Land & Expand: North America’s Data Center Pipeline Expands Under Pressure

Land & Expand is Data Center Frontier’s periodic look at the latest data center development news, including new sites, land acquisitions and campus expansions across North America. This latest installment finds the development pipeline continuing to expand, even as the requirements for bringing large-scale projects online grow more complicated. Developers are securing land, planning new […]

Land & Expand is Data Center Frontier’s periodic look at the latest data center development news, including new sites, land acquisitions and campus expansions across North America.

This latest installment finds the development pipeline continuing to expand, even as the requirements for bringing large-scale projects online grow more complicated. Developers are securing land, planning new power infrastructure and advancing campuses measured in hundreds of megawatts or more. At the same time, local governments and residents are demanding greater clarity on electricity costs, water consumption, noise, tax incentives and the long-term effects of industrial-scale computing facilities.

A succession of development disclosures and project milestones through September and early October 2026 illustrates both the geographical reach of North America’s expanding data center pipeline and the growing difficulty of measuring how much proposed capacity will ultimately be delivered.

The projects range from preliminary discussions and newly secured development sites to campuses already under construction. Some are advancing through formal permitting and power studies; others remain contingent on customers, financing or local approvals. Together, they reveal an industry still expanding aggressively, but operating under increasingly complex development conditions.

Fluidstack: Cameron County, Texas — Up to 1.5 GW

One of the largest newly disclosed projects is Fluidstack’s AI data center development in Cameron County in the Rio Grande Valley. The project surfaced publicly September 10 when Cameron County announced that it had issued Fluidstack a worksite permit for property near Harlingen. The permit authorizes preliminary site work, including grading, utilities and related infrastructure, rather than construction of the data center buildings themselves.

Fluidstack subsequently disclosed considerably more detail on September 21, saying construction had begun on a $4 billion first phase capable of supporting as much as 1.5 GW.

Fluidstack expects the project to generate more than 2,500 construction jobs and several hundred permanent positions.  The company has placed unusual emphasis on the project’s local infrastructure impact. It says it requested no local property-tax abatements and intends to pay for the energy, water and infrastructure necessary to serve the campus. Cooling will use a recirculating closed-loop system.

At up to 1.5 GW in its announced first phase, Cameron County represents a major addition to the Texas AI development pipeline, reflecting the increasingly industrial scale of projects designed to support advanced computing.

Microsoft ATL50: Union City, Georgia

A new filing for Microsoft’s ATL50 campus entered Georgia’s Development of Regional Impact review process on September 15. Microsoft filed plans for ATL50, a new data center campus at 5235 Stonewall Tell Road in Union City, southwest of Atlanta. Plans call for two three-story data center buildings totaling approximately 910,000 square feet on 88 acres. The filing projects completion in 2032.

Microsoft already has a substantial Georgia footprint, with development activity in Fairburn, Douglasville, Palmetto, Rome, East Point and other communities. ATL50 represents another proposed campus in the greater Atlanta market rather than entry into a new region. No electrical capacity has been disclosed.

Project Gravel: Pima County, Arizona

Another proposed development emerged through public-records reporting rather than a corporate announcement. Documents obtained in September disclosed Project Gravel, an eight-building data center campus being evaluated on approximately 160 acres of vacant land in unincorporated Pima County west of Sahuarita, Arizona.

Plans show eight buildings of roughly 203,000 square feet each, producing a potential campus of approximately 1.6 million square feet, along with a dedicated electrical substation, roads and parking infrastructure. Project documents contemplate full buildout by 2029, contingent on the development advancing through the necessary approvals.

County staff had reportedly been evaluating the proposal for months before details became public. Neither the developer nor a prospective tenant has been publicly identified, and the planned electrical load remains undisclosed. The disclosure has already generated local concern: Residents gathered September 29 to discuss the project’s potential effects on water, energy use and the surrounding environment. Sahuarita officials subsequently clarified that the proposed site lies outside town boundaries, under Pima County jurisdiction.

Project Gravel also illustrates the difficulty in determining the true size of the U.S. development pipeline. Large sites can remain in engineering, environmental and land-use review for months before appearing in conventional industry announcements.

Gray Oak Power: Undisclosed South Texas Campus

Another visible development appeared September 25, although considerably less is known about it. Gray Oak Power disclosed that a South Texas data center campus had advanced through ERCOT’s Studied Load Batch Zero process. The company has not disclosed the community, tenant or ultimate campus capacity.

Advancement through ERCOT’s Studied Load Batch Zero process confirms that another large-load development is progressing through the Texas interconnection review system, although it does not represent final grid-connection approval. Gray Oak’s proposed strategy calls for the campus to begin operating with dedicated onsite generation, followed by a utility grid connection and the eventual ability to supply electricity back to the grid. The company targets initial power in 2028 and utility grid service in 2029. Until the location, electrical load and customer are disclosed, the project remains an early-stage development.

Lambda: Mayes County, Oklahoma

On September 27, AI cloud provider Lambda announced an entirely new data center at the MidAmerica Industrial Park in Mayes County, Oklahoma, near Chouteau.

Lambda has not disclosed either the capital cost or megawatt capacity of the facility, but expects development to support as many as 1,000 construction jobs and 100 permanent positions. The company estimates the project could produce approximately $500 million in taxes over its first decade at current rates.

Unlike many data center announcements of several years ago, Lambda’s disclosure immediately addressed electricity costs and water consumption. The company says it will pay the full cost of the energy and infrastructure required to serve the facility, consistent with Oklahoma’s Data Center Customer Ratepayer Protection Act. Lambda also plans to use closed-loop cooling to reduce water consumption and is examining ways to shift or reduce certain computing workloads during periods of peak grid demand.

Google/Crusoe: Armstrong County, Texas

One of September’s most consequential disclosures concerned a project already well into construction. Google had announced plans for an Armstrong County data center in November 2025, but on September 28, Crusoe identified itself as the developer of the Google AI campus outside Amarillo. Crusoe said construction began in June 2025 and that more than 5,500 skilled workers were now on site daily.

The campus has direct connections to Serena’s adjacent 265.5 MW Goodnight 1 wind farm and the 265.5 MW Goodnight 2 project now under construction. Crusoe says excess wind generation can flow to the grid when production exceeds campus requirements. Neither Google nor Crusoe has disclosed the full electrical capacity of the data center campus. Those generation figures should not be confused with the data center’s electrical load, which has not been publicly disclosed.

The disclosure illustrates how construction can advance well beyond the initial project announcement before the full development structure becomes public. It also reflects the growing importance of colocating AI infrastructure with large-scale energy resources.

Clean Cloud Energy: Mahomet, Illinois

Illinois offered a different illustration of the pressures shaping data center development. On September 28, the Village of Mahomet disclosed that Clean Cloud Energy had approached the community about a potential data center campus on rural property west of Champaign. Discussions were preliminary but had advanced to include draft language for a possible development agreement. No formal project capacity or investment amount had been announced.

Those discussions came to an abrupt end. On October 5, the village announced that it would no longer pursue the development opportunity with Clean Cloud Energy, citing extensive public opposition. Residents had raised concerns about proximity to homes, noise, lighting, infrastructure requirements and potential impacts on the Mahomet Aquifer. Village President Jason Tompkins said community feedback had played a significant role in the decision not to proceed.
Mahomet provides a counterpoint to the larger projects advancing elsewhere.

The village’s decision ended its negotiations with the developer, although it does not establish that Clean Cloud Energy has abandoned broader development ambitions in the region. It also demonstrates that community opposition is no longer simply a public-relations challenge. In some jurisdictions, it can decisively alter the development process before formal permitting begins.

Zone Frontier: Potter County, Texas — 200 MW to 500+ MW

Zone Frontier announced a 30-year ground lease covering approximately 4,077 acres in Potter County, Texas, including land that could support as much as 800 acres of data center development.

The initial concept is approximately 200 MW, with the potential to expand beyond 500 MW. At least 1,800 acres could be used for solar generation, battery storage and associated energy infrastructure. The company has also secured a long-term water agreement. The property also surrounds Southwestern Public Service Company’s existing 345 kV Potter County substation, which Zone Frontier identifies as a potential route to grid interconnection alongside its proposed onsite generation resources.

Zone Frontier has not yet secured a tenant, and construction remains contingent on customer commitments, permitting, power arrangements and financing. The lease establishes substantial site control, not a committed construction schedule. Nevertheless, securing more than 4,000 acres with an envisioned development path beyond 500 MW places Potter County firmly within the emerging hyperscale development pipeline.

Beyond the Initial Disclosures: North America’s Development Pipeline Widens

The latest development news extends well beyond the projects disclosed during September. Across North America, hyperscalers and infrastructure developers are advancing additional campuses, expanding power commitments and exploring new regional markets. The activity ranges from redevelopment of former industrial properties to sovereign AI infrastructure and entirely new greenfield projects.

AWS Details 36-Building Plan at Pennsylvania’s Homer City

In Pennsylvania, additional details have emerged about Amazon Web Services’ proposed campus at the former Homer City coal-generating station. An October 6 report described AWS’s preliminary land-development plan for 36 data center buildings spread across approximately 1,100 acres in Indiana County, divided among six development areas.

The proposed buildings would each encompass approximately 225,000 square feet, with construction proceeding in four phases. Under the submitted schedule, work could begin in December 2026, with the final phase starting in 2032 and overall completion targeted for 2036. The proposal also includes electrical substations, supporting infrastructure and redundant generation.

As DCF previously reported, Homer City Redevelopment is building a multigigawatt natural-gas generating complex at the former coal plant site, with AWS positioned as a prospective principal power customer. The power development is already under construction, while AWS’s data center plans remain subject to the applicable land-use and construction approvals.

The newly detailed building program underscores the scale of the transformation: A retired coal-generation complex could become a long-term, integrated power and computing campus, provided the development and generation timelines converge.

Bell Expands Saskatchewan AI Ambitions Toward 1.2 GW

Canada’s emerging AI infrastructure market produced another major development in September when Bell Canada and the Government of Saskatchewan announced a nonbinding agreement to explore up to 900 MW of additional capacity for Bell AI Fabric.

The proposed expansion would build on Bell’s previously announced 300 MW campus near Regina, creating a potential 1.2 GW AI infrastructure hub. The company says total investment associated with a full buildout, including data centers, tenant computing equipment and related power generation, could exceed C$50 billion.

The additional capacity is expected to depend on partner-developed natural-gas generation, while Bell says its proposed facilities will use closed-loop cooling without municipal water requirements. Expansion timing will depend on securing customer commitments.

The significance extends beyond the capacity figure. Bell is positioning Saskatchewan as a center of Canadian-controlled AI infrastructure, reflecting the growing importance of data sovereignty alongside power availability and computing scale. However, the additional 900 MW remains a development objective under a nonbinding agreement, not committed operating capacity.

TeraWulf Accelerates Kentucky’s Muskie Campus Toward 1 GW

In eastern Kentucky, TeraWulf announced October 5 that it had expanded its contracted power arrangements with Kentucky Power for the Muskie Data Campus from 500 MW to 1 GW.

The amended agreements also accelerate the proposed second 500 MW phase from 2030 to 2029. The first phase remains targeted to begin ramping in 2028, while the revised second-phase schedule depends on Kentucky Public Service Commission approval and the utility’s construction timetable.

Unlike an early-stage land acquisition, Muskie’s latest development milestone concerns the amount and timing of contracted electrical service. That distinction matters as developers increasingly compete to establish credible schedules for delivering large blocks of power to AI infrastructure customers.

The amendment does not mean the full gigawatt is available today. It does, however, mark a substantive step in transforming an announced campus into a phased development with defined utility-service arrangements.

Mexico: Cuasar Targets 300 MW in Durango

Mexico’s data center development pipeline is also extending beyond its established concentration in Querétaro.

Cuasar Capital, associated with Spain’s EOSOL group, and infrastructure developer KA URBE IT have announced a partnership to market a proposed AI-oriented data center campus in Durango. The principal facility, DC Norte Uno, is designed for 300 MW of total capacity, including approximately 250 MW of IT load, on a 20-hectare site.

A second proposed facility, DC Norte Dos, would provide approximately 7.74 MW for edge computing and industrial applications. The developers are positioning the campus around high-density AI workloads and connectivity routes linking Durango with established Mexican and cross-border digital infrastructure markets.

The project remains at an early development and commercialization stage. Nevertheless, its proposed scale illustrates how AI infrastructure demand is encouraging developers to explore Mexican markets beyond the country’s existing hyperscale clusters.

Ontario: A 400 MW Proposal Confronts Local Planning Questions

In Sault Ste. Marie, Ontario, Algoma Steel and Red Jar Energy Partners have discussed a potential 400 MW AI data center development, illustrating another approach to converting established industrial locations into digital infrastructure.

The parties have sought an early position in Ontario’s Independent Electricity System Operator connection process to evaluate the feasibility of the project. An October 2029 operating date has been discussed, but the companies have not announced a binding construction commitment.

Municipal planning presents another obstacle. Sault Ste. Marie’s council moved toward preparing an interim-control bylaw that could pause data center development while the city establishes a local regulatory framework.

The proposal therefore remains preliminary. Its significance lies partly in the opportunity to reuse industrial infrastructure, and partly in the challenge of reconciling large new electrical loads with provincial grid planning and municipal approval requirements.

Google Explores New Mexico’s Lea County

Google is considering a new data center development in Lea County, New Mexico, potentially establishing its first self-built data center in the state.

In a September 14 announcement, the company acknowledged that discussions were underway but declined to provide a precise site, proposed electrical capacity or development schedule. Instead, Google emphasized early public engagement, responsible water management and commitments to cover the energy and infrastructure costs required by the project.

Lea County’s location along the Texas border places the potential development within a broader Southwest corridor attracting increasingly large investments in computing and energy infrastructure.

At this stage, Google’s interest represents market exploration rather than a committed construction project. It is nonetheless another indication that hyperscale site selection is moving into regions beyond the industry’s traditional development centers.

Additional Projects to Watch: Filings, Expansions and Capacity Milestones

A further group of developments illustrates how much activity is moving through permitting, construction and utility planning outside the industry’s largest headline announcements.

Project Longhorn, Bastrop County, Texas: An October filing identifies a proposed $366 million first data center building in Cedar Creek, encompassing approximately 498,000 square feet. The broader development has been linked in reporting to a proposed gas-fired power complex capable of supporting approximately 490 MW of IT load. Anthropic has been identified as a possible tenant in related reporting, but its participation has not been confirmed. The filing supplies a more concrete development marker than the previously reported tenant discussions.

Microsoft, Prince William County, Virginia: Microsoft has filed plans for the MNZ07 Wellington Data Center, consisting of two single-story buildings and an onsite substation on approximately 123 acres near Gainesville. The proposal includes federal environmental review because of potential impacts on wetlands and streams. It represents additional hyperscale development in Northern Virginia even as local governments tighten rules governing where new campuses can be built.

Skybox and Prologis, Hutto, Texas: The partners have filed plans for Skybox Hutto 4, an approximately 846,300-square-foot building with a reported development cost of $550 million. The fourth facility would become the largest building proposed at their PowerCampus development, which is targeting 600 MW of IT capacity across the broader site.

Applied Digital, Ellendale, North Dakota: Not every milestone concerns proposed capacity. Applied Digital announced that another 75 MW of critical IT load had reached ready-for-service status at its CoreWeave-leased Polaris Forge 1 campus. The milestone brings completed campus capacity to 250 MW, toward a planned 400 MW full buildout. This is a more tangible measure of deployment progress than an early-stage site announcement.

ThisWay Global, Bryan, Texas: A proposed 73 MW Research and AI Compute Center at Texas A&M-RELLIS would provide computing infrastructure for research, government and industry users. Planned for phased development on approximately 25 acres, the project would use direct-to-chip liquid cooling and remains subject to the necessary approvals.

Taken together, these additional developments reinforce the central distinction emerging across North America. Some developers are acquiring land or introducing proposals; others are securing power agreements, advancing environmental reviews or completing facilities capable of serving customers. The pipeline continues to grow, but the distance between an announced megawatt and an operational one remains a defining measure of development progress.

The Pipeline Grows Under Closer Scrutiny

These development disclosures arrive amid intensifying scrutiny of the industry’s expansion. On July 18, opponents organized 142 demonstrations across 42 states in a coordinated national protest of data center development. A Reuters/Ipsos survey published in June found that only about one-third of Americans supported the rapid pace of construction, while just 14% said they would welcome a data center in their own community.

The pressure continued into September. On September 15, Loudoun County, Virginia, supervisors voted to consider a resolution that could pause final action on certain data center and electrical substation applications requiring legislative approval for up to 12 months. The resolution is scheduled for consideration October 20. In Chicago, Mayor Brandon Johnson introduced a proposal for a one-year moratorium on permits and approvals for new or expanded data centers while city officials study their power, water and community impacts. Neither action represented an enacted moratorium as of October 12.

The pressure continued into September.  Loudoun County, Virginia voted September 15 to develop a process that could pause final action on certain new data center and substation applications for as long as 12 months while the county rewrites its policies. Chicago Mayor Brandon Johnson has proposed a 12-month moratorium on new data centers within the city while officials study their power, water and community impacts.

Yet the flow of development announcements continues. What has changed is the level of scrutiny that accompanies them. New project disclosures increasingly address ratepayer protection, closed-loop cooling, onsite generation, water availability and infrastructure financing alongside investment, construction schedules and job creation. Those commitments reflect an industry adjusting to the realities of developing power-intensive infrastructure at unprecedented scale.

The emerging distinction is between securing a development opportunity and demonstrating that it can be delivered. Land, electrical capacity, financing, permitting and community acceptance are increasingly interdependent requirements. As the latest projects illustrate, the North American data center pipeline remains substantial, but the path from proposed campus to operating infrastructure is becoming more demanding.

Shape
Shape
Stay Ahead

Explore More Insights

Stay ahead with more perspectives on cutting-edge power, infrastructure, energy,  bitcoin and AI solutions. Explore these articles to uncover strategies and insights shaping the future of industries.

Shape

It’s not your model — AI has a data movement problem

But that can be the wrong lever. When you examine the full end-to-end transaction, the model usually isn’t the problem. Take the extraordinary scale of AI traffic as it moves from a branch office to a centralized security stack, then to a cloud region, then to a data-hosted backend somewhere

Read More »

Ørsted builds compliance into automation, speeds firewall changes

Taking on a firewall process One process Ørsted initially targeted for automation was firewall rule management. In the past, an internal customer submitted a firewall request through ServiceNow, and a network security engineer reviewed the request, checking IP addresses, fully qualified domain names, and directory groups. Depending on the type,

Read More »

Middle East supply risks overshadow Russian diesel deal

Escalating security risks in the Middle East are keeping oil markets on edge, with renewed attacks on Saudi Arabia and commercial vessels near the Strait of Hormuz, raising concerns over regional crude exports. The developments have overshadowed US President Donald Trump’s announcement of additional Russian diesel supplies and a proposed Russia-Ukraine energy ceasefire. Oil prices rose more than 2% on Oct. 12, with Brent climbing to $107/bbl and US West Texas Intermediate (WTI) reaching $93.7/bbl. Both benchmarks hit their highest levels since Sept. 29, reversing earlier losses. The gains followed renewed attacks on Saudi Arabia and commercial shipping in the Gulf region. Yemen’s Iran-aligned Houthi movement claimed responsibility for a Saturday strike on Riyadh’s international airport, while additional attacks were reported Sunday. Separately, a tanker was struck by a drone near Sohar, Oman, and another vessel was damaged while transiting the Strait of Hormuz, according to the United Kingdom Maritime Trade Operations agency (UKMTO). The incidents have renewed concerns over further disruption to shipping through the Strait of Hormuz, threatening the recovery in Middle East crude exports recorded in September. Goldman Sachs raised its December Brent price forecast to $90/bbl from $85/bbl, citing an estimated geopolitical risk premium of slightly more than $20/bbl. “We maintain our base case that continued adaptation of Mideast supply will eventually reduce crude oil prices, while potential renewed escalation still poses significant net upside risk,” Goldman Sachs said in a note Oct. 11. Russian diesel deal, energy ceasefire Trump announced on Oct. 9 an agreement with Russian President Vladimir Putin to increase diesel supplies to the US and international markets. Trump said Russia would initially supply more than 300,000 tonnes of diesel, followed by 500,000 tonnes in November and 1 million tonnes thereafter. The US Treasury Department also authorized certain Russian diesel transactions under a

Read More »

Energy Department Authorizes Strategic Petroleum Reserve Exchange to Address Supply Disruptions Due to Hurricane

WASHINGTON—The U.S. Department of Energy (DOE) today announced the authorization of an emergency exchange of up to 4 million barrels of crude oil from the Strategic Petroleum Reserve (SPR) to address supply disruptions due to inclement weather in the Gulf of America. Under the terms of the exchanges, participating companies will return the borrowed crude oil with additional premium barrels in 2027, helping replenish and strengthen the SPR at no additional cost to taxpayers.  “With this emergency exchange, the Energy Department is acting swiftly to help maintain refinery operations, limit disruptions to fuel supplies, and ensure American families and businesses continue to have access to affordable, reliable, and secure energy” said U.S. Secretary of Energy Chris Wright. “In addition to helping minimize supply disruptions, these emergency exchanges will also require Exxon and BP to return more barrels to the Reserve than are currently being withdrawn, saving taxpayers millions of dollars. Rest assured, the Trump Administration is committed to strengthening America’s energy security at every opportunity.” The Department has authorized exchanges of up to 2 million barrels each for ExxonMobil and BP America. ExxonMobil’s exchange will accelerate deliveries of previously awarded SPR crude oil to address immediate supply needs.  DOE will continue working with industry partners to support reliable fuel supplies and respond to hurricane-related disruptions.  For more information about the Strategic Petroleum Reserve, visit energy.gov.

Read More »

Energy Department Supports FERC’s Call for PJM to Protect Ratepayers and Build More Reliable Power

WASHINGTON—The U.S. Department of Energy (DOE) announced its support for the Federal Energy Regulatory Commission’s (FERC) guidance that would help ensure lower electricity costs for American families and businesses across the PJM Interconnection LLC’s (PJM) region spanning across the mid-Atlantic. DOE filed a Notice of Intervention and Statement of Position with FERC supporting its recommendation for PJM’s proposed Reliability Backstop Procurement. FERC recommends PJM submit revised tariff provisions to implement appropriate cost allocation and other reforms. FERC’s recommendations are consistent with President Trump’s Ratepayer Protection Pledge, ensuring large electricity users pay for the generation and infrastructure needed to serve them.  This action follows the Trump Administration’s call in January 2026 for PJM to adopt market rules to strengthen grid reliability and reduce electricity costs. Specifically, the Administration asked PJM to hold an emergency power auction and to accelerate the development of reliable power generation. The Trump administration was joined by governors from all 13 states who participate in the PJM grid. “The Trump Administration remains committed to doing everything it can to lower electricity costs, grow the supply of American energy and strengthen grid reliability,” said U.S. Secretary of Energy Chris Wright. “That’s why President Trump created the Ratepayer Protection Pledge, and the Energy Department supports having large electricity users pay for reliable new power generation.” “In January, the Trump Administration recognized early warning signs of capacity shortfalls in PJM and joined the Governors of all 13 PJM states in issuing a Statement of Principles to PJM, calling for PJM to adopt market rules to strengthen grid reliability and reduce electricity costs for American families and businesses,” said U.S. Deputy Secretary of Energy James P. Danly. “By increasing transparency and preventing unjust cost shifts onto existing customers, the proposed reforms advance President Trump’s Ratepayer Protection Pledge while ensuring Americans continue

Read More »

Shell agrees to acquire interest in Bay du Nord project

Shell plc and Equinor ASA have signed an agreement under which Shell will acquire a 30% interest in the Bay du Nord project offshore Newfoundland and Labrador in Canada. Equinor will retain a 70% interest and remain as the operator of the project. The transaction supports the continued maturation of Bay du Nord towards an investment decision currently targeted for early 2027, Equinor said. Bay du Nord is in Flemish Pass basin, about 500 km offshore Newfoundland and Labrador in 600–1,170 m of water. The development concept is based on a floating production, storage, and offloading vessel (FPSO). Bay du Nord and Cambriol discoveries are included in the initial phase, with potential future subsea tiebacks to Cappahayden, Harpoon, and Baccalieu. Estimated recoverable resources in the initial phase are more than 400 MMbbl of oil. First oil is anticipated in 2031, Equinor said. The project is currently finalizing front-end engineering and design (FEED), with continued work focused on strengthening capital efficiency, execution planning, and overall project robustness. Engagement with provincial and federal governments has supported progress through key milestones, according to the company. Equinor and Shell said they will continue to mature the project towards an investment decision subject to market conditions, regulatory approvals, and the companies’ internal decision processes. The project will require a toal investment of about $14 billion (Can.; US$12.6 billion), Equinor said.

Read More »

Dangote taps EIL for Kenya grassroots refinery project

Dangote Group has enlisted Engineers India Ltd. (EIL) to deliver project management and engineering, procurement, and construction management (EPCM) services for subsidiary Dangote East Africa Petroleum Refinery & Petrochemicals SEZ’s proposed 700,000-b/d grassroots integrated refinery and petrochemical complex to be built in Mokowe, Lamu County, Kenya. As part of the more than $450-million contract, EIL will serve as project management consultant (PMC) and EPCM consultant for the project, the service provider said in separate regulatory filings to BSE Ltd. and The National Stock Exchange of India Ltd. The proposed complex is planned near Lamu Port and the Lamu Port-South Sudan-Ethiopia Transport (LAPSSET) corridor, which will connect the site with inland and regional markets by providing a coastal location for importing construction materials and crude as well as exporting refined products. EIL said award of the PMC-EPCM consultancy contract for the Lamu refinery follows its previous role as PMC-EPCM consultant for Dangote Petroleum Refinery and Petrochemicals FZE (DPRP) 650,000-b/d refinery and petrochemical complex in the Lekki Free Zone near Lagos, Nigeria, which is currently being expanded to 1.4 million b/d. At a Sept. 30 groundbreaking ceremony for the Lamu refinery, Dangote described the $16-billion investment as a project aimed at expanding refined-product supply in East Africa that will serve markets both within and beyond Kenya. While the refinery will presumably process Kenya’s production of domestic crude such as volumes from South Lokichar basin—which could which could begin production before December 2026 at a rate of about 20,000 b/d—the integrated complex also will process crude sourced from other African producers, including Uganda, the African Export-Import Bank (Afreximbank) said in a release Oct. 1. Honeywell to license technologies The EIL contract joins a separate $300-million contract awarded to Honeywell Technologies for delivery process technology and related services at Lamu, including technology licensing, engineering

Read More »

Energy Department Announces New Genesis Mission Awards to Advance Super Intelligence for Science

WASHINGTON—The U.S. Department of Energy (DOE) today announced 12 Phase II Genesis Mission project awards totaling $159 million. Building on the Genesis Mission’s growing portfolio of projects, first announced in July, these Phase II project awards will unleash scientific discoveries with Super Intelligence (SI). President Trump launched the Genesis Mission in November 2025 to accelerate discovery and strengthen U.S. leadership in science, medicine, and technology. “These projects represent a critical step in turning the promise of Super Intelligence for science into transformative scientific capability,” said DOE Under Secretary for Science Dr. Darío Gil. “The Phase II teams have already demonstrated what is possible when SI is integrated with scientific expertise, data, and computing. These awards give them the opportunity to take that work to the next level. By bringing together our National Labs, universities, and industry partners, we are building on extraordinary work already underway and accelerating the pace of discovery.” The Phase II awards are developing new, powerful capabilities to tackle the Nation’s most complex National Science and Technology Challenges. By connecting America’s leading scientists with advanced SI, supercomputing, scientific data, and DOE’s world-class research infrastructure, the Genesis Mission is strengthening U.S. leadership at the frontiers of science and technology. Awarded Projects Through DOE’s Office of Science, the 12 newly awarded projects are: Accelerating the path to commercial fusion energy via an AI-enabled digital twin platform for SPARC: Led by Commonwealth Fusion Systems, this project will build a digital twin to simulate and optimize operations of a fusion demonstration device.  Decoding the RNA Structurome to Secure AI Advantage for the Bioeconomy: Led by the University of California San Diego, the project will expand the RNA structure database five-fold for training SI models to unlock the ability to engineer resilient crops and sustainable microbes.  Lattice Quantum Chromodynamics (LQCD) at the

Read More »

Land & Expand: North America’s Data Center Pipeline Expands Under Pressure

Land & Expand is Data Center Frontier’s periodic look at the latest data center development news, including new sites, land acquisitions and campus expansions across North America. This latest installment finds the development pipeline continuing to expand, even as the requirements for bringing large-scale projects online grow more complicated. Developers are securing land, planning new power infrastructure and advancing campuses measured in hundreds of megawatts or more. At the same time, local governments and residents are demanding greater clarity on electricity costs, water consumption, noise, tax incentives and the long-term effects of industrial-scale computing facilities. A succession of development disclosures and project milestones through September and early October 2026 illustrates both the geographical reach of North America’s expanding data center pipeline and the growing difficulty of measuring how much proposed capacity will ultimately be delivered. The projects range from preliminary discussions and newly secured development sites to campuses already under construction. Some are advancing through formal permitting and power studies; others remain contingent on customers, financing or local approvals. Together, they reveal an industry still expanding aggressively, but operating under increasingly complex development conditions. Fluidstack: Cameron County, Texas — Up to 1.5 GW One of the largest newly disclosed projects is Fluidstack’s AI data center development in Cameron County in the Rio Grande Valley. The project surfaced publicly September 10 when Cameron County announced that it had issued Fluidstack a worksite permit for property near Harlingen. The permit authorizes preliminary site work, including grading, utilities and related infrastructure, rather than construction of the data center buildings themselves. Fluidstack subsequently disclosed considerably more detail on September 21, saying construction had begun on a $4 billion first phase capable of supporting as much as 1.5 GW. Fluidstack expects the project to generate more than 2,500 construction jobs and several hundred permanent positions. 

Read More »

DCF Global: Five Markets Redrawing the AI Infrastructure Map

The Global Constraint Is Execution These five markets demonstrate that the worldwide AI infrastructure buildout is no longer organized around a single development model. Spain is using permitting reform to attract investment. China is concentrating construction around energy resources. India is translating enormous capital commitments into an expanding development pipeline. Latin America is combining hyperscale growth with national industrial objectives. And Southeast Asia is creating interconnected infrastructure markets whose boundaries increasingly extend beyond individual cities and countries. Not every market is competing for the same business. Sovereign cloud services, enterprise applications, AI training clusters, and large-scale inference platforms carry different requirements involving power, connectivity, latency, data residency, and operating economics. But the infrastructure questions remain remarkably consistent. Can a project obtain enough electricity? Can transmission and supporting networks be delivered on schedule? Will the supply chain provide the required equipment? Can the facility be constructed and commissioned efficiently? And will the development retain the regulatory certainty and community acceptance required to operate for decades? The gap between announced development and actual capacity is becoming a defining measurement of the industry. Cushman & Wakefield estimates that Asia-Pacific alone had approximately 26.5 GW of data center capacity in its development pipeline during H1 2026. Of that total, roughly 4.8 GW was under construction, with another 21.7 GW in planning. Those figures reveal both the extraordinary scale of the opportunity and the considerable infrastructure work still required to realize it. What the Global Buildout Means for North America For U.S. data center operators, developers, engineering firms, equipment suppliers, and investors, international expansion is not a separate story. It is increasingly part of the same global competition for capital, equipment, power infrastructure, and specialized expertise. The transformers, switchgear, generators, advanced cooling systems, fiber networks, and electrical distribution equipment required by a major AI campus

Read More »

Bidding war over key component could eliminate third hard disk maker

What if the three remaining hard disk manufacturers became two? Seagate Technology and Western Digital control 90% of the market, according to market researcher TrendForce, with Toshiba picking up the crumbs. Seagate and WD both make their own magnetic drive heads, but Toshiba relies on a third party, TDK, which also sells to Seagate and WD when they need extra capacity. Seeking to guarantee supplies of this critical component, Toshiba made a bid for TDK’s drive head business earlier this year, according to Bloomberg. Concerned that this could affect its ability to meet the growing demand for hard disks from AI data centers, Seagate made a counteroffer, Bloomberg reported. TDK is staying mum.

Read More »

Oracle reportedly lands $7B GPU deal for Tencent

Oracle has reportedly signed a five-year, $7 billion agreement to provide Chinese technology conglomerate Tencent with access to roughly 100,000 advanced AI accelerators deployed in Oracle data centers across Southeast Asia, helping Tencent to sidestep restrictions on advanced AI equipment.  The deal, first reported by the Financial Times, would represent Tencent’s largest overseas cloud commitment with a U.S. provider. Neither Oracle nor Tencent has publicly confirmed the agreement or disclosed the specific AI processors involved. Under the reported terms, Tencent would pay about 30% of the contract value upfront—roughly $2.1 billion—with the remainder paid over the five-year term. That would give Oracle a substantial source of upfront funding for the expensive data center infrastructure required to build out the infrastructure.

Read More »

NVIDIA’s DSX Ready Brings Power and Cooling Into the AI Factory Blueprint

NVIDIA is extending its influence over AI infrastructure beyond the GPU, server rack and network, introducing qualification requirements for the power and cooling systems that increasingly determine the scale and performance of AI data centers. The company’s new NVIDIA DSX Ready program, announced September 21, establishes requirements for specific infrastructure products intended for use with NVIDIA’s DSX AI factory reference designs. Its first two categories—battery energy storage systems (BESS) and coolant distribution units (CDUs)—address two of the most pressing engineering challenges in AI infrastructure: managing rapidly changing electrical demand and removing heat from increasingly dense computing systems. The initial qualified suppliers are Hitachi Energy, LG Energy Solution and Tesla for battery storage, and LG Electronics, LiquidStack and Vertiv for liquid cooling. While the announcement might initially resemble another NVIDIA partner program, its technical details suggest something more consequential. The company is establishing performance criteria for the electrical and mechanical equipment supporting its computing platforms, connecting those requirements to an expanding ecosystem of qualified suppliers. Subsequent partner announcements offer a clearer view of what that means in practice. They describe battery systems designed to respond to AI load fluctuations, coolant distribution equipment operating at multi-megawatt capacities, and integrated cooling architectures intended to make more of a data center’s available power usable for computing. The initiative also coincides with the arrival of Chris Malone, formerly a data center infrastructure executive at OpenAI, Meta and Google, as NVIDIA’s vice president of the DSX Platform. Together, the developments point toward a closer relationship between computing architecture and facility engineering, with NVIDIA seeking to influence not only the processors deployed in AI factories but the infrastructure requirements that support their operation. From Reference Design to Infrastructure Qualification DSX Ready is an extension of the broader NVIDIA DSX AI Factory Platform, introduced in May 2026. As

Read More »

Brookfield’s AREP Deal Extends the AI Infrastructure Stack to Powered Land

The transaction goes beyond Brookfield investing in another portfolio of buildings. It is investing in a developer whose principal product increasingly begins before the building, with land, entitlements, substations, transmission access and utility capacity. PowerHouse Has Become a Gigawatt-Scale Development Platform PowerHouse was founded with a strong Northern Virginia orientation, but its development map now stretches well beyond Data Center Alley as its current portfolio includes projects in Virginia, Texas, Pennsylvania, North Carolina, Nevada, Indiana, Illinois and Kentucky. The company lists 515 MW across its Northern VA Ashburn properties, another 900 MW at its PH 95 development in Spotsylvania, 1.35 GW in Carlisle, Pennsylvania, 1.8 GW at Joliet, Illinois, and substantial campuses across multiple Texas and Indiana locations. The various projects do a good job of illustrating how the definition of a hyperscale development site is changing. At PowerHouse Arcola in Loudoun County, Virginia, PowerHouse announced a long-term hyperscale lease earlier this year. The 37-acre campus includes two planned data center buildings totaling approximately 615,000 square feet and is designed for up to 120 MW of utility capacity. PowerHouse emphasizes not only the buildings but the campus’s on-site substation, fiber access, power security and support for high-density GPU and liquid-cooled deployments. In Texas, it might be that everything really is bigger, and PowerHouse’s Grand Prairie development covers approximately 810 acres and 8.5 million developable square feet. Its project page cites maximum utility power of 1.8 GW and a development schedule extending through 2029 and beyond. The Texas development plans also include a proposed Circle T campus in Westlake outside Fort Worth, which calls for as many as four roughly 300,000-square-foot facilities totaling approximately 300 MW. According to reporting on local filings, PowerHouse has funded a 350-MW Oncor substation intended to serve the campus and the town’s pump station. The company’s development in

Read More »

Microsoft will invest $80B in AI data centers in fiscal 2025

And Microsoft isn’t the only one that is ramping up its investments into AI-enabled data centers. Rival cloud service providers are all investing in either upgrading or opening new data centers to capture a larger chunk of business from developers and users of large language models (LLMs).  In a report published in October 2024, Bloomberg Intelligence estimated that demand for generative AI would push Microsoft, AWS, Google, Oracle, Meta, and Apple would between them devote $200 billion to capex in 2025, up from $110 billion in 2023. Microsoft is one of the biggest spenders, followed closely by Google and AWS, Bloomberg Intelligence said. Its estimate of Microsoft’s capital spending on AI, at $62.4 billion for calendar 2025, is lower than Smith’s claim that the company will invest $80 billion in the fiscal year to June 30, 2025. Both figures, though, are way higher than Microsoft’s 2020 capital expenditure of “just” $17.6 billion. The majority of the increased spending is tied to cloud services and the expansion of AI infrastructure needed to provide compute capacity for OpenAI workloads. Separately, last October Amazon CEO Andy Jassy said his company planned total capex spend of $75 billion in 2024 and even more in 2025, with much of it going to AWS, its cloud computing division.

Read More »

John Deere unveils more autonomous farm machines to address skill labor shortage

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More Self-driving tractors might be the path to self-driving cars. John Deere has revealed a new line of autonomous machines and tech across agriculture, construction and commercial landscaping. The Moline, Illinois-based John Deere has been in business for 187 years, yet it’s been a regular as a non-tech company showing off technology at the big tech trade show in Las Vegas and is back at CES 2025 with more autonomous tractors and other vehicles. This is not something we usually cover, but John Deere has a lot of data that is interesting in the big picture of tech. The message from the company is that there aren’t enough skilled farm laborers to do the work that its customers need. It’s been a challenge for most of the last two decades, said Jahmy Hindman, CTO at John Deere, in a briefing. Much of the tech will come this fall and after that. He noted that the average farmer in the U.S. is over 58 and works 12 to 18 hours a day to grow food for us. And he said the American Farm Bureau Federation estimates there are roughly 2.4 million farm jobs that need to be filled annually; and the agricultural work force continues to shrink. (This is my hint to the anti-immigration crowd). John Deere’s autonomous 9RX Tractor. Farmers can oversee it using an app. While each of these industries experiences their own set of challenges, a commonality across all is skilled labor availability. In construction, about 80% percent of contractors struggle to find skilled labor. And in commercial landscaping, 86% of landscaping business owners can’t find labor to fill open positions, he said. “They have to figure out how to do

Read More »

2025 playbook for enterprise AI success, from agents to evals

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More 2025 is poised to be a pivotal year for enterprise AI. The past year has seen rapid innovation, and this year will see the same. This has made it more critical than ever to revisit your AI strategy to stay competitive and create value for your customers. From scaling AI agents to optimizing costs, here are the five critical areas enterprises should prioritize for their AI strategy this year. 1. Agents: the next generation of automation AI agents are no longer theoretical. In 2025, they’re indispensable tools for enterprises looking to streamline operations and enhance customer interactions. Unlike traditional software, agents powered by large language models (LLMs) can make nuanced decisions, navigate complex multi-step tasks, and integrate seamlessly with tools and APIs. At the start of 2024, agents were not ready for prime time, making frustrating mistakes like hallucinating URLs. They started getting better as frontier large language models themselves improved. “Let me put it this way,” said Sam Witteveen, cofounder of Red Dragon, a company that develops agents for companies, and that recently reviewed the 48 agents it built last year. “Interestingly, the ones that we built at the start of the year, a lot of those worked way better at the end of the year just because the models got better.” Witteveen shared this in the video podcast we filmed to discuss these five big trends in detail. Models are getting better and hallucinating less, and they’re also being trained to do agentic tasks. Another feature that the model providers are researching is a way to use the LLM as a judge, and as models get cheaper (something we’ll cover below), companies can use three or more models to

Read More »

OpenAI’s red teaming innovations define new essentials for security leaders in the AI era

Join our daily and weekly newsletters for the latest updates and exclusive content on industry-leading AI coverage. Learn More OpenAI has taken a more aggressive approach to red teaming than its AI competitors, demonstrating its security teams’ advanced capabilities in two areas: multi-step reinforcement and external red teaming. OpenAI recently released two papers that set a new competitive standard for improving the quality, reliability and safety of AI models in these two techniques and more. The first paper, “OpenAI’s Approach to External Red Teaming for AI Models and Systems,” reports that specialized teams outside the company have proven effective in uncovering vulnerabilities that might otherwise have made it into a released model because in-house testing techniques may have missed them. In the second paper, “Diverse and Effective Red Teaming with Auto-Generated Rewards and Multi-Step Reinforcement Learning,” OpenAI introduces an automated framework that relies on iterative reinforcement learning to generate a broad spectrum of novel, wide-ranging attacks. Going all-in on red teaming pays practical, competitive dividends It’s encouraging to see competitive intensity in red teaming growing among AI companies. When Anthropic released its AI red team guidelines in June of last year, it joined AI providers including Google, Microsoft, Nvidia, OpenAI, and even the U.S.’s National Institute of Standards and Technology (NIST), which all had released red teaming frameworks. Investing heavily in red teaming yields tangible benefits for security leaders in any organization. OpenAI’s paper on external red teaming provides a detailed analysis of how the company strives to create specialized external teams that include cybersecurity and subject matter experts. The goal is to see if knowledgeable external teams can defeat models’ security perimeters and find gaps in their security, biases and controls that prompt-based testing couldn’t find. What makes OpenAI’s recent papers noteworthy is how well they define using human-in-the-middle

Read More »