Land & Expand: North America’s Data Center Pipeline Expands Under Pressure

Land & Expand is Data Center Frontier’s periodic look at the latest data center development news, including new sites, land acquisitions and campus expansions across North America. This latest installment finds the development pipeline continuing to expand, even as the requirements for bringing large-scale projects online grow more complicated. Developers are securing land, planning new […]

Land & Expand is Data Center Frontier’s periodic look at the latest data center development news, including new sites, land acquisitions and campus expansions across North America.

This latest installment finds the development pipeline continuing to expand, even as the requirements for bringing large-scale projects online grow more complicated. Developers are securing land, planning new power infrastructure and advancing campuses measured in hundreds of megawatts or more. At the same time, local governments and residents are demanding greater clarity on electricity costs, water consumption, noise, tax incentives and the long-term effects of industrial-scale computing facilities.

A succession of development disclosures and project milestones through September and early October 2026 illustrates both the geographical reach of North America’s expanding data center pipeline and the growing difficulty of measuring how much proposed capacity will ultimately be delivered.

The projects range from preliminary discussions and newly secured development sites to campuses already under construction. Some are advancing through formal permitting and power studies; others remain contingent on customers, financing or local approvals. Together, they reveal an industry still expanding aggressively, but operating under increasingly complex development conditions.

Fluidstack: Cameron County, Texas — Up to 1.5 GW

One of the largest newly disclosed projects is Fluidstack’s AI data center development in Cameron County in the Rio Grande Valley. The project surfaced publicly September 10 when Cameron County announced that it had issued Fluidstack a worksite permit for property near Harlingen. The permit authorizes preliminary site work, including grading, utilities and related infrastructure, rather than construction of the data center buildings themselves.

Fluidstack subsequently disclosed considerably more detail on September 21, saying construction had begun on a $4 billion first phase capable of supporting as much as 1.5 GW.

Fluidstack expects the project to generate more than 2,500 construction jobs and several hundred permanent positions.  The company has placed unusual emphasis on the project’s local infrastructure impact. It says it requested no local property-tax abatements and intends to pay for the energy, water and infrastructure necessary to serve the campus. Cooling will use a recirculating closed-loop system.

At up to 1.5 GW in its announced first phase, Cameron County represents a major addition to the Texas AI development pipeline, reflecting the increasingly industrial scale of projects designed to support advanced computing.

Microsoft ATL50: Union City, Georgia

A new filing for Microsoft’s ATL50 campus entered Georgia’s Development of Regional Impact review process on September 15. Microsoft filed plans for ATL50, a new data center campus at 5235 Stonewall Tell Road in Union City, southwest of Atlanta. Plans call for two three-story data center buildings totaling approximately 910,000 square feet on 88 acres. The filing projects completion in 2032.

Microsoft already has a substantial Georgia footprint, with development activity in Fairburn, Douglasville, Palmetto, Rome, East Point and other communities. ATL50 represents another proposed campus in the greater Atlanta market rather than entry into a new region. No electrical capacity has been disclosed.

Project Gravel: Pima County, Arizona

Another proposed development emerged through public-records reporting rather than a corporate announcement. Documents obtained in September disclosed Project Gravel, an eight-building data center campus being evaluated on approximately 160 acres of vacant land in unincorporated Pima County west of Sahuarita, Arizona.

Plans show eight buildings of roughly 203,000 square feet each, producing a potential campus of approximately 1.6 million square feet, along with a dedicated electrical substation, roads and parking infrastructure. Project documents contemplate full buildout by 2029, contingent on the development advancing through the necessary approvals.

County staff had reportedly been evaluating the proposal for months before details became public. Neither the developer nor a prospective tenant has been publicly identified, and the planned electrical load remains undisclosed. The disclosure has already generated local concern: Residents gathered September 29 to discuss the project’s potential effects on water, energy use and the surrounding environment. Sahuarita officials subsequently clarified that the proposed site lies outside town boundaries, under Pima County jurisdiction.

Project Gravel also illustrates the difficulty in determining the true size of the U.S. development pipeline. Large sites can remain in engineering, environmental and land-use review for months before appearing in conventional industry announcements.

Gray Oak Power: Undisclosed South Texas Campus

Another visible development appeared September 25, although considerably less is known about it. Gray Oak Power disclosed that a South Texas data center campus had advanced through ERCOT’s Studied Load Batch Zero process. The company has not disclosed the community, tenant or ultimate campus capacity.

Advancement through ERCOT’s Studied Load Batch Zero process confirms that another large-load development is progressing through the Texas interconnection review system, although it does not represent final grid-connection approval. Gray Oak’s proposed strategy calls for the campus to begin operating with dedicated onsite generation, followed by a utility grid connection and the eventual ability to supply electricity back to the grid. The company targets initial power in 2028 and utility grid service in 2029. Until the location, electrical load and customer are disclosed, the project remains an early-stage development.

Lambda: Mayes County, Oklahoma

On September 27, AI cloud provider Lambda announced an entirely new data center at the MidAmerica Industrial Park in Mayes County, Oklahoma, near Chouteau.

Lambda has not disclosed either the capital cost or megawatt capacity of the facility, but expects development to support as many as 1,000 construction jobs and 100 permanent positions. The company estimates the project could produce approximately $500 million in taxes over its first decade at current rates.

Unlike many data center announcements of several years ago, Lambda’s disclosure immediately addressed electricity costs and water consumption. The company says it will pay the full cost of the energy and infrastructure required to serve the facility, consistent with Oklahoma’s Data Center Customer Ratepayer Protection Act. Lambda also plans to use closed-loop cooling to reduce water consumption and is examining ways to shift or reduce certain computing workloads during periods of peak grid demand.

Google/Crusoe: Armstrong County, Texas

One of September’s most consequential disclosures concerned a project already well into construction. Google had announced plans for an Armstrong County data center in November 2025, but on September 28, Crusoe identified itself as the developer of the Google AI campus outside Amarillo. Crusoe said construction began in June 2025 and that more than 5,500 skilled workers were now on site daily.

The campus has direct connections to Serena’s adjacent 265.5 MW Goodnight 1 wind farm and the 265.5 MW Goodnight 2 project now under construction. Crusoe says excess wind generation can flow to the grid when production exceeds campus requirements. Neither Google nor Crusoe has disclosed the full electrical capacity of the data center campus. Those generation figures should not be confused with the data center’s electrical load, which has not been publicly disclosed.

The disclosure illustrates how construction can advance well beyond the initial project announcement before the full development structure becomes public. It also reflects the growing importance of colocating AI infrastructure with large-scale energy resources.

Clean Cloud Energy: Mahomet, Illinois

Illinois offered a different illustration of the pressures shaping data center development. On September 28, the Village of Mahomet disclosed that Clean Cloud Energy had approached the community about a potential data center campus on rural property west of Champaign. Discussions were preliminary but had advanced to include draft language for a possible development agreement. No formal project capacity or investment amount had been announced.

Those discussions came to an abrupt end. On October 5, the village announced that it would no longer pursue the development opportunity with Clean Cloud Energy, citing extensive public opposition. Residents had raised concerns about proximity to homes, noise, lighting, infrastructure requirements and potential impacts on the Mahomet Aquifer. Village President Jason Tompkins said community feedback had played a significant role in the decision not to proceed.
Mahomet provides a counterpoint to the larger projects advancing elsewhere.

The village’s decision ended its negotiations with the developer, although it does not establish that Clean Cloud Energy has abandoned broader development ambitions in the region. It also demonstrates that community opposition is no longer simply a public-relations challenge. In some jurisdictions, it can decisively alter the development process before formal permitting begins.

Zone Frontier: Potter County, Texas — 200 MW to 500+ MW

Zone Frontier announced a 30-year ground lease covering approximately 4,077 acres in Potter County, Texas, including land that could support as much as 800 acres of data center development.

The initial concept is approximately 200 MW, with the potential to expand beyond 500 MW. At least 1,800 acres could be used for solar generation, battery storage and associated energy infrastructure. The company has also secured a long-term water agreement. The property also surrounds Southwestern Public Service Company’s existing 345 kV Potter County substation, which Zone Frontier identifies as a potential route to grid interconnection alongside its proposed onsite generation resources.

Zone Frontier has not yet secured a tenant, and construction remains contingent on customer commitments, permitting, power arrangements and financing. The lease establishes substantial site control, not a committed construction schedule. Nevertheless, securing more than 4,000 acres with an envisioned development path beyond 500 MW places Potter County firmly within the emerging hyperscale development pipeline.

Beyond the Initial Disclosures: North America’s Development Pipeline Widens

The latest development news extends well beyond the projects disclosed during September. Across North America, hyperscalers and infrastructure developers are advancing additional campuses, expanding power commitments and exploring new regional markets. The activity ranges from redevelopment of former industrial properties to sovereign AI infrastructure and entirely new greenfield projects.

AWS Details 36-Building Plan at Pennsylvania’s Homer City

In Pennsylvania, additional details have emerged about Amazon Web Services’ proposed campus at the former Homer City coal-generating station. An October 6 report described AWS’s preliminary land-development plan for 36 data center buildings spread across approximately 1,100 acres in Indiana County, divided among six development areas.

The proposed buildings would each encompass approximately 225,000 square feet, with construction proceeding in four phases. Under the submitted schedule, work could begin in December 2026, with the final phase starting in 2032 and overall completion targeted for 2036. The proposal also includes electrical substations, supporting infrastructure and redundant generation.

As DCF previously reported, Homer City Redevelopment is building a multigigawatt natural-gas generating complex at the former coal plant site, with AWS positioned as a prospective principal power customer. The power development is already under construction, while AWS’s data center plans remain subject to the applicable land-use and construction approvals.

The newly detailed building program underscores the scale of the transformation: A retired coal-generation complex could become a long-term, integrated power and computing campus, provided the development and generation timelines converge.

Bell Expands Saskatchewan AI Ambitions Toward 1.2 GW

Canada’s emerging AI infrastructure market produced another major development in September when Bell Canada and the Government of Saskatchewan announced a nonbinding agreement to explore up to 900 MW of additional capacity for Bell AI Fabric.

The proposed expansion would build on Bell’s previously announced 300 MW campus near Regina, creating a potential 1.2 GW AI infrastructure hub. The company says total investment associated with a full buildout, including data centers, tenant computing equipment and related power generation, could exceed C$50 billion.

The additional capacity is expected to depend on partner-developed natural-gas generation, while Bell says its proposed facilities will use closed-loop cooling without municipal water requirements. Expansion timing will depend on securing customer commitments.

The significance extends beyond the capacity figure. Bell is positioning Saskatchewan as a center of Canadian-controlled AI infrastructure, reflecting the growing importance of data sovereignty alongside power availability and computing scale. However, the additional 900 MW remains a development objective under a nonbinding agreement, not committed operating capacity.

TeraWulf Accelerates Kentucky’s Muskie Campus Toward 1 GW

In eastern Kentucky, TeraWulf announced October 5 that it had expanded its contracted power arrangements with Kentucky Power for the Muskie Data Campus from 500 MW to 1 GW.

The amended agreements also accelerate the proposed second 500 MW phase from 2030 to 2029. The first phase remains targeted to begin ramping in 2028, while the revised second-phase schedule depends on Kentucky Public Service Commission approval and the utility’s construction timetable.

Unlike an early-stage land acquisition, Muskie’s latest development milestone concerns the amount and timing of contracted electrical service. That distinction matters as developers increasingly compete to establish credible schedules for delivering large blocks of power to AI infrastructure customers.

The amendment does not mean the full gigawatt is available today. It does, however, mark a substantive step in transforming an announced campus into a phased development with defined utility-service arrangements.

Mexico: Cuasar Targets 300 MW in Durango

Mexico’s data center development pipeline is also extending beyond its established concentration in Querétaro.

Cuasar Capital, associated with Spain’s EOSOL group, and infrastructure developer KA URBE IT have announced a partnership to market a proposed AI-oriented data center campus in Durango. The principal facility, DC Norte Uno, is designed for 300 MW of total capacity, including approximately 250 MW of IT load, on a 20-hectare site.

A second proposed facility, DC Norte Dos, would provide approximately 7.74 MW for edge computing and industrial applications. The developers are positioning the campus around high-density AI workloads and connectivity routes linking Durango with established Mexican and cross-border digital infrastructure markets.

The project remains at an early development and commercialization stage. Nevertheless, its proposed scale illustrates how AI infrastructure demand is encouraging developers to explore Mexican markets beyond the country’s existing hyperscale clusters.

Ontario: A 400 MW Proposal Confronts Local Planning Questions

In Sault Ste. Marie, Ontario, Algoma Steel and Red Jar Energy Partners have discussed a potential 400 MW AI data center development, illustrating another approach to converting established industrial locations into digital infrastructure.

The parties have sought an early position in Ontario’s Independent Electricity System Operator connection process to evaluate the feasibility of the project. An October 2029 operating date has been discussed, but the companies have not announced a binding construction commitment.

Municipal planning presents another obstacle. Sault Ste. Marie’s council moved toward preparing an interim-control bylaw that could pause data center development while the city establishes a local regulatory framework.

The proposal therefore remains preliminary. Its significance lies partly in the opportunity to reuse industrial infrastructure, and partly in the challenge of reconciling large new electrical loads with provincial grid planning and municipal approval requirements.

Google Explores New Mexico’s Lea County

Google is considering a new data center development in Lea County, New Mexico, potentially establishing its first self-built data center in the state.

In a September 14 announcement, the company acknowledged that discussions were underway but declined to provide a precise site, proposed electrical capacity or development schedule. Instead, Google emphasized early public engagement, responsible water management and commitments to cover the energy and infrastructure costs required by the project.

Lea County’s location along the Texas border places the potential development within a broader Southwest corridor attracting increasingly large investments in computing and energy infrastructure.

At this stage, Google’s interest represents market exploration rather than a committed construction project. It is nonetheless another indication that hyperscale site selection is moving into regions beyond the industry’s traditional development centers.

Additional Projects to Watch: Filings, Expansions and Capacity Milestones

A further group of developments illustrates how much activity is moving through permitting, construction and utility planning outside the industry’s largest headline announcements.

Project Longhorn, Bastrop County, Texas: An October filing identifies a proposed $366 million first data center building in Cedar Creek, encompassing approximately 498,000 square feet. The broader development has been linked in reporting to a proposed gas-fired power complex capable of supporting approximately 490 MW of IT load. Anthropic has been identified as a possible tenant in related reporting, but its participation has not been confirmed. The filing supplies a more concrete development marker than the previously reported tenant discussions.

Microsoft, Prince William County, Virginia: Microsoft has filed plans for the MNZ07 Wellington Data Center, consisting of two single-story buildings and an onsite substation on approximately 123 acres near Gainesville. The proposal includes federal environmental review because of potential impacts on wetlands and streams. It represents additional hyperscale development in Northern Virginia even as local governments tighten rules governing where new campuses can be built.

Skybox and Prologis, Hutto, Texas: The partners have filed plans for Skybox Hutto 4, an approximately 846,300-square-foot building with a reported development cost of $550 million. The fourth facility would become the largest building proposed at their PowerCampus development, which is targeting 600 MW of IT capacity across the broader site.

Applied Digital, Ellendale, North Dakota: Not every milestone concerns proposed capacity. Applied Digital announced that another 75 MW of critical IT load had reached ready-for-service status at its CoreWeave-leased Polaris Forge 1 campus. The milestone brings completed campus capacity to 250 MW, toward a planned 400 MW full buildout. This is a more tangible measure of deployment progress than an early-stage site announcement.

ThisWay Global, Bryan, Texas: A proposed 73 MW Research and AI Compute Center at Texas A&M-RELLIS would provide computing infrastructure for research, government and industry users. Planned for phased development on approximately 25 acres, the project would use direct-to-chip liquid cooling and remains subject to the necessary approvals.

Taken together, these additional developments reinforce the central distinction emerging across North America. Some developers are acquiring land or introducing proposals; others are securing power agreements, advancing environmental reviews or completing facilities capable of serving customers. The pipeline continues to grow, but the distance between an announced megawatt and an operational one remains a defining measure of development progress.

The Pipeline Grows Under Closer Scrutiny

These development disclosures arrive amid intensifying scrutiny of the industry’s expansion. On July 18, opponents organized 142 demonstrations across 42 states in a coordinated national protest of data center development. A Reuters/Ipsos survey published in June found that only about one-third of Americans supported the rapid pace of construction, while just 14% said they would welcome a data center in their own community.

The pressure continued into September. On September 15, Loudoun County, Virginia, supervisors voted to consider a resolution that could pause final action on certain data center and electrical substation applications requiring legislative approval for up to 12 months. The resolution is scheduled for consideration October 20. In Chicago, Mayor Brandon Johnson introduced a proposal for a one-year moratorium on permits and approvals for new or expanded data centers while city officials study their power, water and community impacts. Neither action represented an enacted moratorium as of October 12.

The pressure continued into September.  Loudoun County, Virginia voted September 15 to develop a process that could pause final action on certain new data center and substation applications for as long as 12 months while the county rewrites its policies. Chicago Mayor Brandon Johnson has proposed a 12-month moratorium on new data centers within the city while officials study their power, water and community impacts.

Yet the flow of development announcements continues. What has changed is the level of scrutiny that accompanies them. New project disclosures increasingly address ratepayer protection, closed-loop cooling, onsite generation, water availability and infrastructure financing alongside investment, construction schedules and job creation. Those commitments reflect an industry adjusting to the realities of developing power-intensive infrastructure at unprecedented scale.

The emerging distinction is between securing a development opportunity and demonstrating that it can be delivered. Land, electrical capacity, financing, permitting and community acceptance are increasingly interdependent requirements. As the latest projects illustrate, the North American data center pipeline remains substantial, but the path from proposed campus to operating infrastructure is becoming more demanding.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

North America rig numbers dip

Total drilling activity in North America decreased slightly the week ended Nov. 6 with a total of 827 rigs working, reported Baker Hughes. A 1-rig increase in the US helped offset a 3-rig loss in Canada. The total North American rig count is down 2 units from this time last

Read More »

Vaalco advances to second exploration phase in block offshore Côte D’Ivoire

Vaalco Energy Inc., Houston, has been granted government approval to begin the second exploration phase at Block CI-705, offshore Côte d’Ivoire. News comes following encouraging results following completion of the first exploration phase work commitments, which included the evaluation and interpretation of existing seismic and well data, the company said in a release Nov. 9. Work on the second exploration phase includes additional seismic reprocessing, relinquishing 25% of the exploration block to the government, and commitment to drill an exploration well by yearend-2028. In March 2025, Vaalco farmed into and became operator of the exploration license with a 70% working interest. The block lies in the Ivoirien basin about 70 km to the west of Vaalco’s CI-40 Block, which hold Baobab and Kossipo oil fields. “We see encouraging prospectivity on the block in the play types proven throughout the Ivoirien Basin including both structural and stratigraphic traps in the Upper Cretaceous and Albian sections,” said George Maxwell, Vaalco’s chief executive officer. “Recent nearby discoveries are on trend with CI-705 and provide additional validation of our play concepts and our view of the block’s prospectivity,” he continued.

Read More »

BSR, consortium enter talks for potential downstream collaborations

Vietnam Refining and Petrochemical Corp. (BSR) has entered talks with a consortium of FutureTec Co. and Zhejiang Hanghua Technology Co. Ltd. (Hanghua) to discuss and explore development opportunities along the refining and petrochemical value chain. At a Nov. 5 meeting between the parties, officials from the companies weighed potential collaborations on the deep processing of petroleum products, the development of value-added products, and research into related industrial infrastructure projects, BSR said in a release Nov. 6. While specific projects discussed at the meeting were not revealed, BSR said the event has laid the groundwork for further in-depth talks on potential areas of collaboration that would contributing to expanding the petrochemical refining value chain, improving resource utilization efficiency, and moving operations towards sustainable development. The proposed collaboration discussion comes amid shared interests of BSR and the FutureTec-Hanghua consortium in developing green, clean, and environmentally friendly products, as well as researching and developing new higher-value products, BSR said. With its experience in operating and managing refineries, BSR offers a favorable platform for expanding cooperation efforts with partners such as FutureTec and Hanghua that bring specialized capabilities in technology, research, and product development, added Nguyen Viet Thang, BSR’s general director. Potential collaborations with external partners come alongside BSR’s upgrading and expansion project now underway at the operator’s the 6.5-million tonne/year (tpy) refinery in the Dung Quat Economic Zone of Binh Tri Commune in Binh Son District, Quang Ngai Province, Vietnam. During the Nov. 5 meeting with the FutureTec-Hanghua consortium, BSR said its near-term plans for the refinery—which is currently operating at about 121% capacity—include further improving operational efficiency; optimizing technological processes; diversifying crude oil and product sourcing; as well as developing additional cleaner, sustainable fuels, petrochemicals, and high-value products. The operator said it will also continue focusing on efforts further efficient energy use,

Read More »

Every virtual megawatt needs a meter

Last month, Google announced a deal with Voltus for a virtual power plant (VPP) of up to 1,070 MW in PJM, roughly the output of a large nuclear reactor. Rather than build a plant, Voltus will offer homes and businesses financial incentives to trim usage when the grid is strained, through smart thermostats, batteries and flexible equipment. The deal represents an inflection point for the power and utilities sector, where “speed to power” innovations are defining the moment. It also underscores the importance of the equipment that will decide how far such programs go: the electric meter. Capacity you find instead of build NEMA’s 2026 Grid Reliability Study projects U.S. economy-wide electricity demand as much as 55% by 2050, with data center consumption alone growing 300% over the next decade. New generation and transmission can’t keep pace, as permitting, capital needs and equipment and skilled labor backlogs protracting project delivery timelines. As a result, operators are looking for capacity in the system they already have. On the transmission side, grid-enhancing technologies show what’s possible: PJM modeling finds they could unlock between six and seven GW of usable capacity. At the grid edge, the opportunity may be larger. Demand response contributed 33.3 GW of enrolled wholesale capacity in 2024, about 6.5% of peak demand in organized markets and could reach 20% of U.S. peak by 2030. Behind-the-meter resources, which include microgrids and aggregations of customer-sited resources (i.e., VPPs), are scaling too. What these grid-edge resources share is a need for measurement. A demand response event or VPP dispatch only has value if someone can prove the load dropped and pay the customer who dropped it. That job falls to the electric meter. Barriers to scale Despite the momentum, only 6.5% of U.S. electricity customers are enrolled in retail demand response programs.

Read More »

The next wave of energy storage capacity is already on the grid

Next week, much of the industry will gather in Las Vegas for RE+ to talk about what gets built next. It’s an important conversation, but I’d encourage asset owners to bring a second question with them: what more can we get from what’s already been built? This question matters more than ever as electricity demand climbs and customers feel it on their monthly bill. EIA expects consumption to grow another 3.1% in 2027, driven largely by data centers and other commercial loads, while residential customers will pay nearly 5% more for power this year. The industry is working hard to add capacity, but getting it built takes time. According to Lawrence Berkeley National Laboratory and GridTracker, the median project built in 2025 spent more than five years moving from interconnection request to commercial operation and only 13% of the capacity that requested interconnection between 2000 and 2020 had come online by the end of 2025. New generation is essential, but the fleet already operating is an opportunity we can’t afford to pass up. With nearly 52 gigawatts (GW) of utility-scale battery storage operating in the U.S. as of mid-2026, the installed base is too large to overlook and performance across it varies widely. When a battery energy storage system (BESS) falls short, the instinct is often to blame the battery and reach for augmentation or replacement, but in many cases the bottleneck is the controls, software and integration around it. Operating assets are under more pressure Higher prices should raise the value of delivering power when and where the grid needs it, yet revenues for many operating assets are moving in the other direction. In ERCOT, the average battery earned 84% less in 2025 than at its 2023 peak, as more storage competed for the same services. With incentive economics

Read More »

Beyond megawatts: Nuclear’s other capacity expansion challenge

Nuclear growth plans are accelerating as data centers, large-load customers, uprates, restarts, extended operations and new generation projects reshape the industry’s outlook. But the challenge of capacity expansion extends far beyond megawatts. Every utility must also expand the capacity of its workforce.  The workforce challenge is not simply about hiring more people. Recruiting is critical, but so are retention strategies, qualification timelines, knowledge transfer processes and the availability of experienced employees and contractors. Utilities must continue operating existing plants safely and reliably while extending asset life, modernizing infrastructure, preparing for growth and developing the next generation of workers. In many cases, the same people are asked to do all of it.  An experienced engineer supporting an uprate may also be needed for aging management reviews. The supervisor helping qualify new employees may also be responsible for outage preparation. The skilled craft resources needed for capital projects are often the same resources supporting ongoing plant reliability and maintenance activities. To execute an ambitious growth plan, your workforce needs support and clear expectations as it navigates the demands of the present and the future.  That reality makes employee engagement and retention critical operational necessities.  Keeping today’s fleet running while preparing for tomorrow’s expansion  Across the industry, organizations are managing a growing list of demands. Employees are operating plants, supporting outages, resolving equipment issues, onboarding new hires, transferring knowledge, implementing modernization efforts and preparing for future growth. Subsequent license renewal and long-term operations programs add further demands through inspections, evaluations, documentation and equipment replacement activities.  At the same time, many organizations continue to face shortages in experienced operators, engineers, technicians and other critical roles. Long qualification timelines and retirements only increase the pressure.  Growth introduces another challenge that is less visible but equally important: cognitive load. Experienced employees must continually sort through competing

Read More »

Behind-the-meter power: An effective tool for bringing large utility customers online faster

Data centers and AI infrastructure are intensifying the strain on existing power grids across the U.S. Large-load facilities are built quickly, only to face years-long waits for grid interconnection and new generation capacity, such as gas turbines. Behind-the-meter (BTM) power is becoming an effective solution to bridge the gap between what the grid can provide and what data centers need to operate smoothly. Utilities and large-scale customers alike are embracing BTM power: 80 percent of utilities view BTM power generation as permanent infrastructure and expect it to serve a significant share of large-load demand by 2030, according to Bloom Energy’s 2026 Utilities Insights Report. Nearly two-thirds of data center developers cite onsite power as their primary response when grid timelines slip. “BTM addresses a major issue, which is avoiding increases in grid retail prices,” says Nik Nunes, Chief Executive Officer at Industrial Development Funding (IDF), a top investment partner of Bloom Energy. “For that reason, several governors have come out in support of it.” Key considerations for successful BTM power generation BTM power isn’t always a simple fix. It involves complications related to regulatory requirements, power storage and permitting. Yet, when used in tandem with local utilities in front of meter power resources, it can provide an effective bridge for bringing large-scale customers online faster, helping them bypass lengthy wait times for a grid connection. BTM can also be affordable over the long term relative to other power sources. To launch a successful BTM power effort, data center developers must address growing public concerns about noise, water usage and emissions. In many jurisdictions, permitting has become a challenge, and BTM power projects are often delayed. To simplify air permitting, it’s helpful for BTM solutions to produce few or no combustion-related emissions. Bloom Energy fuel cells run on natural gas today

Read More »

Land & Expand: Texas’ AI Boom Meets a New Political Reality

Hut 8 Advances a Gigawatt-Scale Campus Near Corpus Christi Another significant development came November 4, when Hut 8 reported continued progress on its Beacon Point AI data center campus in the Corpus Christi region. The company said that its previously announced second 352 MW IT-capacity lease had fully commercialized the campus, bringing the total contracted IT capacity associated with the two phases to 704 MW. The campus is designed around approximately 1 GW of utility capacity, a separate measure from the critical IT load under lease. Hut 8 estimates approximately $19.6 billion in base-term contract value across the two phases. In its third-quarter results, the company said construction of the campus substation had begun, alongside foundation and underground utility work for the first phase. Initial data hall delivery is targeted for the third quarter of 2027, with the second phase targeted for the second quarter of 2028. The company also disclosed agreements to acquire two energized sites in West Texas, with up to 230 MW of utility capacity at full energization, subject to outstanding approvals and infrastructure development. Those acquisitions point to another important trend: the increasing value of existing electrical infrastructure and sites that can potentially be adapted to serve advanced computing. As new greenfield projects face lengthy power studies and regulatory requirements, already energized locations may offer an alternative route to capacity. The distinction is especially important in markets such as Dallas-Fort Worth, where DCF’s analysis of CBRE’s first-half 2026 data found that approximately 95% of the region’s 765 MW under construction had already been preleased. PowerHouse and Big Watt Win Approval for Taylor Technology Campus Not every large new project is meeting resistance at the municipal level. On October 8, the City of Taylor approved a development agreement with PowerHouse Data Centers and Big Watt Digital for

Read More »

Google targets AI’s next infrastructure bottlenecks with two new TPUs

“It’s like adding more lanes to the highway,” he observed. “We’re not necessarily making each car travel faster, we’re creating more capacity so more traffic can move through the system at the same time.” Handling bursts, idling However, an agentic workload doesn’t behave exactly like a traditional inference workload. “It is bursty, long running, but often idle,” Lohmeyer noted. While it might generate outputs and call tools, it still has to wait for a response, maybe from a human, “literally for days.” During that time, it doesn’t need to do anything; it just needs to preserve context. But if resources are tied up for that entire multi-day period, they’re being wasted “90% plus of the time,” he said. Google Cloud’s open source TPU Sync is designed to address these issues by unifying memory, storage, and networking in software. The model-state layer for TPUs turns chip high bandwidth memory (HBM), host DRAM, shared storage, and the data center network into a “single, co-designed memory hierarchy,” the company said. It automatically tiers KV caches off the chip in milliseconds, streams context across nodes, and synchronizes RL weights to cut transfer latency and Time to First Token (TTFT) by more than 90%.

Read More »

DCF Global: Britain’s New Bargain With the AI Data Center Industry

The Global Perspective: A New Bargain for the AI Economy? Britain’s new Data Centre Covenant may ultimately prove important well beyond the United Kingdom. Governments across the world are attempting to reconcile the economic promise of AI infrastructure with the extraordinary physical requirements of building it. Electricity networks must accommodate loads measured in hundreds of megawatts. Utilities must plan transmission and generation investments years in advance. Communities are being asked to host facilities whose construction costs can run into billions, but whose permanent employment footprints may be relatively modest. At the same time, national governments increasingly view domestic computing capacity as a strategic asset. Britain is attempting to connect those issues within a single policy framework. Its approach differs in important respects from the fragmented regulatory environment in the United States, where utility commissions, state governments, local authorities, and regional grid operators exercise separate—and sometimes competing—powers over development. Nevertheless, the underlying questions are increasingly similar. In DCF’s October examination of Virginia’s changing data center policies, the industry’s largest established market was confronting new expectations concerning infrastructure costs, utility commitments, community impacts, and the conditions under which large facilities should receive development approval. Britain’s Covenant addresses comparable pressures through a more coordinated national initiative. It effectively proposes that preferential treatment for strategically important data center development should be accompanied by demonstrable public value. That is a meaningful evolution in the relationship between government and the industry. For years, data center investment announcements have emphasized capital expenditure, construction employment, technological leadership, and economic development. Those considerations remain important. But Britain’s emerging framework asks a more demanding set of questions: Can the project obtain real electricity capacity? Will it pay its fair share of infrastructure costs? Does it contribute to domestic capability? What obligations does it have to its host community? And can

Read More »

Don’t mention the data center: OpenAI calls them ‘compute campuses’ instead

Data centers’ increasing power consumption is straining the grid, with AI servers accounting for an ever larger share of that consumption, with further increases forecast. These demands are leading to a growing number of protests against the development of data centers, which could lead to construction delays. OpenAI claims that its Grid Protectors Program will meet some of those issues head-on by taking into account future capacity needs and working to make power flexibility a key element in data center, sorry, compute campus, design. The company said that the approach would differ, region by region. It has yet to finalize all the details of the scheme, but it hopes to head off some of the protests. It remains to be seen whether it has this effect. Google recently took the opposite approach to the peak consumption problem, proposing to pay people to turn off their appliances at times of high demand so that it can continue to power its data centers.

Read More »

Agentic AI boom expected to reshape CPU market

These activities include planning tasks, scheduling subtasks, calling external tools, managing interactions between multiple agents and evaluating results. Agents also rely on conventional computing resources to execute Python code, search databases, crawl websites and process information, according to TrendForce. As a result, the CPU is enjoying a new lease on life and becoming a more significant component of AI infrastructure rather than simply serving as a supporting processor for GPUs, according to TrendForce. TrendForce notes that traditional AI data centers have typically deployed approximately one CPU for every four to eight GPUs, reflecting the industry’s emphasis on accelerating computationally intensive AI workloads.

Read More »

DCF Poll: Does the Data Center Industry Need a Political Reset?

Matt Vincent is Editor in Chief of Data Center Frontier, where he leads editorial strategy and coverage focused on the infrastructure powering cloud computing, artificial intelligence, and the digital economy. A veteran B2B technology journalist with more than two decades of experience, Vincent specializes in the intersection of data centers, power, cooling, and emerging AI-era infrastructure. Since assuming the EIC role in 2023, he has helped guide Data Center Frontier’s coverage of the industry’s transition into the gigawatt-scale AI era, with a focus on hyperscale development, behind-the-meter power strategies, liquid cooling architectures, and the evolving energy demands of high-density compute, while working closely with the Digital Infrastructure Group at Endeavor Business Media to expand the brand’s analytical and multimedia footprint. Vincent also hosts The Data Center Frontier Show podcast, where he interviews industry leaders across hyperscale, colocation, utilities, and the data center supply chain to examine the technologies and business models reshaping digital infrastructure. Since its inception he serves as Head of Content for the Data Center Frontier Trends Summit. Before becoming Editor in Chief, he served in multiple senior editorial roles across Endeavor Business Media’s digital infrastructure portfolio, with coverage spanning data centers and hyperscale infrastructure, structured cabling and networking, telecom and datacom, IP physical security, and wireless and Pro AV markets. He began his career in 2005 within PennWell’s Advanced Technology Division and later held senior editorial positions supporting brands such as Cabling Installation & Maintenance, Lightwave Online, Broadband Technology Report, and Smart Buildings Technology. Vincent is a frequent moderator, interviewer, and keynote speaker at industry events including the HPC Forum, where he delivers forward-looking analysis on how AI and high-performance computing are reshaping digital infrastructure. He graduated with honors from Indiana University Bloomington with a B.A. in English Literature and Creative Writing and lives in southern New Hampshire with

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »