A data center can have an excellent power usage effectiveness (PUE) rating and still be a poor infrastructure investment. It may be located on a grid that cannot deliver additional power, rely on increasingly contested water supplies, or require extensive reconstruction to accommodate the next generation of AI hardware. None of those shortcomings will necessarily register in conventional facility-efficiency metrics.
That is the argument underlying the World Economic Forum’s September 21 report, Data Centre Sustainability and Resilience: A Decision Playbook for AI Infrastructure, developed in collaboration with Marsh. Rather than defining sustainability primarily through the performance of an individual facility, the report examines an AI campus in the context of the power generation, transmission, cooling, water, land, fiber, supply chains and communities on which it depends.
The scale of the challenge was reinforced by the International Energy Agency’s November release of its World Energy Outlook 2026, which projects that global data center electricity consumption will approximately double to 1,000 terawatt-hours (TWh) by 2030 under its Stated Policies Scenario.
Since the WEF report’s publication, announcements from hyperscalers, utilities and infrastructure suppliers have begun to put its recommendations to the test. Google has entered into a major nuclear uprate agreement and a separate set of power arrangements in Wyoming, while Amazon is supporting the evaluation of nearly a gigawatt of advanced nuclear generation in Indiana. NVIDIA is placing greater emphasis on computational output relative to power consumption and the ability to dynamically manage an AI factory’s electrical load. OpenAI has outlined a program intended to make future campuses responsive to grid constraints. Meanwhile, regulators, communities and utility customers are increasingly questioning who should bear the costs and risks of AI infrastructure expansion.
A Trillion-Dollar Opportunity, With an Important Qualification
The WEF estimates that more sustainable and resilient development practices could help unlock $700 billion to $1 trillion in global data center investment through 2030 by reducing project delays and cancellations. It is a substantial figure, but one better understood as an indication of the scale of investment potentially at risk than as a forecast of recoverable capital.
The estimate is based on applying an assumed 10%–15% exposure to project delays and cancellations against a projected $7 trillion in investment. Delayed investment, however, is not necessarily lost investment. Projects can also be derailed by deteriorating economics, financing constraints, equipment availability or changing demand assumptions that better environmental and infrastructure planning alone cannot resolve.
For a developer unable to establish when utility service will be available, the financial consequences of delayed energization can easily outweigh modest improvements in facility efficiency. A campus that requires unanticipated transmission or water infrastructure may face a substantially different capital budget from the one originally presented to investors. Given the pace of technological change, a facility design that cannot accommodate successive generations of processors may also strand mechanical and electrical investments long before the building reaches the end of its useful life.
Against this backdrop, the WEF’s central recommendation is not simply to spend more money on sustainability initiatives, but to identify the constraints that could undermine a project’s financial returns before making commitments that are expensive to reverse. Its framework encompasses development pathways, common decision principles, recommended metrics and market-specific constraint profiles, with guidance for developers, operators, enterprise customers, financial institutions and policymakers.
For developers, that means evaluating whether a proposed site can support both the initial project and subsequent expansion. For investors, it means looking beyond conventional construction costs and projected returns to assess exposure to delays, regulatory uncertainty and infrastructure dependencies. The framework does not prescribe a single solution. Its value lies in identifying the trade-offs that could undermine a project’s economics while there is still an opportunity to address them.
Nuclear Uprates Show the Appeal of Existing Infrastructure
One of the clearest examples came on October 6, when Google and Constellation announced a 20-year agreement supporting 890 MW of additional nuclear generating capacity at 11 operating reactor units in Illinois, Pennsylvania and New Jersey. Constellation outlined more than $4.3 billion in planned investments to increase the thermal and electrical output of existing facilities, with the first uprate expected in 2028.
The approach aligns with the WEF’s emphasis on evaluating infrastructure as a system. Rather than developing new generating stations, Constellation aims to increase output from facilities with established operating teams, existing grid connections and decades of operational experience. While uprates still require substantial capital investment, engineering work and regulatory approvals, they present a different execution risk profile than greenfield nuclear development.
The companies also announced a separate 15-year power supply agreement associated with 2,700 MW of existing generation within the PJM Interconnection market. The distinction is important: the proposed 890-MW uprate program represents incremental generating capacity, while the larger supply agreement draws on existing generation. The scale of a power procurement agreement does not necessarily reflect the amount of new capacity being added to the grid.
The financing landscape received additional support on October 27, when the U.S. Department of Energy (DOE) announced a conditional loan commitment of up to $5 billion for Constellation nuclear uprates and modernization projects in Illinois, Maryland and Pennsylvania. DOE estimates that the broader program could add nearly 1.1 GW of generating capacity from existing reactors. The DOE and Google announcements cover overlapping but not identical portfolios of projects, and their capacity figures should not be treated as additive. If finalized, the federal financing could reduce borrowing costs and improve the economics of extracting additional generating capacity from existing nuclear assets.
For data center developers, the critical consideration is how much power can be delivered, and when, rather than simply the size of an offtake agreement. Even nuclear uprates, which offer potential advantages over new plant construction, must be financed, approved, scheduled and completed before their additional generating capacity becomes available to support growing AI demand.
Wyoming Illustrates the Limits of Power-First Siting
Google’s expanding plans around Cheyenne, Wyoming, provide a more complex example of the infrastructure considerations identified by the WEF. On October 6, Black Hills Corp. disclosed definitive agreements to serve a planned Google data center through an arrangement involving up to 590 MW of grid-connected service and management of approximately 2.1 GW of third-party power resources through a private microgrid. The utility outlined $1.8 billion in planned investments to develop 564 MW of company-owned natural gas generating capacity, along with contractual and regulatory provisions intended to insulate existing customers from project-related costs. The overall 2.7-GW resource portfolio includes reserve margins and should not be equated with the campus’s anticipated computing load.
Eight days later, American Electric Power (AEP) announced plans to invest approximately $4 billion in a 702-MW Bloom Energy solid oxide fuel-cell installation near Cheyenne under a 20-year power purchase agreement (PPA) with Google. As DCF previously reported, construction is expected to begin before the end of 2026, with full operations targeted for late 2028. AEP also intends to incorporate carbon capture technology in pursuit of near-zero-emissions power, although the proposed system’s configuration and emissions performance remain to be established. The extent to which the AEP project overlaps with the capacity identified in the Black Hills agreements has not been publicly clarified.
Cheyenne demonstrates both the advantages and limitations of power-first siting. Developers are organizing generation, utility service and load management around the requirements of large-scale computing infrastructure rather than treating energy procurement as a final step in site selection. Securing generation commitments, however, addresses only part of the equation. A comprehensive assessment of project sustainability and resilience must also account for fuel supply, emissions, cooling water requirements, the microgrid’s interaction with the wider electrical network, reliability during equipment outages and the allocation of infrastructure costs to existing utility customers.
Google’s Geothermal Strategy Offers Another Pathway
Google’s pursuit of enhanced geothermal power in Utah offers another variation on power-first development. As DCF recently reported, the company’s 15-year agreement with Fervo Energy for 396 MW of grid-connected geothermal generation is accompanied by a potential 600-MW expansion that could deliver power directly to a proposed data center campus in Beaver County.
The distinction between contracted grid-connected generation, with initial power delivery expected in 2028, and a prospective behind-the-meter expansion subject to further commercial and regulatory milestones reinforces the importance of evaluating not only the source of electricity but also the infrastructure and contractual mechanisms through which it reaches the computing campus.
Amazon’s Indiana Nuclear Project Presents a Different Risk Profile
On October 19, AEP, X-energy and Amazon announced a development agreement to evaluate a 960-MW advanced nuclear project at the former Breed coal-fired power plant site in Sullivan County, Indiana. The proposed development calls for 12 Xe-100 small modular reactors (SMRs), each with a generating capacity of 80 MW. Amazon is supporting development work and intends to purchase electricity under a long-term agreement should the project proceed.
The proposed reuse of a retired generating site is consistent with the WEF’s recommendation to evaluate existing infrastructure and regional resources when selecting development locations. Former power plant sites can offer advantages over greenfield development, including available land, established transmission corridors and a regional workforce with energy industry experience. Leveraging those assets could reduce some development barriers, although the companies have yet to announce a final investment decision. Reactor licensing, nuclear fuel availability, construction schedules, financing and integration with the regional electrical grid remain critical dependencies.
The contrast with Constellation’s nuclear uprate program is instructive. Both initiatives address the growing demand for firm generating capacity, but one seeks to increase output from operating reactors while the other depends on the commercial-scale deployment of an emerging reactor technology. Existing infrastructure can offer development advantages in both cases, but the associated timelines, capital requirements and execution risks differ considerably. The WEF’s framework is particularly useful in distinguishing these factors when evaluating the long-term economics of power procurement for AI infrastructure.
Power Contracts Begin to Address the Costs of AI Growth
The WEF repeatedly connects project viability to community acceptance. But as DCF’s recent coverage of the growing data center backlash illustrates, the challenge extends well beyond conventional public outreach. Increasingly, disputes center on utility rates, infrastructure investment and whether existing customers will be asked to subsidize the rapid expansion of AI infrastructure.
An October 5 amended agreement between Kentucky Power and TeraWulf offers a direct example of how these concerns are beginning to influence power procurement. The agreement would double contracted electricity demand at TeraWulf’s Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW, with phased delivery targeted through 2029. Subject to Kentucky Public Service Commission (PSC) approval, the arrangement would also provide $100 million in winter electricity bill credits to residential customers over the first 10 years of the contract, funded by TeraWulf, alongside collateral requirements and other customer protections.
The project moved further into the regulatory process on November 13, when Kentucky Power filed plans with the PSC seeking approval for infrastructure needed to serve the campus, including a new 760-MW combined-cycle natural gas generating facility and a transmission substation. The utility projects more than $500 million in fixed-cost rate offsets for customers over the life of the agreement, in addition to the residential bill credits. TeraWulf has also agreed to cover estimated financing costs associated with construction of the proposed generating facility. Regulatory decisions could come as early as mid-2027.
What makes the arrangement noteworthy is that the financial impact on existing utility customers is being addressed through large-load contracts and formal regulatory proceedings rather than being left primarily to the public debate surrounding local development approvals. Whether the proposed protections ultimately deliver the anticipated benefits will depend on regulatory decisions, project execution and enforcement of the contractual provisions.
For utilities, developers and regulators, the relevant questions extend well beyond conventional facility-efficiency metrics: Who finances new transmission and generation? What minimum payment obligations apply if a campus consumes less electricity than projected? Who bears the financial risk if a development is delayed, downsized or canceled? These are the practical considerations underpinning the WEF’s broader argument that sustainable AI infrastructure must also be economically and socially durable.
NVIDIA Shifts the Focus From Megawatts Installed to Computing Output
On October 21, NVIDIA outlined several advances in its DSX AI factory platform, including software designed to optimize power allocation across AI workloads and cooling architectures intended to reduce onsite water consumption. As DCF previously reported, NVIDIA’s expanding DSX strategy reflects an increasingly integrated approach to AI factory design and operation, linking decisions made at the computing level with the electrical and mechanical infrastructure supporting it.
NVIDIA says its DSX MaxLPS technology can enable operators to generate the same number of tokens using up to 30% less power by dynamically reallocating available power within an AI factory’s provisioned capacity. Its DSX Flex software, meanwhile, is designed to coordinate workload power consumption with grid conditions, demand-response requirements and electricity prices. NVIDIA is also promoting reference designs that combine closed-loop liquid cooling with dry-cooler heat rejection, estimating that an illustrative 2-GW deployment could reduce daily water consumption for facility cooling by approximately 54 million liters compared with conventional cooling-tower-based systems.
These figures represent potential performance gains under specified design and operating conditions rather than independently established results across operating AI campuses. Local climate, workload characteristics, hardware configurations and facility design will influence the benefits realized in individual deployments.
The WEF encourages enterprise customers to evaluate smaller AI models, more efficient workload placement and whether computationally intensive processing is necessary for a given application. NVIDIA is extending that consideration into the engineering and operation of the AI factory itself: Can equivalent computational output be achieved with less power, or can more useful computing be delivered within an existing power allocation? For operators facing prolonged utility interconnection timelines and limited opportunities to secure additional generating capaci
Grid Flexibility Is Becoming a Commercial Proposition
The concept of AI facilities dynamically adjusting their electrical demand gained further commercial traction on November 2, when OpenAI introduced its Grid Protectors program. The initiative calls for developers and operators of future AI computing campuses to work with utilities and grid operators to establish mechanisms for reducing electricity demand during periods of grid stress. OpenAI identified its planned Effingham County, Georgia, campus as an initial deployment, citing an agreement with Georgia Power that provides for up to 1,000 MW of flexible demand response.
The operational and contractual details will determine the effectiveness of such arrangements: how much load can be reduced, how rapidly and for what duration, how frequently curtailment can occur, and whether reductions in grid demand will affect computing services or require the use of onsite generation or energy storage. OpenAI indicated that these parameters would be established in conjunction with utilities and would vary by location, reflecting differences in regional grid conditions and campus operating requirements.
OpenAI also cited Georgia Power’s projections of approximately $950 million in annual customer savings beginning in 2029. Those projected benefits, however, reflect the utility’s broader portfolio of large-load agreements and anticipated demand growth, rather than the financial impact of OpenAI’s project alone. As with the Kentucky Power–TeraWulf arrangement, the economic benefits to existing utility customers will ultimately depend on the terms and execution of the underlying agreements.
The WEF’s recommendation to integrate data centers into regional grid planning does not imply that every AI campus should operate as an interruptible load. Rather, the objective is to distinguish workloads that can tolerate temporary reductions in power consumption from those requiring continuous operation, and to structure commercial agreements around that distinction. NVIDIA’s DSX Flex technology and OpenAI’s Grid Protectors initiative illustrate how grid-responsive computing is progressing from an engineering proposition toward commercial products and contractual commitments. Demonstrating its effectiveness at operational gigawatt-scale AI campuses remains the next significant test.
Water Use Becomes a Legislative and Permitting Issue
The policy environment is catching up with the engineering discussion. On October 8, the National Conference of State Legislatures (NCSL) reported that its review of legislative activity in 2025 and 2026 had identified approximately 100 bills and resolutions across 39 states addressing data center water use and planning. Much of the proposed legislation focuses on disclosure requirements, consumption forecasts and the information water utilities and resource managers need to evaluate the potential impact of new development.
This activity aligns with the WEF’s emphasis on looking beyond conventional onsite water usage effectiveness (WUE) metrics. Closed-loop liquid cooling can minimize the need for replacement water within the cooling circuit, but the method of heat rejection remains a critical design consideration. Dry cooling can substantially reduce onsite water consumption while potentially increasing electricity demand during periods of high ambient temperatures. Evaporative cooling may offer greater energy efficiency under certain operating conditions, but at the expense of higher water consumption. The indirect water requirements associated with electricity generation and hardware manufacturing further complicate assessments of a facility’s overall water footprint.
For developers seeking regulatory approval and community acceptance, the ability to document and explain anticipated water consumption is becoming nearly as consequential as the selection of cooling technology itself. Communities, regulators and water authorities increasingly want to know where a facility’s water will come from, how much it will consume under normal and drought conditions, and whether projected demand will compete with the needs of households, agriculture and existing industry. As with electricity procurement, the viability of a proposed campus depends not simply on its engineering efficiency but on the availability and long-term resilience of the regional resources supporting it.
Existing Powered Sites Gain Strategic Value
Much of the WEF report addresses decisions made before a new campus is built, but its implications for the existing data center market may be even more immediate. Established operators already possess assets that new developers can spend years trying to secure: utility interconnections, substations, fiber connectivity, zoning approvals, physical facilities and established relationships with utilities and surrounding communities. As access to power increasingly dictates development timelines, these assets could become more valuable.
Existing infrastructure, however, is not inherently ready for AI-scale computing. An air-cooled facility designed around traditional enterprise workloads may lack the piping, pumping systems, heat-rejection capacity, electrical distribution infrastructure and localized power density needed to support racks exceeding 100 kW. The cost and complexity of retrofitting these systems may, in some cases, favor new construction. But where additional grid interconnections are unavailable or require years to secure, an existing powered site can offer a substantial strategic advantage, provided its infrastructure can be economically adapted.
This is where the WEF framework, NVIDIA’s emphasis on workload management and the integrated AI factory engineering approach being advanced by Schneider Electric converge. Coordinating workload scheduling, computing utilization, power distribution and thermal management could enable facilities to support more useful AI computing without a proportional increase in connected electrical load. The value of these approaches, however, must ultimately be demonstrated through measurable computational output and more efficient utilization of constrained infrastructure.
The transition also complicates conventional approaches to electrical system design and redundancy planning. As Google and Cummins engineers discussed at the October 2026 7×24 Exchange conference, synchronized AI workloads can produce rapid electrical load fluctuations that require different approaches to software controls, energy storage and generator response. Average power consumption and peak rack ratings alone are insufficient design parameters. Operators must also understand how workloads behave over time, how electrical infrastructure responds to transient loads, and what forms of operational flexibility can be achieved without compromising reliability or service commitments.
What the Announcements Demonstrate—and What Remains Unresolved
Industry developments since September have reinforced several of the WEF’s central conclusions. Power availability is shaping site selection and financing, while existing generation assets are receiving renewed attention as alternatives to greenfield power development. Data center customers are being asked to assume more explicit responsibility for the infrastructure costs associated with their electricity demand. Cooling technologies are increasingly being evaluated against local resource constraints rather than universal efficiency targets, and AI workload management is becoming an integral consideration in power-system design.
The framework nevertheless leaves important questions unresolved. It provides no universal methodology for determining when additional electricity consumption is justified by water conservation, or how much additional capital should be committed to resilience. Many of its proposed metrics are not yet standardized or widely reported, and reliable accounting for the energy, water and materials associated with semiconductor manufacturing, cooling equipment and successive generations of accelerator hardware remains difficult.
What is becoming clear is that sustainability is inseparable from the economics of building and operating AI infrastructure. Location, available utility power, mechanical efficiency, leasing demand and uptime remain fundamental considerations, but at AI scale they are only the starting point. Increasingly, the economics of a facility will depend on the timing and reliability of power delivery, the allocation of infrastructure costs and risks, the productivity of installed computing capacity and the ability to accommodate successive generations of technology without premature capital reinvestment.
The next generation of data center infrastructure will be judged not simply by how much capacity gets built, but by whether that capacity can be powered, cooled, financed, adapted and operated without transferring unacceptable costs to the systems and communities supporting it.