Data centers are getting their own natural gas power plants

EXECUTIVE SUMMARY One of the biggest roadblocks to starting up a data center is getting approval to connect to the electric grid—a wait that could last as long as a decade. Some developers aren’t willing to wait and are instead opting to build their own off-grid, or behind-the-meter, gas power plants to fuel the AI boom.   xAI’s Memphis campus has famously used dozens of natural gas turbines, some of them without permits, as far back as 2024. At the time, that facility was a rarity, and it faced scrutiny from regulators. It remains the subject of ongoing legal battles. But the strategy of going off-grid for power has since become a lot more common. As of October 2026, data center developers have announced plans for more than 100 behind-the-meter gas power plants at facilities in the US, according to data from Cleanview, a market intelligence company. The facilities have a combined planned capacity of over 115 gigawatts, more than double the peak power demand of California. The vast majority of these announcements have come since the beginning of 2025. It’s possible that not all these facilities will be built; only a small fraction are under construction or operating today. But there’s a growing trend of large data centers looking to build their own power supply, and this could shape the grid—and its climate impacts—for decades to come. Building your own power plant is generally more expensive than just hooking up to the grid, but the AI rush has made developers willing to pay a significant premium to get online faster. “The biggest motivator for on-site power right now from data centers is speed,” says Musfika Mishi, an associate at BloombergNEF, an energy consultancy. When developers want to build a new industrial facility—like a data center—that requires a lot of electricity, they need to request a grid connection from a local utility or regional grid operator. That request kicks off a yearslong process in which grid planners study the existing grid to understand what would need to be built to safely deliver power to the facility without compromising reliability. Upgrades might be required, like building new transmission lines or larger transformers, and the developer might be on the hook to help pay for them. Rather than waiting for that process to play out, developers can opt to instead build their own power plants. These facilities are referred to as “behind the meter” because they sit on the customer’s side of a utility meter—supplying the building directly, rather than relying on a utility via a grid hookup. “This shift in the data center developers’ power strategies towards off-grid gas raises some important questions about how data centers will be powered going forward,” says Brendan Pierpont, director of electricity at the think tank Energy Innovation. Behind-the-meter doesn’t always mean being totally disconnected from the grid, however. Some facilities may build such plants as a temporary measure, eventually connecting to the grid and tapping their own power plants only as backup. “It’s really just a very expensive way to bridge that maybe five-to-seven-year timeline gap until these data centers can get a grid connection,” Pierpont says.  Even if gas plants are pitched as a near-term solution, building new fossil fuel infrastructure could lead to longer-term effects, since an operator might choose to continue running plants once they’ve spent money building them. “Even though data centers say that it’s a grid-bridging solution, the probability that it is going to be in use much longer is a real risk, and that leads to fossil fuel lock-in,” Mishi says.  The on-site gas rush could have major implications for greenhouse-gas emissions. Today, the US grid is still reliant on fossil fuels, but nuclear and renewables together make up about 40% of electricity generation. That means making a grid connection is generally a lower-emissions option than relying entirely on an on-site gas plant. (That’s not the case everywhere—India, for example, is expecting to see a data center boom in the next decade, and its grid is largely served by emissions-intensive coal-fired power plants today.)  Utilities are already planning to build more natural gas power plants on the grid to meet rising electricity demand. Equipment manufacturers are struggling to keep up with the surge, and it’s pushing developers of behind-the-meter plants toward less-efficient alternatives.  Today, large natural gas plants generally use combined-cycle turbines. These capture heat to generate additional electricity, making them more efficient than single-cycle turbines, which are generally cheaper to build. Very few of the planned behind-the-meter facilities, however, will use combined-cycle turbines, Mishi says. That means these off-grid plants will likely produce more greenhouse-gas emissions than even other natural gas resources.  BloombergNEF is also tracking on-site natural gas plants at data centers, finding 181 gigawatts’ worth of announced projects globally, with 90% of that capacity designated for the US. If all planned behind-the-meter gas plants for data centers in the US go ahead, they could emit 345 million metric tons of carbon dioxide equivalent each year by 2035, according to a BloombergNEF report. That’s 152 million metric tons more than if those data centers pulled power from the US grid—a difference greater than the total annual emissions of the Netherlands.  And while it might seem logical that data centers bringing their own power could ease communities’ energy bills, those facilities going off-grid doesn’t protect prices for everyone else, says Matthias Fripp, director of global policy research at Energy Innovation. More demand for natural gas could push its price higher, he explains, which could in turn raise rates for the roughly 60% of American households that use natural gas for heating and cooking. That effect may also trickle into electricity prices. There’s still a lot of uncertainty about how much of this gas rush will come to fruition, so this future isn’t set in stone. Today, just 4.9 gigawatts of behind-the-meter gas projects tied to data centers are operating, and 15.8 gigawatts are under construction, according to Cleanview’s data. Creative solutions could also help limit the climate burden of the on-site gas buildout, BloombergNEF’s Mishi says. Building gas alongside on-site renewables or energy storage could help limit how often a gas plant needs to fire up, she says, though the economics of building multiple energy sources can be tricky.  While the grid is struggling to keep up with demand, building more renewables could help, Fripp adds. In a recent study, his team found that building renewables and energy storage to meet rising electricity demand could be reliable and cheaper than relying on fossil fuels. “These data centers want a lot of power, and they want it fast, and the grid is not well equipped to provide that,” Fripp says. “There are potentially good solutions and bad solutions … Rushing off the grid and putting in your own behind-the-meter gas is probably a bad way, because it’s still going to raise other people’s bills, and it’s not great for the environment.”

One of the biggest roadblocks to starting up a data center is getting approval to connect to the electric grid—a wait that could last as long as a decade. Some developers aren’t willing to wait and are instead opting to build their own off-grid, or behind-the-meter, gas power plants to fuel the AI boom.  

xAI’s Memphis campus has famously used dozens of natural gas turbines, some of them without permits, as far back as 2024. At the time, that facility was a rarity, and it faced scrutiny from regulators. It remains the subject of ongoing legal battles. But the strategy of going off-grid for power has since become a lot more common.

As of October 2026, data center developers have announced plans for more than 100 behind-the-meter gas power plants at facilities in the US, according to data from Cleanview, a market intelligence company. The facilities have a combined planned capacity of over 115 gigawatts, more than double the peak power demand of California. The vast majority of these announcements have come since the beginning of 2025.

It’s possible that not all these facilities will be built; only a small fraction are under construction or operating today. But there’s a growing trend of large data centers looking to build their own power supply, and this could shape the grid—and its climate impacts—for decades to come.

Building your own power plant is generally more expensive than just hooking up to the grid, but the AI rush has made developers willing to pay a significant premium to get online faster. “The biggest motivator for on-site power right now from data centers is speed,” says Musfika Mishi, an associate at BloombergNEF, an energy consultancy.

When developers want to build a new industrial facility—like a data center—that requires a lot of electricity, they need to request a grid connection from a local utility or regional grid operator. That request kicks off a yearslong process in which grid planners study the existing grid to understand what would need to be built to safely deliver power to the facility without compromising reliability. Upgrades might be required, like building new transmission lines or larger transformers, and the developer might be on the hook to help pay for them.

Rather than waiting for that process to play out, developers can opt to instead build their own power plants. These facilities are referred to as “behind the meter” because they sit on the customer’s side of a utility meter—supplying the building directly, rather than relying on a utility via a grid hookup.

“This shift in the data center developers’ power strategies towards off-grid gas raises some important questions about how data centers will be powered going forward,” says Brendan Pierpont, director of electricity at the think tank Energy Innovation.

Behind-the-meter doesn’t always mean being totally disconnected from the grid, however. Some facilities may build such plants as a temporary measure, eventually connecting to the grid and tapping their own power plants only as backup. “It’s really just a very expensive way to bridge that maybe five-to-seven-year timeline gap until these data centers can get a grid connection,” Pierpont says. 

Even if gas plants are pitched as a near-term solution, building new fossil fuel infrastructure could lead to longer-term effects, since an operator might choose to continue running plants once they’ve spent money building them. “Even though data centers say that it’s a grid-bridging solution, the probability that it is going to be in use much longer is a real risk, and that leads to fossil fuel lock-in,” Mishi says. 

The on-site gas rush could have major implications for greenhouse-gas emissions. Today, the US grid is still reliant on fossil fuels, but nuclear and renewables together make up about 40% of electricity generation. That means making a grid connection is generally a lower-emissions option than relying entirely on an on-site gas plant. (That’s not the case everywhere—India, for example, is expecting to see a data center boom in the next decade, and its grid is largely served by emissions-intensive coal-fired power plants today.) 

Utilities are already planning to build more natural gas power plants on the grid to meet rising electricity demand. Equipment manufacturers are struggling to keep up with the surge, and it’s pushing developers of behind-the-meter plants toward less-efficient alternatives. 

Today, large natural gas plants generally use combined-cycle turbines. These capture heat to generate additional electricity, making them more efficient than single-cycle turbines, which are generally cheaper to build. Very few of the planned behind-the-meter facilities, however, will use combined-cycle turbines, Mishi says. That means these off-grid plants will likely produce more greenhouse-gas emissions than even other natural gas resources. 

BloombergNEF is also tracking on-site natural gas plants at data centers, finding 181 gigawatts’ worth of announced projects globally, with 90% of that capacity designated for the US. If all planned behind-the-meter gas plants for data centers in the US go ahead, they could emit 345 million metric tons of carbon dioxide equivalent each year by 2035, according to a BloombergNEF report. That’s 152 million metric tons more than if those data centers pulled power from the US grid—a difference greater than the total annual emissions of the Netherlands. 

And while it might seem logical that data centers bringing their own power could ease communities’ energy bills, those facilities going off-grid doesn’t protect prices for everyone else, says Matthias Fripp, director of global policy research at Energy Innovation. More demand for natural gas could push its price higher, he explains, which could in turn raise rates for the roughly 60% of American households that use natural gas for heating and cooking. That effect may also trickle into electricity prices.

There’s still a lot of uncertainty about how much of this gas rush will come to fruition, so this future isn’t set in stone. Today, just 4.9 gigawatts of behind-the-meter gas projects tied to data centers are operating, and 15.8 gigawatts are under construction, according to Cleanview’s data.

Creative solutions could also help limit the climate burden of the on-site gas buildout, BloombergNEF’s Mishi says. Building gas alongside on-site renewables or energy storage could help limit how often a gas plant needs to fire up, she says, though the economics of building multiple energy sources can be tricky. 

While the grid is struggling to keep up with demand, building more renewables could help, Fripp adds. In a recent study, his team found that building renewables and energy storage to meet rising electricity demand could be reliable and cheaper than relying on fossil fuels.

“These data centers want a lot of power, and they want it fast, and the grid is not well equipped to provide that,” Fripp says. “There are potentially good solutions and bad solutions … Rushing off the grid and putting in your own behind-the-meter gas is probably a bad way, because it’s still going to raise other people’s bills, and it’s not great for the environment.”

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

Pros and cons of running AI on consumer hardware

So, instead of going the cloud route, the company opted to do something else: to use three MacBook Pros at about $5,000 each. The hardware was also readily available, Patel says. “On the Apple side, there’s not many hardware restrictions at this time,” he says. Meanwhile, more robust and specialized

Read More »

Vår Energi to acquire ConocoPhillips’ Norway business, including Greater Ekofisk operatorship, in $4.4-billion deal

The acquisition gives Vår Energi operatorship of the Greater Ekofisk Area, including the Ekofisk, Eldfisk, Embla, Tor, and Tommeliten Alfa and Gamma fields.  “The transaction adds significant scale, reserves and operatorship, while creating the opportunity to unlock materially greater value from a high-quality asset base with substantial remaining resources and

Read More »

CrowdStrike buys missing network security piece in $43.9B Zscaler deal

The two companies are not starting from scratch. The statement described the relationship as one of CrowdStrike’s largest technology alliances, with more than 2,000 shared customers and 16 integrations. CrowdStrike argued that a partnership integrates separate products, while one company integrates “the data, the roadmap, the go-to-market, and the commercial

Read More »

TotalEnergies acquires interests in US gas assets from Continental Resources

@import url(‘https://fonts.googleapis.com/css2?family=Inter:wght@100..900&display=swap’); .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; color: color-mix(in srgb, currentColor 60%, transparent); } TotalEnergies SE has signed an agreement with Continental Resources Inc. to acquire interests in certain US natural gas upstream assets. A deal value was not disclosed. The transaction is expected to add about 150 MMscfd of net gas production, or roughly 26,000 boe/d, to TotalEnergies’ US portfolio by 2032, the company said Nov. 23. “We are pleased to further expand our cooperation with Continental Resources, a leading US operator in the region,” said Nicolas Terraz, president, exploration and production, TotalEnergies. “This transaction will strengthen our natural gas production in the [US] and consolidate TotalEnergies’ integrated position from upstream gas production to LNG exports.”   <!–> –> Sept. 29, 2025 <!–> –> <!–> Sept. 27, 2024 ]–> <!–> –> <!–> April 8, 2024 ]–> <!–> The deal follows TotalEnergies’ acquisition of non-operated interests with Continental in the Anadarko basin in 2025 and purchases in the Eagle Ford from EOG Resources and Lewis Energy in 2024. The newly acquired assets are described as low-cost, low-emission properties connected to existing midstream infrastructure. Combined with TotalEnergies’ operated Barnett shale position, the assets are expected to raise the company’s net US natural gas production to about 850 MMscfd, or more than 140,000 boe/d, beginning in 2032. TotalEnergies said it exported 19 million tonnes of US LNG in 2025, representing 18% of total US LNG exports. The company holds upstream gas production assets in Texas, Oklahoma, and the US Gulf of Mexico, interests in Cameron LNG and Rio Grande LNG, and LNG offtake

Read More »

Phillips 66 advances Humber refinery’s gasoline-improvement project

@import url(‘https://fonts.googleapis.com/css2?family=Inter:wght@100..900&display=swap’); .ebm-page__main h1, .ebm-page__main h2, .ebm-page__main h3, .ebm-page__main h4, .ebm-page__main h5, .ebm-page__main h6 { font-family: Inter; } body { line-height: 150%; letter-spacing: 0.025em; } button, .ebm-button-wrapper { font-family: Inter; } .label-style { text-transform: uppercase; color: var(–color-grey); font-weight: 600; font-size: 0.75rem; } .caption-style { font-size: 0.75rem; color: color-mix(in srgb, currentColor 60%, transparent); } Phillips 66 Co. has received major pieces of equipment for a previously announced project designed to enable production of higher-quality gasoline at its 221,000-b/d Humber refinery at South Killingholme in North Lincolnshire, UK, about 180 miles north of London on England’s eastern coast. On Nov. 20, the refinery received a delivery with a combined weight of more than 3,780 tonnes consisting of 55 shipping containers carrying 30 major pieces of equipment, as well as a mix of 30 mixed pre-assembled and self-contained units for further integration and assembly as part of the operator’s Humber gasoline quality improvement project, Phillips 66 UK said in separate posts to its official social media accounts. First announced in late 2025, the multiyear project at Humber site will allow the refinery to produce higher-value, higher-quality gasoline that will serve to strengthen UK domestic supply and support greater access to higher-value, premium export markets. While Phillips 66 has yet to reveal specific elements to be involved in the gasoline-quality upgrading works, the company reconfirmed in its latest November presentation to investors the project’s targeted completion remains on track for 2027.

Read More »

The grid’s hidden bottleneck: engineering capacity

The power system is undergoing an unprecedented transformation. Many of the reasons driving that change are well recognized and frequently discussed. Electricity demand from data centers, manufacturing and the electrification of transportation and building heating and cooling is surging. In fact, earlier this year the North American Electric Reliability Corporation (NERC) warned that grid reliability risks were increasing because demand was outpacing the new generation and transmission needed to serve it. Another challenge: the grid is old. The most recent American Society of Civil Engineers’ Infrastructure Report Card gave the nation’s energy system a D+, in part because of the age of the grid. Utilities have responded to an aging grid and skyrocketing electricity demand by making significant investments. The Edison Electric Institute (EEI) recently forecast that investor-owned utilities would spend $1.4 trillion through 2030 to meet customer demand for power. However, increased capital investment does not automatically translate into increased project execution. While funding, equipment availability and construction resources are critical, the engineering processes required to move projects from planning into construction represent another significant constraint. Utilities must not only invest in additional infrastructure but also rethink how that infrastructure is engineered and delivered. The engineering capacity squeeze Utilities are under pressure to move more projects through engineering and into construction, but experienced engineering resources are increasingly difficult to secure. While utilities can expand internal teams or engage additional engineering, procurement and construction (EPC) partners, scaling traditional engineering processes often introduces additional challenges. Different design tools, inconsistent engineering standards and repetitive manual work can limit productivity and increase coordination demands. That leaves utilities with a pressing question: how can they execute significantly more capital projects without a proportional increase in engineering resources? The substation engineering bottleneck Substation engineering provides a compelling example. While utilities have extensive engineering standards and established design practices, many

Read More »

Energy Secretary Keeps Critical Generation Available in Mid-Atlantic

WASHINGTON—U.S. Secretary of Energy Chris Wright today issued an emergency order to address critical grid reliability issues facing the mid-Atlantic region of the United States. The order directs PJM Interconnection L.L.C. (PJM), in coordination with Constellation Energy Corporation (Constellation Energy), to ensure Units 3 and 4 of the Eddystone Generating Station in Pennsylvania remain available to operate and to employ economic dispatch to minimize costs for the American people. The units were originally slated to shut down on May 31, 2025.   “The energy sources that perform when you need them most are the most valuable,” said U.S. Secretary of Energy Chris Wright. “President Trump and the Energy Department are committed to keeping critical generation available when demand is highest, reducing the risk of blackouts and ensuring Americans have affordable, reliable, and secure power—regardless of whether the wind is blowing or the sun is shining.”  Secretary Wright first ordered that the two Eddystone Generating Station units remain online past their planned retirement date in a May 30, 2025 emergency order. Subsequent orders were issued later in 2025 and 2026. Keeping these units operational has strengthened energy security in the PJM region, ensuring reliable electricity for American families and businesses. This order is in effect beginning on November 21, 2026, through February 18, 2027. 

Read More »

ExxonMobil takes FID on Angola Block 15 extension project

The Block 15 Lifespan Extension Project, about 145 km off Angola’s northern coast, will utilize existing infrastructure to develop additional resources throughout the Kizomba Hub area. The investment decision completes project FIDs following approval of Kizomba C redevelopment in 2025. ANPG also noted a hydrocarbon discovery in the block at the Tchihumba West-01ST1 exploration well, about 350 km northwest of Luanda. The discovery is the 21st in the block and the second this year. The well, drilled by the Valaris DS-9 in about 1,400 m of water, encountered 65.4 m of sandstone reservoir with hydrocarbon presence and good petrophysical properties. ExxonMobil is operator at Block 15 (36%) with partners Azule Energy Exploration (ANG) Ltd. (24%), Azule Energy ANG BV (18%), Equinor Angola (12%), and Sonongol E&P (10%).

Read More »

Market reforms bolster grid, may lower costs this winter: FERC

Listen to the article 4 min This audio is auto-generated. Please let us know if you have feedback. Electric market reforms in the West and Northeast may bolster grid reliability and, in some cases, lower costs this winter, according to the Federal Energy Regulatory Commission’s annual winter market and reliability report, released Thursday. Expanded markets help offset drought impacts In the West, the California Independent System Operator launched the Extended Day Ahead Market and the Southwest Power Pool expanded into the Western Interconnection earlier this year. “EDAM and SPP’s expansion should provide ratepayers in much of the West with production cost savings and improved reliability in winter 2026-2027, particularly during cold weather events,” FERC staff said in the report. This winter, the markets’ improved coordination of generation and reduced need for reserve power supplies will help offset lower power output from the Glen Canyon and Hoover dams due to historically low water levels in the Colorado River basin, staff said. “On a day-to-day basis, these conditions can create congestion and affect system operators’ ability to respond to voltage support challenges, event response mitigation needs, or any additional grid stressors,” staff said in the report. About 45% of the continental United States and 95% of the Intermountain West region is in a drought, according to the report. Hydro, oil pose challenges for Northeast In the Northeast, ISO New England lowered its capacity performance pay rate, which should lower electricity prices during emergency conditions or capacity performance events this winter, staff said. Also, the New York Independent System Operator changed its installed capacity market rules to reflect uncertainty about how much power Hydro–Québec will deliver over the 1,250-MW Champlain Hudson Power Express transmission line in the winter, they noted. The U.S. subsidiary of the Canadian utility Hydro-Québec — the primary reservation holder — has an obligation

Read More »

It’s the Roaring 2020’s for the HPC-AI Data Center Industry, But It Comes with Costs

It has been, and will very likely continue to be, the “Roaring 2020’s” for the HPC-AI data center industry. But similar to the generally healthy U.S. economy, affordability is a problem. Driven by demand for advanced computing technology, the HPC-AI data center infrastructure industry is generating tremendous growth, according to the latest market update figures released by industry analyst firm Hyperion Research. But with high demand come strains on supply chains that result in higher costs that restrain even higher growth. This is the picture presented this week by Hyperion at their annual breakfast at the SC26 Supercomputing Conference in Chicago. The customary large crowd turned out to hear Hyperion CEO Earl Joseph and colleagues discuss the state of the industry, some sectors of which are expanding at a clip Joseph said has never before been seen. “2025 was an extremely high growth year for the market…,” said Hyperion CEO Earl Joseph of on-premises servers for HPC, AI and data centers. “The first half of this year is growing at 20 percent… This is more than a doubling of historic growth. And then looking at the overall market in addition to servers, the storage, middleware, application services and spending for running HPC and AI for science workloads in the cloud…the market has just grown tremendously.” Among Hyperion’s key findings:         Overall HPC spending grew by just under 17 percent in 2025 reaching a total of more than $70 billion, including nearly 30 percent growth in cloud usage. Worldwide sales of on-prem for HPC and AI-for-science servers reached $29.4 billion, an increase of nearly 15 percent, with the EMEA region growing by roughly 10 percent. For the combination of HPC and AI-for-science on-prem servers plus cloud, the overall market is expected to double over the next five years,

Read More »

The Data Center Backlash Has a Playbook

The data center industry’s next development constraint may have less to do with megawatts than with the politics of where those megawatts are deployed. The warning became difficult to ignore on November 3, when American voters approved 33 local ballot measures restricting data center development or expressing opposition to it, according to Ballotpedia’s analysis of the 2026 midterm elections. The results included outright bans, partial prohibitions, temporary moratoriums, and new requirements for community oversight. Voters also rejected 13 measures that would have favored development or expressed support for it. For an industry accustomed to evaluating prospective sites through the availability of power, land, fiber, capital, and construction resources, the election results reinforced another increasingly consequential consideration: whether the communities hosting digital infrastructure are willing to accept its growing physical and economic footprint. As Data Center Frontier recently examined in its post-election assessment of the industry’s political future, the national push to accelerate AI infrastructure construction is colliding with a more complicated political reality at the state and local levels. Opposition crosses party lines, while questions surrounding utility rates, water, environmental impacts, and local economic benefits have moved from planning commission meetings into broader electoral debate. That changing environment was the subject of a conversation recorded at the DCF Trends Summit 2026 in Reston, Virginia, where DCF contributing editor Doug Black sat down with Adam Waitkunas, president of Milldam Public Relations, and Julia Chuang, founder of LocalQ Labs and an associate professor of sociology at the University of Maryland. Their discussion explored a fundamental shift in the development equation: community opposition is becoming more organized and politically consequential, but also more observable through data. The challenge for developers is to understand that risk early enough to influence site selection and project design, while recognizing that public trust cannot be manufactured through

Read More »

Oak Ridge’s AI Factory Moment: Lux, Nuclear Power, and the Next Data Center Frontier

For much of its history, Oak Ridge has been associated with the Manhattan Project and the subsequent development of America’s nuclear research and production capabilities. Established during World War II, the community became home to major facilities for uranium enrichment, nuclear materials processing, scientific research, and ultimately high-performance computing. Today, that legacy is being repurposed for a new generation of industrial development. The former K-25 uranium enrichment complex, once a critical part of the nation’s atomic weapons program, has been transformed into the East Tennessee Technology Park (ETTP), where extensive environmental cleanup and redevelopment have made former federal property available for commercial use. At an October 27 gathering in Oak Ridge, federal officials and nuclear industry representatives highlighted more than $15 billion in announced nuclear-related projects across the region, an investment wave subsequently documented in a November 17 DOE report on Oak Ridge’s emerging energy hub. The investment figure largely represents planned private-sector development rather than completed capital spending. Regional officials also anticipate demand for thousands of construction workers over the next five years, with additional permanent manufacturing and operating positions potentially following as projects advance. In March, DOE completed its largest Oak Ridge land transfer to date, conveying more than 700 acres for economic reuse. The transfer included a 624-acre parcel designated for Orano USA’s planned uranium enrichment complex and a 77-acre parcel associated with Oklo’s proposed nuclear fuel recycling development. Overall, more than 2,500 acres have been transferred from federal ownership for redevelopment, following decades of cleanup and the demolition of hundreds of former industrial structures. For nuclear developers, the appeal is straightforward: large industrial sites, existing utility and transportation infrastructure, proximity to federal laboratories, and an established community of nuclear engineers, technicians, researchers, and specialized manufacturers. For data center developers, the implications are somewhat different but no

Read More »

Dell and Microsoft drive private AI as enterprises seek greater data control

Dell Technologies and Microsoft are expanding their private cloud partnership with a new set of infrastructure offerings designed to let enterprises run AI models closer to their data, reduce reliance on public cloud services and maintain control over sensitive information. The announcement, made during Microsoft’s Ignite conference, extends Dell’s AI Factory with Nvidia initiative to Dell Private Cloud environments. It also reflects a growing industry push toward internally deployed AI inferencing, particularly among organizations dealing with sensitive corporate information, regulatory requirements and data residency restrictions, Dell stated. The expanded offering combines Dell Private Cloud, Microsoft Azure Local, Microsoft Foundry Local and Nvidia acceleration. The objective is to provide organizations with an integrated infrastructure for deploying heavy AI workloads inside their own data centers and firewalls, the companies said.

Read More »

StarlingX 13.0 updates the network stack for distributed edge deployments

Edge sites do not always come with the network gear that a data center takes for granted. That’s a challenge the open-source StarlingX project from the OpenInfra Foundation is now tackling in its 13.0 update. StarlingX is an open-source distributed cloud platform that combines Linux, Kubernetes, OpenStack, and Ceph. The OpenInfra Foundation hosts the project, and operators including Verizon, Vodafone, T-Systems and KDDI use it for 5G and Open Radio Access Network (O-RAN) infrastructure. Earlier this year, the StarlingX 12.0 update added precision timing capabilities to help networking stay on time. The 13.0 update tackles a different set of issues. Key features include: Gateway API support. Calico-based support is available to hosted applications, while platform services still use Ingress NGINX Optional certificate authority. The Enterprise Java Beans Certificate Authority (EJBCA) runs on the platform and serves certificates to hosted applications. Subcloud restore. A backup restores directly onto a factory-installed node at a subcloud, a remote edge site, with no operating system reinstall. Direct upgrades. Operators can upgrade from two releases back with a single reboot per host. Layer 2 switching. A new Open vSwitch application lets servers at sites with no router next to them bridge traffic and connect directly to aggregation routers. “The OpenvSwitch application adds Layer 2 switching to the K8S platform,” Greg Waines, a senior member of technical staff at Wind River and a StarlingX Technical Steering Committee member, told Network World. “A server can bridge traffic between its SR-IOV network interfaces and other servers, and it can forward traffic to the site routers.”

Read More »

Sovereign AI is about control, not just location

Guetari was open about the term itself being fuzzy. “Sovereignty is very vague and not always clear,” he told me. “It’s about control, auditability, observability.” He drew a line between data locality, meaning the data stays in-country, and sovereignty, which he described as being “more about control, control of what happens to your data and your workload.” He then made the case for why F5 belongs in that conversation: “This is what we have been doing for two decades.” F5 has always sat in the data path, deciding what an application can communicate with, enforcing security rules, and logging what happened. For a regulated bank or government agency, the ability to reconstruct exactly what happened after an incident is worth more than a press release about a data center’s location. The token is the new unit of economics The most interesting part of my conversation with Guetari wasn’t about security. It was about business models. He argued that every successful technology business has found the right unit to monetize. “The cloud is selling the unit of the cloud, which is the CPU core, very well. SaaS is the seat,” he said. “Telcos have been very successful early on using the voice minute, and then they moved to the gigabyte. Sooner or later, that unit will be the token, and most telcos will have to move to the token. And the ones who will not go to token, unfortunately, will be just pipes.”

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »