Kentucky Power for the Muskie Data Campus from 500 MW to 1 GW.

The amended agreements also accelerate the proposed second 500 MW phase from 2030 to 2029. The first phase remains targeted to begin ramping in 2028, while the revised second-phase schedule depends on Kentucky Public Service Commission approval and the utility’s construction timetable.

Unlike an early-stage land acquisition, Muskie’s latest development milestone concerns the amount and timing of contracted electrical service. That distinction matters as developers increasingly compete to establish credible schedules for delivering large blocks of power to AI infrastructure customers.

The amendment does not mean the full gigawatt is available today. It does, however, mark a substantive step in transforming an announced campus into a phased development with defined utility-service arrangements.

Mexico: Cuasar Targets 300 MW in Durango

Mexico’s data center development pipeline is also extending beyond its established concentration in Querétaro.

Cuasar Capital, associated with Spain’s EOSOL group, and infrastructure developer KA URBE IT have announced a partnership to market a proposed AI-oriented data center campus in Durango. The principal facility, DC Norte Uno, is designed for 300 MW of total capacity, including approximately 250 MW of IT load, on a 20-hectare site.

A second proposed facility, DC Norte Dos, would provide approximately 7.74 MW for edge computing and industrial applications. The developers are positioning the campus around high-density AI workloads and connectivity routes linking Durango with established Mexican and cross-border digital infrastructure markets.

The project remains at an early development and commercialization stage. Nevertheless, its proposed scale illustrates how AI infrastructure demand is encouraging developers to explore Mexican markets beyond the country’s existing hyperscale clusters.

Ontario: A 400 MW Proposal Confronts Local Planning Questions

In Sault Ste. Marie, Ontario, Algoma Steel and Red Jar Energy Partners have discussed a potential 400 MW AI data center development, illustrating another approach to converting established industrial locations into digital infrastructure.

The parties have sought an early position in Ontario’s Independent Electricity System Operator connection process to evaluate the feasibility of the project. An October 2029 operating date has been discussed, but the companies have not announced a binding construction commitment.

Municipal planning presents another obstacle. Sault Ste. Marie’s council moved toward preparing an interim-control bylaw that could pause data center development while the city establishes a local regulatory framework.

The proposal therefore remains preliminary. Its significance lies partly in the opportunity to reuse industrial infrastructure, and partly in the challenge of reconciling large new electrical loads with provincial grid planning and municipal approval requirements.

Google Explores New Mexico’s Lea County

Google is considering a new data center development in Lea County, New Mexico, potentially establishing its first self-built data center in the state.

In a September 14 announcement, the company acknowledged that discussions were underway but declined to provide a precise site, proposed electrical capacity or development schedule. Instead, Google emphasized early public engagement, responsible water management and commitments to cover the energy and infrastructure costs required by the project.

Lea County’s location along the Texas border places the potential development within a broader Southwest corridor attracting increasingly large investments in computing and energy infrastructure.

At this stage, Google’s interest represents market exploration rather than a committed construction project. It is nonetheless another indication that hyperscale site selection is moving into regions beyond the industry’s traditional development centers.

Additional Projects to Watch: Filings, Expansions and Capacity Milestones

A further group of developments illustrates how much activity is moving through permitting, construction and utility planning outside the industry’s largest headline announcements.

Project Longhorn, Bastrop County, Texas: An October filing identifies a proposed $366 million first data center building in Cedar Creek, encompassing approximately 498,000 square feet. The broader development has been linked in reporting to a proposed gas-fired power complex capable of supporting approximately 490 MW of IT load. Anthropic has been identified as a possible tenant in related reporting, but its participation has not been confirmed. The filing supplies a more concrete development marker than the previously reported tenant discussions.

Microsoft, Prince William County, Virginia: Microsoft has filed plans for the MNZ07 Wellington Data Center, consisting of two single-story buildings and an onsite substation on approximately 123 acres near Gainesville. The proposal includes federal environmental review because of potential impacts on wetlands and streams. It represents additional hyperscale development in Northern Virginia even as local governments tighten rules governing where new campuses can be built.

Skybox and Prologis, Hutto, Texas: The partners have filed plans for Skybox Hutto 4, an approximately 846,300-square-foot building with a reported development cost of $550 million. The fourth facility would become the largest building proposed at their PowerCampus development, which is targeting 600 MW of IT capacity across the broader site.

Applied Digital, Ellendale, North Dakota: Not every milestone concerns proposed capacity. Applied Digital announced that another 75 MW of critical IT load had reached ready-for-service status at its CoreWeave-leased Polaris Forge 1 campus. The milestone brings completed campus capacity to 250 MW, toward a planned 400 MW full buildout. This is a more tangible measure of deployment progress than an early-stage site announcement.

ThisWay Global, Bryan, Texas: A proposed 73 MW Research and AI Compute Center at Texas A&M-RELLIS would provide computing infrastructure for research, government and industry users. Planned for phased development on approximately 25 acres, the project would use direct-to-chip liquid cooling and remains subject to the necessary approvals.

Taken together, these additional developments reinforce the central distinction emerging across North America. Some developers are acquiring land or introducing proposals; others are securing power agreements, advancing environmental reviews or completing facilities capable of serving customers. The pipeline continues to grow, but the distance between an announced megawatt and an operational one remains a defining measure of development progress.

The Pipeline Grows Under Closer Scrutiny

These development disclosures arrive amid intensifying scrutiny of the industry’s expansion. On July 18, opponents organized 142 demonstrations across 42 states in a coordinated national protest of data center development. A Reuters/Ipsos survey published in June found that only about one-third of Americans supported the rapid pace of construction, while just 14% said they would welcome a data center in their own community.

The pressure continued into September. On September 15, Loudoun County, Virginia, supervisors voted to consider a resolution that could pause final action on certain data center and electrical substation applications requiring legislative approval for up to 12 months. The resolution is scheduled for consideration October 20. In Chicago, Mayor Brandon Johnson introduced a proposal for a one-year moratorium on permits and approvals for new or expanded data centers while city officials study their power, water and community impacts. Neither action represented an enacted moratorium as of October 12.

The pressure continued into September.  Loudoun County, Virginia voted September 15 to develop a process that could pause final action on certain new data center and substation applications for as long as 12 months while the county rewrites its policies. Chicago Mayor Brandon Johnson has proposed a 12-month moratorium on new data centers within the city while officials study their power, water and community impacts.

Yet the flow of development announcements continues. What has changed is the level of scrutiny that accompanies them. New project disclosures increasingly address ratepayer protection, closed-loop cooling, onsite generation, water availability and infrastructure financing alongside investment, construction schedules and job creation. Those commitments reflect an industry adjusting to the realities of developing power-intensive infrastructure at unprecedented scale.

The emerging distinction is between securing a development opportunity and demonstrating that it can be delivered. Land, electrical capacity, financing, permitting and community acceptance are increasingly interdependent requirements. As the latest projects illustrate, the North American data center pipeline remains substantial, but the path from proposed campus to operating infrastructure is becoming more demanding.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

F5 scrambles to fix more critical BIG-IP security flaws

CVE-2026-121805: When an iRule that processes client traffic using the PEM:subscriber command is configured on a virtual server, undisclosed requests can cause the Traffic Management Microkernel (TMM) to terminate and may lead to remote code execution (RCE); CVE-2026-120292: When an HTTP profile and an iRule using the MR:message route command

Read More »

The grid’s hidden bottleneck: engineering capacity

The power system is undergoing an unprecedented transformation. Many of the reasons driving that change are well recognized and frequently discussed. Electricity demand from data centers, manufacturing and the electrification of transportation and building heating and cooling is surging. In fact, earlier this year the North American Electric Reliability Corporation (NERC) warned that grid reliability risks were increasing because demand was outpacing the new generation and transmission needed to serve it. Another challenge: the grid is old. The most recent American Society of Civil Engineers’ Infrastructure Report Card gave the nation’s energy system a D+, in part because of the age of the grid. Utilities have responded to an aging grid and skyrocketing electricity demand by making significant investments. The Edison Electric Institute (EEI) recently forecast that investor-owned utilities would spend $1.4 trillion through 2030 to meet customer demand for power. However, increased capital investment does not automatically translate into increased project execution. While funding, equipment availability and construction resources are critical, the engineering processes required to move projects from planning into construction represent another significant constraint. Utilities must not only invest in additional infrastructure but also rethink how that infrastructure is engineered and delivered. The engineering capacity squeeze Utilities are under pressure to move more projects through engineering and into construction, but experienced engineering resources are increasingly difficult to secure. While utilities can expand internal teams or engage additional engineering, procurement and construction (EPC) partners, scaling traditional engineering processes often introduces additional challenges. Different design tools, inconsistent engineering standards and repetitive manual work can limit productivity and increase coordination demands. That leaves utilities with a pressing question: how can they execute significantly more capital projects without a proportional increase in engineering resources? The substation engineering bottleneck Substation engineering provides a compelling example. While utilities have extensive engineering standards and established design practices, many

Read More »

Energy Secretary Keeps Critical Generation Available in Mid-Atlantic

WASHINGTON—U.S. Secretary of Energy Chris Wright today issued an emergency order to address critical grid reliability issues facing the mid-Atlantic region of the United States. The order directs PJM Interconnection L.L.C. (PJM), in coordination with Constellation Energy Corporation (Constellation Energy), to ensure Units 3 and 4 of the Eddystone Generating Station in Pennsylvania remain available to operate and to employ economic dispatch to minimize costs for the American people. The units were originally slated to shut down on May 31, 2025.   “The energy sources that perform when you need them most are the most valuable,” said U.S. Secretary of Energy Chris Wright. “President Trump and the Energy Department are committed to keeping critical generation available when demand is highest, reducing the risk of blackouts and ensuring Americans have affordable, reliable, and secure power—regardless of whether the wind is blowing or the sun is shining.”  Secretary Wright first ordered that the two Eddystone Generating Station units remain online past their planned retirement date in a May 30, 2025 emergency order. Subsequent orders were issued later in 2025 and 2026. Keeping these units operational has strengthened energy security in the PJM region, ensuring reliable electricity for American families and businesses. This order is in effect beginning on November 21, 2026, through February 18, 2027. 

Read More »

ExxonMobil takes FID on Angola Block 15 extension project

The Block 15 Lifespan Extension Project, about 145 km off Angola’s northern coast, will utilize existing infrastructure to develop additional resources throughout the Kizomba Hub area. The investment decision completes project FIDs following approval of Kizomba C redevelopment in 2025. ANPG also noted a hydrocarbon discovery in the block at the Tchihumba West-01ST1 exploration well, about 350 km northwest of Luanda. The discovery is the 21st in the block and the second this year. The well, drilled by the Valaris DS-9 in about 1,400 m of water, encountered 65.4 m of sandstone reservoir with hydrocarbon presence and good petrophysical properties. ExxonMobil is operator at Block 15 (36%) with partners Azule Energy Exploration (ANG) Ltd. (24%), Azule Energy ANG BV (18%), Equinor Angola (12%), and Sonongol E&P (10%).

Read More »

Market reforms bolster grid, may lower costs this winter: FERC

Listen to the article 4 min This audio is auto-generated. Please let us know if you have feedback. Electric market reforms in the West and Northeast may bolster grid reliability and, in some cases, lower costs this winter, according to the Federal Energy Regulatory Commission’s annual winter market and reliability report, released Thursday. Expanded markets help offset drought impacts In the West, the California Independent System Operator launched the Extended Day Ahead Market and the Southwest Power Pool expanded into the Western Interconnection earlier this year. “EDAM and SPP’s expansion should provide ratepayers in much of the West with production cost savings and improved reliability in winter 2026-2027, particularly during cold weather events,” FERC staff said in the report. This winter, the markets’ improved coordination of generation and reduced need for reserve power supplies will help offset lower power output from the Glen Canyon and Hoover dams due to historically low water levels in the Colorado River basin, staff said. “On a day-to-day basis, these conditions can create congestion and affect system operators’ ability to respond to voltage support challenges, event response mitigation needs, or any additional grid stressors,” staff said in the report. About 45% of the continental United States and 95% of the Intermountain West region is in a drought, according to the report. Hydro, oil pose challenges for Northeast In the Northeast, ISO New England lowered its capacity performance pay rate, which should lower electricity prices during emergency conditions or capacity performance events this winter, staff said. Also, the New York Independent System Operator changed its installed capacity market rules to reflect uncertainty about how much power Hydro–Québec will deliver over the 1,250-MW Champlain Hudson Power Express transmission line in the winter, they noted. The U.S. subsidiary of the Canadian utility Hydro-Québec — the primary reservation holder — has an obligation

Read More »

Dangote awards contracts advancing Lekki refining complex expansion

Dangote Group’s Dangote Petroleum Refinery and Petrochemicals FZE (DPRP) has awarded separate contracts to Kirloskar Group of India’s Kirloskar Brothers Ltd. (KBL) and Kirloskar Ebara Pumps Ltd. (KEPL)—a KBL joint venture with Ebara Corp. of Japan—for delivery of engineering services and equipment as part of a phased capacity expansion currently underway at DPRP’s 650,000-b/d refinery and petrochemical complex in the Lekki Free Zone near Lagos, Nigeria. In a Nov. 20 regulatory filing submitted to both BSE Ltd. and The National Stock Exchange of India Ltd., KBL said the combined value of the orders under the contracts amounted to about $38.94 million, $21.34 million of which would cover KEPL’s scope of work, with KBL to retain the remaining $17.60 million as compensation for a leg of the project. The service provider offered no additional details regarding either its own of KEPL’s scope of deliverables under the agreement other than that the work was to include engineering expertise and provision of “specialized pumping solutions for demanding energy applications.” The Lekki complex expansion involves increasing the refinery’s crude processing capacity by an additional 750,000 b/d to 1.4 million b/d in two phases to be executed between 2025-28 and 2028-30, respectively. The proposed expansion also includes plans to increase the site’s production of propylene by 750,000 tonnes/year (tpy), as well as adding 400,000 tpy of fresh production capacity for linear alkylbenzene (LAB).

Read More »

How NV5 Digital Twins Help Oil & Gas Facilities Reduce Downtime and Improve Safety

Refining, midstream, and production operators face increasing pressure to reduce downtime, improve safety, and make faster decisions with increasingly complex asset data. One leading international energy company partnered with NV5 Geospatial to deploy high-fidelity digital twins that unified engineering, inspection, and operational data across multiple facilities. The result: faster planning and approvals, safer operations, fewer travel requirements, and measurable reductions in outage windows.   The Challenge  The company’s refineries and offshore/onshore facilities are high-consequence environments where even brief shutdowns can cost millions per day. Engineering drawings, P&IDs, laser scans, SCADA/IoT feeds, and maintenance systems existed in separate silos making it difficult for staff to access a shared, current view of assets or to plan complex maintenance activities safely and efficiently.   Additionally, the organization sought to reduce field exposure for subject-matter experts (SMEs) by enabling remote collaboration and to improve predictability in outage planning and maintenance “switchovers,” where downtime forecasting directly affects operational revenue.   The Solution  NV5 Digital Twin = Geospatial system of record + automation.  NV5 delivered a scalable, field-to-cloud workflow that fused reality capture, engineering data, and live system integration into a unified, photorealistic 3D environment.   Reality Capture  Rotary-wing acquisition using NV5’s custom multi-sensor pod with RIEGL VUX-240 LiDAR (~300 ppsm) and 150MP nadir + oblique imagery (1″ GSD), flown with 80% side/forward lap for high-fidelity photomesh creation.  NV5 coordinated with local air-traffic control and operated from a nearby hangar to minimize mobilization time.  IS-BAO Stage 3 aviation safety certification and on-staff licensed surveyors ensured quality and compliance.   This level of detail enables operators to virtually inspect assets, plan maintenance activities, and validate engineering decisions without repeated site visits. Processing and Integration  SBET-calibrated LiDAR and imagery were processed into advanced classified point clouds, DEM/DSM surfaces, and textured 3D meshes (delivered OBJ/Esri Scene Layer, and Cesium 3D Tiles 1.1 formats).  Engineering

Read More »

The Data Center Backlash Has a Playbook

The data center industry’s next development constraint may have less to do with megawatts than with the politics of where those megawatts are deployed. The warning became difficult to ignore on November 3, when American voters approved 33 local ballot measures restricting data center development or expressing opposition to it, according to Ballotpedia’s analysis of the 2026 midterm elections. The results included outright bans, partial prohibitions, temporary moratoriums, and new requirements for community oversight. Voters also rejected 13 measures that would have favored development or expressed support for it. For an industry accustomed to evaluating prospective sites through the availability of power, land, fiber, capital, and construction resources, the election results reinforced another increasingly consequential consideration: whether the communities hosting digital infrastructure are willing to accept its growing physical and economic footprint. As Data Center Frontier recently examined in its post-election assessment of the industry’s political future, the national push to accelerate AI infrastructure construction is colliding with a more complicated political reality at the state and local levels. Opposition crosses party lines, while questions surrounding utility rates, water, environmental impacts, and local economic benefits have moved from planning commission meetings into broader electoral debate. That changing environment was the subject of a conversation recorded at the DCF Trends Summit 2026 in Reston, Virginia, where DCF contributing editor Doug Black sat down with Adam Waitkunas, president of Milldam Public Relations, and Julia Chuang, founder of LocalQ Labs and an associate professor of sociology at the University of Maryland. Their discussion explored a fundamental shift in the development equation: community opposition is becoming more organized and politically consequential, but also more observable through data. The challenge for developers is to understand that risk early enough to influence site selection and project design, while recognizing that public trust cannot be manufactured through

Read More »

Oak Ridge’s AI Factory Moment: Lux, Nuclear Power, and the Next Data Center Frontier

For much of its history, Oak Ridge has been associated with the Manhattan Project and the subsequent development of America’s nuclear research and production capabilities. Established during World War II, the community became home to major facilities for uranium enrichment, nuclear materials processing, scientific research, and ultimately high-performance computing. Today, that legacy is being repurposed for a new generation of industrial development. The former K-25 uranium enrichment complex, once a critical part of the nation’s atomic weapons program, has been transformed into the East Tennessee Technology Park (ETTP), where extensive environmental cleanup and redevelopment have made former federal property available for commercial use. At an October 27 gathering in Oak Ridge, federal officials and nuclear industry representatives highlighted more than $15 billion in announced nuclear-related projects across the region, an investment wave subsequently documented in a November 17 DOE report on Oak Ridge’s emerging energy hub. The investment figure largely represents planned private-sector development rather than completed capital spending. Regional officials also anticipate demand for thousands of construction workers over the next five years, with additional permanent manufacturing and operating positions potentially following as projects advance. In March, DOE completed its largest Oak Ridge land transfer to date, conveying more than 700 acres for economic reuse. The transfer included a 624-acre parcel designated for Orano USA’s planned uranium enrichment complex and a 77-acre parcel associated with Oklo’s proposed nuclear fuel recycling development. Overall, more than 2,500 acres have been transferred from federal ownership for redevelopment, following decades of cleanup and the demolition of hundreds of former industrial structures. For nuclear developers, the appeal is straightforward: large industrial sites, existing utility and transportation infrastructure, proximity to federal laboratories, and an established community of nuclear engineers, technicians, researchers, and specialized manufacturers. For data center developers, the implications are somewhat different but no

Read More »

Dell and Microsoft drive private AI as enterprises seek greater data control

Dell Technologies and Microsoft are expanding their private cloud partnership with a new set of infrastructure offerings designed to let enterprises run AI models closer to their data, reduce reliance on public cloud services and maintain control over sensitive information. The announcement, made during Microsoft’s Ignite conference, extends Dell’s AI Factory with Nvidia initiative to Dell Private Cloud environments. It also reflects a growing industry push toward internally deployed AI inferencing, particularly among organizations dealing with sensitive corporate information, regulatory requirements and data residency restrictions, Dell stated. The expanded offering combines Dell Private Cloud, Microsoft Azure Local, Microsoft Foundry Local and Nvidia acceleration. The objective is to provide organizations with an integrated infrastructure for deploying heavy AI workloads inside their own data centers and firewalls, the companies said.

Read More »

StarlingX 13.0 updates the network stack for distributed edge deployments

Edge sites do not always come with the network gear that a data center takes for granted. That’s a challenge the open-source StarlingX project from the OpenInfra Foundation is now tackling in its 13.0 update. StarlingX is an open-source distributed cloud platform that combines Linux, Kubernetes, OpenStack, and Ceph. The OpenInfra Foundation hosts the project, and operators including Verizon, Vodafone, T-Systems and KDDI use it for 5G and Open Radio Access Network (O-RAN) infrastructure. Earlier this year, the StarlingX 12.0 update added precision timing capabilities to help networking stay on time. The 13.0 update tackles a different set of issues. Key features include: Gateway API support. Calico-based support is available to hosted applications, while platform services still use Ingress NGINX Optional certificate authority. The Enterprise Java Beans Certificate Authority (EJBCA) runs on the platform and serves certificates to hosted applications. Subcloud restore. A backup restores directly onto a factory-installed node at a subcloud, a remote edge site, with no operating system reinstall. Direct upgrades. Operators can upgrade from two releases back with a single reboot per host. Layer 2 switching. A new Open vSwitch application lets servers at sites with no router next to them bridge traffic and connect directly to aggregation routers. “The OpenvSwitch application adds Layer 2 switching to the K8S platform,” Greg Waines, a senior member of technical staff at Wind River and a StarlingX Technical Steering Committee member, told Network World. “A server can bridge traffic between its SR-IOV network interfaces and other servers, and it can forward traffic to the site routers.”

Read More »

Sovereign AI is about control, not just location

Guetari was open about the term itself being fuzzy. “Sovereignty is very vague and not always clear,” he told me. “It’s about control, auditability, observability.” He drew a line between data locality, meaning the data stays in-country, and sovereignty, which he described as being “more about control, control of what happens to your data and your workload.” He then made the case for why F5 belongs in that conversation: “This is what we have been doing for two decades.” F5 has always sat in the data path, deciding what an application can communicate with, enforcing security rules, and logging what happened. For a regulated bank or government agency, the ability to reconstruct exactly what happened after an incident is worth more than a press release about a data center’s location. The token is the new unit of economics The most interesting part of my conversation with Guetari wasn’t about security. It was about business models. He argued that every successful technology business has found the right unit to monetize. “The cloud is selling the unit of the cloud, which is the CPU core, very well. SaaS is the seat,” he said. “Telcos have been very successful early on using the voice minute, and then they moved to the gigabyte. Sooner or later, that unit will be the token, and most telcos will have to move to the token. And the ones who will not go to token, unfortunately, will be just pipes.”

Read More »

Palo Alto Networks bets $4.5B on enterprise AI with Applied Compute acquisition

GPUs and data centers To train and host those models, Palo Alto plans to build its own compute capacity, CFO Dipak Golechha said on the call. The spending “will mostly go to GPUs and servers,” with a smaller share for the facilities that house them, he said. Palo Alto will “continue to source from our cloud partners” and add dedicated capacity over time, Golechha said. Arora said the company aims for more than100 megawatts of compute in the next three to five years. Gogia said Palo Alto has sovereignty credentials for security data, including customer-held keys and a European Cortex service governed by Deutsche Telekom. “None of that yet extends to GPUs,” he said, adding that a US-headquartered operator faces the same jurisdictional questions as the hyperscalers it rents capacity from. “A sovereign hosting offer with no named region, operator or date is a promise looking for an address,” Gogia said. Compliance officers should ask Palo Alto for a region list, the operator, and a dated certification plan, he said.

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »