Kinder Morgan Inc. (KMI) has taken final investment decision (FID) on its Southeast Connector and Permian Link natural gas pipeline projects. Southern Natural Gas (SNG), a KMI subsidiary, secured sufficient long-term, take-or-pay transportation agreements with shippers to proceed with Southeast Connector, designed to transport up to 2.6 bcfd through about 470 miles of new pipeline.
Subject to receipt of required permits and approvals, service is expected to begin in phases starting fourth-quarter 2030. The $3.1-billion project could be expanded if demand warrants.
“Large-load interconnection requests across the Southeast now exceed 200 Gw,” said KMI chief executive officer and director Kimberly Dang in the company’s earnings call, noting that this could represent roughly 8 bcfd of natural gas demand if it all came to fruition and if it was all served by gas-fired generation.
Natural Gas Pipeline Co. of America (NGPL), another KMI subsidiary, reached FID on the 2.8-bcfd Permian Link. Estimated cost of the project is $4.2-billion, of which KMI’s share is expected to be about $1.6 billion.
The 434-mile pipeline will serve new power generation for an A-rated hyperscaler and is supported by long-term, take-or-pay transportation agreements. NGPL expects to place the project in service third-quarter 2030, subject to required permits and approvals.
KMI also sanctioned the second and third phases of its Creekside Lateral project in central Texas, following execution of additional long-term, take-or-pay agreements with data center and industrial customers. The company has now contracted 750 MMcfd of the system’s 1.3-bcfd design capacity, with potential for future expansion to more than 2 bcfd. KMI expects to place the project in service in phases, beginning fourth-quarter 2026 and continuing throught fourth-quarter 2027, subject to permits and approvals.
SNG and Tennessee Gas Pipeline (TGP), meanwhile, took FID on the 10-bcf Bear Creek Storage Expansion project, to be used by TGP which has secured long-term binding agreements for the capacity. The extra capacity is expected to enter service in April 2029, subject to required permits and approvals.
Refined products, terminals
KMI’s Houston Ship Channel refined products hub moved 427,000 b/d across its 11 docks in third-quarter 2026, a 39% year-on-year increase and an all-time record for the site. The company attributed the record quarter to the worldwide shortage in refined product supplies and associated price dislocations and is advancing enhancements to in-tank blending capabilities for butane and other gasoline components.
Permitting and right-of-way acquisition also are progressing for two dedicated refined products pipelines connecting KMI’s Pasadena Terminal with a nearby major refinery. The $139-million project is backed by a long-term storage and volume commitment with a major national oil company and is expected to enter service third-quarter 2027.
KMI is also expanding its 1.5-million-bbl Kinder Morgan Export Terminal on the Houston Ship Channel. The $30-million project is supported by a long-term storage commitment with a major international trading company and is expected to be placed in service first-quarter 2027.
Earnings
The announcements and project updates were part of KMI’s third-quarter 2026 earnings reporting. The company reported net income attributable to KMI of $764 million, up nearly 22% from third-quarter 2025.