AI Is Turning Energy Storage Into Active Power Infrastructure

AI Turns the Power Problem Into a Transient Problem At the heart of the issue is the changing behavior of the IT load. In a conventional data center, DeLattre said, large numbers of independent loads create a relatively predictable electrical profile. AI clusters introduce much greater synchronization. As GPUs begin processing a common workload, large […]

AI Turns the Power Problem Into a Transient Problem

At the heart of the issue is the changing behavior of the IT load. In a conventional data center, DeLattre said, large numbers of independent loads create a relatively predictable electrical profile. AI clusters introduce much greater synchronization.

As GPUs begin processing a common workload, large numbers of accelerators can increase their power consumption simultaneously. Instead of asking the electrical infrastructure to serve a relatively smooth load, the facility can experience fast power pulses moving through the system.

Hybrid supercapacitors are intended to act as a buffer between that dynamic compute load and the infrastructure supplying it. During an upward transient, storage provides some of the incremental power demanded by the IT load. When demand falls, the storage system recharges.

The objective is not to create additional energy. It is to keep every upstream component — from the UPS to generators and ultimately the utility connection — from having to respond directly to every rapid change taking place inside the AI cluster.

From the perspective of the upstream power source, DeLattre said, the goal is to make a highly dynamic AI load appear significantly smoother. That distinction between energy and power is central to Musashi’s argument for hybrid supercapacitors.

A conventional supercapacitor, also known as an electric double-layer capacitor, can deliver very high power almost instantly but stores relatively little energy. A lithium-ion battery can store considerably more energy, but DeLattre argues that it is less suited to being aggressively charged and discharged tens or hundreds of thousands of times.

Musashi’s hybrid technology uses a capacitor architecture with a lithium-doped graphite electrode intended to increase energy density while preserving the fast response and high cycling capability associated with capacitors. DeLattre reduces the distinction to a simple formulation.

“Batteries are very good at storing energy,” he said. “Supercapacitors or hybrid supercapacitors are very good at managing power.” Increasingly, he argues, managing power is precisely the problem AI infrastructure needs to solve.

From Backup Insurance to Active Power Infrastructure

That represents a significant departure from the historical role of storage inside the data center. For decades, batteries associated with uninterruptible power systems have essentially functioned as insurance. The utility fails, the UPS carries the critical load while backup generation starts and, if everything works as intended, the batteries return to standby.

AI potentially reverses that model. Instead of sitting idle until an emergency, energy storage can become part of normal data center operation, cycling repeatedly as it buffers compute peaks, stabilizes electrical buses and prevents fast-changing IT demand from propagating through the rest of the facility.

That changes the characteristics operators need from the storage itself. Response time becomes important. So does recharge speed. Cycle life becomes significantly more consequential if an asset expected to operate occasionally must instead charge and discharge repeatedly throughout its service life.

“We’re moving from energy storage as a backup infrastructure to really now energy storage … as part of an active power infrastructure,” DeLattre said.

That distinction also changes how storage economics should be evaluated. DeLattre said operators looking at frequently cycled storage need to consider more than acquisition cost. Footprint, maintenance, cooling requirements, replacement intervals and operational risk can all become part of the calculation.

Musashi says its system can exceed 100,000 cycles at 100% depth of discharge and potentially reach much higher cycle counts when operated at shallower depths of discharge over a 15-year design life.

Those figures are manufacturer specifications, but they illustrate the underlying question operators increasingly face: What happens to storage economics when the battery or capacitor is no longer waiting for a rare outage, but working every day?

The answer becomes even more significant if one storage asset can perform more than one job — providing short-duration resiliency while also managing normal AI power fluctuations.

At that point, DeLattre said, energy storage starts becoming “an infrastructure decision rather than simply a component comparison.”

Where You Manage the Transient Matters

Another emerging question is where that storage should physically sit. DeLattre does not expect a single answer. At the UPS level, high-power storage can provide ride-through during the interval between loss of utility service and generators accepting load. But AI is also creating interest in placing storage considerably closer to the compute itself.

DeLattre pointed to Musashi’s work with power-system providers including Flex and Delta, where capacitive energy storage can be positioned near server systems. The closer a buffer is placed to the origin of the transient, the less of that rapid change has to travel through the upstream electrical system.

“The biggest lesson we’ve learned … is where you manage the transient matters,” DeLattre said. That concept could become increasingly important as AI rack densities rise. A transient handled near the processor or rack does not have to propagate through multiple conversion stages, power distribution equipment and ultimately the facility-level power system before being addressed.

Musashi is also working with DG Matrix on architectures that combine storage with intelligent solid-state power electronics. In that model, the power system can coordinate the load and different forms of storage at a higher level, with the same basic objective: allowing the AI compute environment to behave dynamically without forcing the entire electrical infrastructure supplying it to behave the same way.

The eventual result may look less like a centralized battery room and more like distributed energy storage embedded at multiple points throughout the power architecture. Different technologies could occupy different layers because each layer is solving a different problem.

Can Storage Get More Compute From Existing Megawatts?

That architecture becomes particularly interesting in an industry where securing utility capacity has emerged as one of the central constraints on AI infrastructure development. Energy storage cannot solve a fundamental shortage of generation.

DeLattre is explicit about that limitation. If a data center needs an additional 10 MW continuously, storage does not eliminate the need to provide those 10 MW from the grid, onsite generation or another energy source.

Short-duration peaks are a different problem. Consider a data center whose average consumption remains within its available utility capacity but whose AI workloads occasionally create brief excursions above that envelope.

Rather than forcing the upstream infrastructure to follow every peak, a high-power storage system could supply incremental power during the excursion and recharge when demand falls.

The power source would see something closer to the facility’s average load instead of the instantaneous demand of the compute environment. For operators, the attraction is straightforward: potentially extracting more productive compute from an electrical envelope they have already secured.

“If you need 10 additional megawatts continuously, you’re still going to need 10 additional megawatts,” DeLattre said.

But needing those 10 MW for only a matter of seconds presents a fundamentally different engineering problem. This is also where electrical infrastructure and AI performance begin to intersect.

One alternative to energy buffering is software-based power management that prevents GPUs from ramping as aggressively. DeLattre argues that throttling accelerators to make their electrical behavior easier to manage can reduce the efficiency and performance of the compute resource operators paid to install.

Storage potentially moves that compromise elsewhere: allow the GPUs to operate dynamically while using the power system to prevent those dynamics from being imposed directly on the grid or generator.

Does the AI Data Center Still Need Minutes of UPS Runtime?

The distinction between power and energy raises another, more provocative question. How much UPS runtime does a modern data center actually require?

Data center operators have traditionally designed UPS systems around minutes of battery runtime. But DeLattre argues that the industry should at least reconsider that assumption where the primary mission of the UPS is to bridge the transition to backup generation.

If generators can reliably start and accept the load in seconds, he asks, does every facility need several minutes of stored energy, or does it principally need enough power to span the transfer? Those are different design objectives.

Musashi’s ES400 provides an example of the type of system DeLattre has in mind. The 400-kW platform can provide approximately 33 seconds of discharge at 333 kW, according to DeLattre, with systems capable of being paralleled where additional power capacity is required.

He describes generator startup and transfer as typically occurring within roughly 10 to 20 seconds. The argument does not mean minutes of UPS battery runtime are universally unnecessary. Data center resiliency requirements vary by topology, operating philosophy, generator architecture and the failure conditions a system is designed to withstand.

But the rise of AI gives operators another reason to separate two questions that have often been packaged together: How much energy needs to be stored, and how much power must be available instantly?

If storage is also going to absorb AI transients thousands of times rather than simply wait for a utility outage, optimizing those two requirements separately becomes more compelling.

Seconds, Not Hours

None of that makes batteries obsolete. In fact, DeLattre’s view of the emerging energy storage architecture depends on different technologies doing different jobs.

If an operator needs to run a data center for four hours following a grid outage, he said, a hybrid supercapacitor would be the wrong solution. Batteries, generators, fuel cells or other longer-duration resources make considerably more sense.

Similarly, hybrid supercapacitors are unlikely to be economically attractive for shifting energy consumption across periods measured in hours.

Their useful territory sits at the other end of the spectrum. A lot of power, delivered almost immediately, for a relatively short duration. And, increasingly important for AI, capable of doing it repeatedly. “Think seconds instead of hours,” DeLattre said.

The distinction matters because the AI power challenge is creating several problems that have traditionally been grouped under the broad heading of energy storage.

Resiliency is one problem. Long-duration backup is another. Grid interaction is another. Short-duration ride-through is another. Rapid GPU-driven power transients are yet another.

There is little reason to assume one storage chemistry or one physical storage system will be optimal for all of them.

From the Battery Room to an Energy Storage Architecture

That may ultimately be the most important change AI brings to data center energy storage. DeLattre expects that within three to five years, operators may talk less about “the UPS battery” or “the battery room” and increasingly about an overall energy storage architecture.

Some storage could provide longer-duration backup. Some could support the utility interface. Some could supply short-duration ride-through. And some could sit extremely close to processors, absorbing rapid changes in demand before they ever reach the rest of the electrical system.

That evolution would coincide with other changes already being contemplated for high-density AI infrastructure, including higher-voltage DC architectures, solid-state transformers, fewer power-conversion stages, onsite generation and increasingly intelligent power management.

In that environment, high-power storage becomes less of a static reserve and more of a control mechanism. That does not establish hybrid supercapacitors as the answer to every AI power problem. DeLattre himself argues against that conclusion.

Instead, the more significant possibility is that AI is dismantling the assumption that “energy storage” is one thing with one job. As compute becomes more dynamic, the electrical architecture serving it may have to become more specialized as well.

The battery room may not disappear. But it may become only one layer in a much broader energy storage system built around the behavior of AI itself.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Pros and cons of running AI on consumer hardware

So, instead of going the cloud route, the company opted to do something else: to use three MacBook Pros at about $5,000 each. The hardware was also readily available, Patel says. “On the Apple side, there’s not many hardware restrictions at this time,” he says. Meanwhile, more robust and specialized

Read More »

Vår Energi to acquire ConocoPhillips’ Norway business, including Greater Ekofisk operatorship, in $4.4-billion deal

The acquisition gives Vår Energi operatorship of the Greater Ekofisk Area, including the Ekofisk, Eldfisk, Embla, Tor, and Tommeliten Alfa and Gamma fields.  “The transaction adds significant scale, reserves and operatorship, while creating the opportunity to unlock materially greater value from a high-quality asset base with substantial remaining resources and

Read More »

TotalEnergies acquires interests in US gas assets from Continental Resources

@import url(‘https://fonts.googleapis.com/css2?family=Inter:wght@100..900&display=swap’); .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; color: color-mix(in srgb, currentColor 60%, transparent); } TotalEnergies SE has signed an agreement with Continental Resources Inc. to acquire interests in certain US natural gas upstream assets. A deal value was not disclosed. The transaction is expected to add about 150 MMscfd of net gas production, or roughly 26,000 boe/d, to TotalEnergies’ US portfolio by 2032, the company said Nov. 23. “We are pleased to further expand our cooperation with Continental Resources, a leading US operator in the region,” said Nicolas Terraz, president, exploration and production, TotalEnergies. “This transaction will strengthen our natural gas production in the [US] and consolidate TotalEnergies’ integrated position from upstream gas production to LNG exports.”   <!–> –> Sept. 29, 2025 <!–> –> <!–> Sept. 27, 2024 ]–> <!–> –> <!–> April 8, 2024 ]–> <!–> The deal follows TotalEnergies’ acquisition of non-operated interests with Continental in the Anadarko basin in 2025 and purchases in the Eagle Ford from EOG Resources and Lewis Energy in 2024. The newly acquired assets are described as low-cost, low-emission properties connected to existing midstream infrastructure. Combined with TotalEnergies’ operated Barnett shale position, the assets are expected to raise the company’s net US natural gas production to about 850 MMscfd, or more than 140,000 boe/d, beginning in 2032. TotalEnergies said it exported 19 million tonnes of US LNG in 2025, representing 18% of total US LNG exports. The company holds upstream gas production assets in Texas, Oklahoma, and the US Gulf of Mexico, interests in Cameron LNG and Rio Grande LNG, and LNG offtake

Read More »

Phillips 66 advances Humber refinery’s gasoline-improvement project

@import url(‘https://fonts.googleapis.com/css2?family=Inter:wght@100..900&display=swap’); .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; color: color-mix(in srgb, currentColor 60%, transparent); } Phillips 66 Co. has received major pieces of equipment for a previously announced project designed to enable production of higher-quality gasoline at its 221,000-b/d Humber refinery at South Killingholme in North Lincolnshire, UK, about 180 miles north of London on England’s eastern coast. On Nov. 20, the refinery received a delivery with a combined weight of more than 3,780 tonnes consisting of 55 shipping containers carrying 30 major pieces of equipment, as well as a mix of 30 mixed pre-assembled and self-contained units for further integration and assembly as part of the operator’s Humber gasoline quality improvement project, Phillips 66 UK said in separate posts to its official social media accounts. First announced in late 2025, the multiyear project at Humber site will allow the refinery to produce higher-value, higher-quality gasoline that will serve to strengthen UK domestic supply and support greater access to higher-value, premium export markets. While Phillips 66 has yet to reveal specific elements to be involved in the gasoline-quality upgrading works, the company reconfirmed in its latest November presentation to investors the project’s targeted completion remains on track for 2027.

Read More »

The grid’s hidden bottleneck: engineering capacity

The power system is undergoing an unprecedented transformation. Many of the reasons driving that change are well recognized and frequently discussed. Electricity demand from data centers, manufacturing and the electrification of transportation and building heating and cooling is surging. In fact, earlier this year the North American Electric Reliability Corporation (NERC) warned that grid reliability risks were increasing because demand was outpacing the new generation and transmission needed to serve it. Another challenge: the grid is old. The most recent American Society of Civil Engineers’ Infrastructure Report Card gave the nation’s energy system a D+, in part because of the age of the grid. Utilities have responded to an aging grid and skyrocketing electricity demand by making significant investments. The Edison Electric Institute (EEI) recently forecast that investor-owned utilities would spend $1.4 trillion through 2030 to meet customer demand for power. However, increased capital investment does not automatically translate into increased project execution. While funding, equipment availability and construction resources are critical, the engineering processes required to move projects from planning into construction represent another significant constraint. Utilities must not only invest in additional infrastructure but also rethink how that infrastructure is engineered and delivered. The engineering capacity squeeze Utilities are under pressure to move more projects through engineering and into construction, but experienced engineering resources are increasingly difficult to secure. While utilities can expand internal teams or engage additional engineering, procurement and construction (EPC) partners, scaling traditional engineering processes often introduces additional challenges. Different design tools, inconsistent engineering standards and repetitive manual work can limit productivity and increase coordination demands. That leaves utilities with a pressing question: how can they execute significantly more capital projects without a proportional increase in engineering resources? The substation engineering bottleneck Substation engineering provides a compelling example. While utilities have extensive engineering standards and established design practices, many

Read More »

Energy Secretary Keeps Critical Generation Available in Mid-Atlantic

WASHINGTON—U.S. Secretary of Energy Chris Wright today issued an emergency order to address critical grid reliability issues facing the mid-Atlantic region of the United States. The order directs PJM Interconnection L.L.C. (PJM), in coordination with Constellation Energy Corporation (Constellation Energy), to ensure Units 3 and 4 of the Eddystone Generating Station in Pennsylvania remain available to operate and to employ economic dispatch to minimize costs for the American people. The units were originally slated to shut down on May 31, 2025.   “The energy sources that perform when you need them most are the most valuable,” said U.S. Secretary of Energy Chris Wright. “President Trump and the Energy Department are committed to keeping critical generation available when demand is highest, reducing the risk of blackouts and ensuring Americans have affordable, reliable, and secure power—regardless of whether the wind is blowing or the sun is shining.”  Secretary Wright first ordered that the two Eddystone Generating Station units remain online past their planned retirement date in a May 30, 2025 emergency order. Subsequent orders were issued later in 2025 and 2026. Keeping these units operational has strengthened energy security in the PJM region, ensuring reliable electricity for American families and businesses. This order is in effect beginning on November 21, 2026, through February 18, 2027. 

Read More »

ExxonMobil takes FID on Angola Block 15 extension project

The Block 15 Lifespan Extension Project, about 145 km off Angola’s northern coast, will utilize existing infrastructure to develop additional resources throughout the Kizomba Hub area. The investment decision completes project FIDs following approval of Kizomba C redevelopment in 2025. ANPG also noted a hydrocarbon discovery in the block at the Tchihumba West-01ST1 exploration well, about 350 km northwest of Luanda. The discovery is the 21st in the block and the second this year. The well, drilled by the Valaris DS-9 in about 1,400 m of water, encountered 65.4 m of sandstone reservoir with hydrocarbon presence and good petrophysical properties. ExxonMobil is operator at Block 15 (36%) with partners Azule Energy Exploration (ANG) Ltd. (24%), Azule Energy ANG BV (18%), Equinor Angola (12%), and Sonongol E&P (10%).

Read More »

Market reforms bolster grid, may lower costs this winter: FERC

Listen to the article 4 min This audio is auto-generated. Please let us know if you have feedback. Electric market reforms in the West and Northeast may bolster grid reliability and, in some cases, lower costs this winter, according to the Federal Energy Regulatory Commission’s annual winter market and reliability report, released Thursday. Expanded markets help offset drought impacts In the West, the California Independent System Operator launched the Extended Day Ahead Market and the Southwest Power Pool expanded into the Western Interconnection earlier this year. “EDAM and SPP’s expansion should provide ratepayers in much of the West with production cost savings and improved reliability in winter 2026-2027, particularly during cold weather events,” FERC staff said in the report. This winter, the markets’ improved coordination of generation and reduced need for reserve power supplies will help offset lower power output from the Glen Canyon and Hoover dams due to historically low water levels in the Colorado River basin, staff said. “On a day-to-day basis, these conditions can create congestion and affect system operators’ ability to respond to voltage support challenges, event response mitigation needs, or any additional grid stressors,” staff said in the report. About 45% of the continental United States and 95% of the Intermountain West region is in a drought, according to the report. Hydro, oil pose challenges for Northeast In the Northeast, ISO New England lowered its capacity performance pay rate, which should lower electricity prices during emergency conditions or capacity performance events this winter, staff said. Also, the New York Independent System Operator changed its installed capacity market rules to reflect uncertainty about how much power Hydro–Québec will deliver over the 1,250-MW Champlain Hudson Power Express transmission line in the winter, they noted. The U.S. subsidiary of the Canadian utility Hydro-Québec — the primary reservation holder — has an obligation

Read More »

It’s the Roaring 2020’s for the HPC-AI Data Center Industry, But It Comes with Costs

It has been, and will very likely continue to be, the “Roaring 2020’s” for the HPC-AI data center industry. But similar to the generally healthy U.S. economy, affordability is a problem. Driven by demand for advanced computing technology, the HPC-AI data center infrastructure industry is generating tremendous growth, according to the latest market update figures released by industry analyst firm Hyperion Research. But with high demand come strains on supply chains that result in higher costs that restrain even higher growth. This is the picture presented this week by Hyperion at their annual breakfast at the SC26 Supercomputing Conference in Chicago. The customary large crowd turned out to hear Hyperion CEO Earl Joseph and colleagues discuss the state of the industry, some sectors of which are expanding at a clip Joseph said has never before been seen. “2025 was an extremely high growth year for the market…,” said Hyperion CEO Earl Joseph of on-premises servers for HPC, AI and data centers. “The first half of this year is growing at 20 percent… This is more than a doubling of historic growth. And then looking at the overall market in addition to servers, the storage, middleware, application services and spending for running HPC and AI for science workloads in the cloud…the market has just grown tremendously.” Among Hyperion’s key findings:         Overall HPC spending grew by just under 17 percent in 2025 reaching a total of more than $70 billion, including nearly 30 percent growth in cloud usage. Worldwide sales of on-prem for HPC and AI-for-science servers reached $29.4 billion, an increase of nearly 15 percent, with the EMEA region growing by roughly 10 percent. For the combination of HPC and AI-for-science on-prem servers plus cloud, the overall market is expected to double over the next five years,

Read More »

The Data Center Backlash Has a Playbook

The data center industry’s next development constraint may have less to do with megawatts than with the politics of where those megawatts are deployed. The warning became difficult to ignore on November 3, when American voters approved 33 local ballot measures restricting data center development or expressing opposition to it, according to Ballotpedia’s analysis of the 2026 midterm elections. The results included outright bans, partial prohibitions, temporary moratoriums, and new requirements for community oversight. Voters also rejected 13 measures that would have favored development or expressed support for it. For an industry accustomed to evaluating prospective sites through the availability of power, land, fiber, capital, and construction resources, the election results reinforced another increasingly consequential consideration: whether the communities hosting digital infrastructure are willing to accept its growing physical and economic footprint. As Data Center Frontier recently examined in its post-election assessment of the industry’s political future, the national push to accelerate AI infrastructure construction is colliding with a more complicated political reality at the state and local levels. Opposition crosses party lines, while questions surrounding utility rates, water, environmental impacts, and local economic benefits have moved from planning commission meetings into broader electoral debate. That changing environment was the subject of a conversation recorded at the DCF Trends Summit 2026 in Reston, Virginia, where DCF contributing editor Doug Black sat down with Adam Waitkunas, president of Milldam Public Relations, and Julia Chuang, founder of LocalQ Labs and an associate professor of sociology at the University of Maryland. Their discussion explored a fundamental shift in the development equation: community opposition is becoming more organized and politically consequential, but also more observable through data. The challenge for developers is to understand that risk early enough to influence site selection and project design, while recognizing that public trust cannot be manufactured through

Read More »

Oak Ridge’s AI Factory Moment: Lux, Nuclear Power, and the Next Data Center Frontier

For much of its history, Oak Ridge has been associated with the Manhattan Project and the subsequent development of America’s nuclear research and production capabilities. Established during World War II, the community became home to major facilities for uranium enrichment, nuclear materials processing, scientific research, and ultimately high-performance computing. Today, that legacy is being repurposed for a new generation of industrial development. The former K-25 uranium enrichment complex, once a critical part of the nation’s atomic weapons program, has been transformed into the East Tennessee Technology Park (ETTP), where extensive environmental cleanup and redevelopment have made former federal property available for commercial use. At an October 27 gathering in Oak Ridge, federal officials and nuclear industry representatives highlighted more than $15 billion in announced nuclear-related projects across the region, an investment wave subsequently documented in a November 17 DOE report on Oak Ridge’s emerging energy hub. The investment figure largely represents planned private-sector development rather than completed capital spending. Regional officials also anticipate demand for thousands of construction workers over the next five years, with additional permanent manufacturing and operating positions potentially following as projects advance. In March, DOE completed its largest Oak Ridge land transfer to date, conveying more than 700 acres for economic reuse. The transfer included a 624-acre parcel designated for Orano USA’s planned uranium enrichment complex and a 77-acre parcel associated with Oklo’s proposed nuclear fuel recycling development. Overall, more than 2,500 acres have been transferred from federal ownership for redevelopment, following decades of cleanup and the demolition of hundreds of former industrial structures. For nuclear developers, the appeal is straightforward: large industrial sites, existing utility and transportation infrastructure, proximity to federal laboratories, and an established community of nuclear engineers, technicians, researchers, and specialized manufacturers. For data center developers, the implications are somewhat different but no

Read More »

Dell and Microsoft drive private AI as enterprises seek greater data control

Dell Technologies and Microsoft are expanding their private cloud partnership with a new set of infrastructure offerings designed to let enterprises run AI models closer to their data, reduce reliance on public cloud services and maintain control over sensitive information. The announcement, made during Microsoft’s Ignite conference, extends Dell’s AI Factory with Nvidia initiative to Dell Private Cloud environments. It also reflects a growing industry push toward internally deployed AI inferencing, particularly among organizations dealing with sensitive corporate information, regulatory requirements and data residency restrictions, Dell stated. The expanded offering combines Dell Private Cloud, Microsoft Azure Local, Microsoft Foundry Local and Nvidia acceleration. The objective is to provide organizations with an integrated infrastructure for deploying heavy AI workloads inside their own data centers and firewalls, the companies said.

Read More »

StarlingX 13.0 updates the network stack for distributed edge deployments

Edge sites do not always come with the network gear that a data center takes for granted. That’s a challenge the open-source StarlingX project from the OpenInfra Foundation is now tackling in its 13.0 update. StarlingX is an open-source distributed cloud platform that combines Linux, Kubernetes, OpenStack, and Ceph. The OpenInfra Foundation hosts the project, and operators including Verizon, Vodafone, T-Systems and KDDI use it for 5G and Open Radio Access Network (O-RAN) infrastructure. Earlier this year, the StarlingX 12.0 update added precision timing capabilities to help networking stay on time. The 13.0 update tackles a different set of issues. Key features include: Gateway API support. Calico-based support is available to hosted applications, while platform services still use Ingress NGINX Optional certificate authority. The Enterprise Java Beans Certificate Authority (EJBCA) runs on the platform and serves certificates to hosted applications. Subcloud restore. A backup restores directly onto a factory-installed node at a subcloud, a remote edge site, with no operating system reinstall. Direct upgrades. Operators can upgrade from two releases back with a single reboot per host. Layer 2 switching. A new Open vSwitch application lets servers at sites with no router next to them bridge traffic and connect directly to aggregation routers. “The OpenvSwitch application adds Layer 2 switching to the K8S platform,” Greg Waines, a senior member of technical staff at Wind River and a StarlingX Technical Steering Committee member, told Network World. “A server can bridge traffic between its SR-IOV network interfaces and other servers, and it can forward traffic to the site routers.”

Read More »

Sovereign AI is about control, not just location

Guetari was open about the term itself being fuzzy. “Sovereignty is very vague and not always clear,” he told me. “It’s about control, auditability, observability.” He drew a line between data locality, meaning the data stays in-country, and sovereignty, which he described as being “more about control, control of what happens to your data and your workload.” He then made the case for why F5 belongs in that conversation: “This is what we have been doing for two decades.” F5 has always sat in the data path, deciding what an application can communicate with, enforcing security rules, and logging what happened. For a regulated bank or government agency, the ability to reconstruct exactly what happened after an incident is worth more than a press release about a data center’s location. The token is the new unit of economics The most interesting part of my conversation with Guetari wasn’t about security. It was about business models. He argued that every successful technology business has found the right unit to monetize. “The cloud is selling the unit of the cloud, which is the CPU core, very well. SaaS is the seat,” he said. “Telcos have been very successful early on using the voice minute, and then they moved to the gigabyte. Sooner or later, that unit will be the token, and most telcos will have to move to the token. And the ones who will not go to token, unfortunately, will be just pipes.”

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »